Q. Write short notes on Abrasion Test?
The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.
The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted. The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')
The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.
The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).
The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.
Q. Write briefly for Trolley Permits? It is the permit given to the Moter Trolley / Push Trolley, Cycle / Moped Trolley. It is essential to have Trolley Permit before taking t
friction circle method of stability of slope
working from whole to part
The state of stress at a point is given through the stress components sx = 70 MPa, sy = 10 MPa, and txy = - 40 MPa. Using Mohr''s circle find (i) Principal stresses, and (ii) Princ
Retardation of fresh concrete has numerous benefits as below: (i) A rapid hydration process leads to loss in concrete strength since concrete will have a poorer structure with
Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed
describe with neat sketch the process of manufacturing of cement in the modern factory by dry process
pentavalent will be added impurity
Ask question laws of sollid friction #Minimum 100 words accepted#
Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd