Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Explain hardness - water softening, Explain Hardness - Water Softening ...

Explain Hardness - Water Softening 1) Hardness is used to characterize a water that does not lather well, causes a scum in the bath tub and leaves hard, white, crusty deposits

Concrete, What practical steps can one take to mitigate the adverse effects...

What practical steps can one take to mitigate the adverse effects in using aggregates with higher than specified flakiness index in the production of concrete

Obstacles, Obstacles which can be ranged

Obstacles which can be ranged

Significance of tailwater level in culverts, Significance of tailwater leve...

Significance of tailwater level in culverts Headwater level and tailwater level of culverts are significant parameters in hydraulic design. Headwater level can't be set too la

Jacking face for pipe-jacking, Ground settlement occurs ahead or behind the...

Ground settlement occurs ahead or behind the jacking face for pipe-jacking? It's reported by Lake (1992) that settlements are expected at ground surface at a distance of 1-2 ti

Softening test point, the importance of softening point of a bitumen materi...

the importance of softening point of a bitumen material in the design of a pavement

Define the shock transmission unit, Define the Shock Transmission Unit? ...

Define the Shock Transmission Unit? Ever since engineers have started designing multi span simply supported bridges, they have been dreaming of connecting all the spans togethe

Chain surveying, Chain Surveying: In the chain surveying, you have stu...

Chain Surveying: In the chain surveying, you have studied the basics of chain surveying. In chain surveying, various equipment and instruments are used for measuring distances

Define equipments required for conducting uwmt, Define Equipments required ...

Define Equipments required for conducting UWMT? Equipments required for conducting UWMT are: Inspection Equipment: a) Electronic yoke with power cable b) Ground fault interr

Define friction pendulum bearing, Define Friction Pendulum Bearing? In ...

Define Friction Pendulum Bearing? In friction pendulum bearings, the lateral displacement is permitted at the interface of the bearing element between the superstructure and th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd