Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Designing of pipe jacking, Question While designing of pipe jacking , ...

Question While designing of pipe jacking , what particular areas on pipe joints have to engineers make sure of? Answer While in pipe jacking, jacked pipes may well ha

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Define well steoning, Q. Define Well Steoning? It is the side wall of w...

Q. Define Well Steoning? It is the side wall of well foundation. It is built of masonry or cement concrete not less than M 10 grade, sufficient bond rods should be provided to

Surveying, 3 types of obstacles in chaining detail

3 types of obstacles in chaining detail

Compaction, describe how quality control is maintained in a rolled fill dam...

describe how quality control is maintained in a rolled fill dam

How to calculate the dry density and void ratio, A moist soil sample compac...

A moist soil sample compacted into a mould of 1000 cm 3 capacity and weight 35 N, weighs 53.5 N with the mould. A representative sample of soil taken from it has an initial weight

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

Rb slab, #questionshow me picture..

#questionshow me picture..

Explain the dynamic or vibration tests, Explain the Dynamic or Vibration Te...

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd