Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Differentiate, differentiate between components and resolved parts

differentiate between components and resolved parts

Road and traffic engineering(signal timing design), what are the basic assu...

what are the basic assumption of traffic flow model and capacity model used in signal timing design ? discuss

Examine the state of stress at the junction of flange, Examine the state of...

Examine the state of stress at the junction of flange: A beam of I-section as shown in Figure (a) is subjected to a bending moment of 84.928 kN m and a shear force of 106.1 kN

Construction of concrete carriageway, Question If construction of conc...

Question If construction of concrete carriageway is carried out in summer, be capable of expansion joints be omitted? Answer If construction of concrete carriageway

Determine the viscosity of water, A soil sample consists of particles rangi...

A soil sample consists of particles ranging in size from 0.6 mm to 0.02 mm. The average exact gravity of the particles is 2.66. Verify the time of settlement of the coarsest and fi

Preparation for underwater inspection - tool and equipment, Preparation for...

Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req

The material that have lowest resistivity is , The material that have lowes...

The material that have lowest resistivity is Answer: Silver is the material

Neglecting bearing at the tip of the piles, A square pile group of 9 piles ...

A square pile group of 9 piles of 25 cm diameter is arranged with a pile spacing of 1m. The length of the piles is 9 m. Unit cohesion of the clay is 75 kN/m 2 . Neglecting beari

Surveying, description of instruments used transfer upper floors *plumb-bob...

description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd