Write short notes on abrasion test, Civil Engineering

Assignment Help:

Q. Write short notes on Abrasion Test?

The abrasion test for ballast shall be carried out using Los-Angeles machine.The abrasive charge shall consist of 12 nos. cast iron or steel spheres approx. 48mm dia and each weighing between 390 and 445 gm ensuring total weight of charge as 5,000 ± 25 gm.

The test sample of 10000gm shall consist of clean ballast conforming to the following grading :- Passing 50mm and retained on 40 mm square mesh sieve 5,000 gm and Passing 40 mm and retained on 25mm square mesh sieve 5,000 gm tolerance of ± 2% permitted.

The sample shall be dried in oven at 100 - 110 °C to a constant weight and weighed (Weight 'A')

The test sample and the abrasive charge shall be placed in the Los-Angeles abrasion testing machine and the machine rotated at a speed of 20 - 33 revolutions/minute for 1000 revolutions. At the completion of test, the material shall be discharged and sieved through 1.70mm IS sieve.

The material coarser than 1.70 mm IS sieve shall be washed, dried in oven at 100-110°C to a constant weight and weighed (weight B).

The proportion of loss between Weight "A" and Weight "B" of the test sample shall be expressed as a percentage of the original weight of the test sample. This value shall be reported as: Aggregate Abrasion Value =((A-B)/A)X100.


Related Discussions:- Write short notes on abrasion test

Angle&direction, whate does mean bearing?with example

whate does mean bearing?with example

Designing of roadbase material, Question In General Specification for C...

Question In General Specification for Civil Engineering Works, designing of roadbase material is based on recipe approach. Give reason. Answer Designing of roadbase

Chemical classification of stones, Chemical Classification On the basis...

Chemical Classification On the basis of their chemical composition engineers prefer to classify  rocks as: 1.    Silicious rocks 2.    Argillaceous rocks 3.    Calcare

Construction material, 4. Calculate the loose volume of material needed to ...

4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench

Foundation, The strap serves the same purpose as the interior portion of a ...

The strap serves the same purpose as the interior portion of a combined footing but is much narrower to save materials. ? The resultant soil pressure is assumed at the centers of b

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

Two property rule , The state of a pure substance of given mass is defined ...

The state of a pure substance of given mass is defined by specifying two appropriate properties provided that 1. The system is in equilibrium 2. Gravity, motion, electricity,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd