Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Differences between pipe jacking and micro-tunnelling, Q. Differences betwe...

Q. Differences between pipe jacking and micro-tunnelling? Pipe jacking is a general scheme of installation of pipes with a tunnelling shield in front and the pipes are jacked f

WMM, what is wmm what are all the uses of that wmm

what is wmm what are all the uses of that wmm

Two pegs test, the distance between two pegs M and N is 7,063 as measured o...

the distance between two pegs M and N is 7,063 as measured on a slope. the height measured on the pegs are that M=1.814M and N=0.5687M

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Design the transverse shear reinforcement, Details of a simply-supported be...

Details of a simply-supported beam are given in Figures (a) and (b). Note that the dead load, g includes the self weight. Design the transverse shear reinforcement in ter

Explain bridge selection criteria - underwater inspection, Explain the Brid...

Explain the Bridge Selection Criteria - Underwater inspection? Various factors influence the bridge selection criteria. As a minimum, all structures must receive routine underw

Stabilization of Black Cotton soil, How the stabilization of black cotton ...

How the stabilization of black cotton soil was done in field? what are the methods to do that?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd