Installing the Mixer:
Mixers are installed at site itself or suitably at central place, respectively called as site mixing and central mixing. The choice between the two depends upon various factors, like as accessibility, availability of working space, water supply, transportation routes, etc. As far as possible, mixer should be installed close to the concreting site and at firm and leveled ground. Before starting the mixing operation, cleanliness of mixer should be ensured.