Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Explain the aashto classification system, Explain the AASHTO Classification...

Explain the AASHTO Classification System   1.  Identify the percent passing the No.10, No. 40, and No. 200 sieves. Identify the LL and PI of the fraction passing the No. 40 sie

How do you determine specific gravity of cement, Cement is usually purchase...

Cement is usually purchased as a powdery substance that is mixed with sand, aggregate, gravel, and water to form concrete. As the cement itself is usually a powder, it is hard to c

Explain damage inspections - underwater inspection of bridge, Explain the D...

Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Water-bound macadam road construction for unpaved roads, how can I come up ...

how can I come up with the research on the water bound macadam road construction

What is shock transmission unit in bridges, Q. What is Shock transmission u...

Q. What is Shock transmission unit in bridges? Shock transmission unit is fundamentally a device connecting separate structural units. It's characterized by its ability to tran

Lifting of girders, Q. Lifting of girders? Lifting of girders : For gre...

Q. Lifting of girders? Lifting of girders : For greasing the bearings girders are required to be lifted. But the gap between the bottom flange of plate girders and the bed bloc

Explain about differential settlement, Q. Explain about Differential settle...

Q. Explain about Differential settlement? Structural stability is not very much affected by uniform settlement of a structural system. Major amount of damages will be taking pl

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Scale., how many scale are there and what are they use

how many scale are there and what are they use

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd