Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Civil Engineering Technology, Why hoisting and conveying equipment is very ...

Why hoisting and conveying equipment is very important in civil engineering?

Define non-destructive inspection of concrete substructures, Define Non-des...

Define Non-destructive inspection of Concrete Substructures? If there is evidence of significant deterioration, then a Level III inspection, involving either non-destructive or

Highway, what is the difference between bitumin and asphalt

what is the difference between bitumin and asphalt

Survey, Methods of orientation,Principles of resection

Methods of orientation,Principles of resection

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

Building construction drawings, I need a drawing detail of expansion joints...

I need a drawing detail of expansion joints in building and different sizes

Routing maintenance and major maintenance, What is the difference between r...

What is the difference between routing maintenance and major maintenance in school facilities? Ans) The routine maintenance is the minor and consistent repairs that are engaged

Uses of medain mode and mean, what is the uses of mean mode and medain in c...

what is the uses of mean mode and medain in civil engineering

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd