What is unitary method, Mathematics

Assignment Help:

Explanation of  Unitary Method

Unitary Method keeps of following two steps:- 

    Step 1 involves find the value of one unit. 

    Step 2 involves find the value of required units. 

Below are some examples explaining Unitary Method. 

Example A 5 buses carry 200 passengers. How many passengers can 20 buses carry ? 

Answer = The process is as :- 

    Step 1 = Calculate how many passengers 1 bus carry : 

To find this, we have to divide the given number of passengers(200) by given number of buses(5) because one bus will carry less passengers as compared to 5 buses 

5 buses carry passengers = 200 

1 bus carry passengers = 200 ÷ 5     = 40 

Step 2 = Determine how many passengers 20 bus carry : 

To find, we have to multiply the necessary number of buses(20) with number of passengers one bus can carry(40) because more buses will carry more passengers. 

1 bus carry passengers = 40 

5 buses carry passengers = 40 × 20     = 800. 

 

Alternative Method 

Above mentioned method is so long. Once you understand the concept of Unitary Method, you can directly apply this method in following ways :- 

5 buses carry passengers = 200 

1 bus carry passengers = (200 ÷ 5) 

20 bus carry passengers = (200 ÷ 5) × 20     = 40 × 20     = 800. 

Example 2 = 5 worker can complete a work in 20 days. In how many days same work will be completed if 10 workers are employed. 

Answer = The process is as :- 

    Step 1 = Find in how many days 1 worker will do the given work. 

To find this, we have to multiply the given worker(5) with given number of days(20) because one worker will take more days to complete the given work as compared to 5 workers. 

5 workers complete the given works in days = 20 

1 worker complete the given works in days = (20 × 5)     = 100 

Step 2 = Find in how many days 10 worker will do the given work. 

To find this, we have to divide numbers of days in which 1 worker will complete(100days) by the required number of workers(10) because more men complete given work in lesser days. 

1 worker complete the given works in days = 100 

10 workers complete the given works in days = (100 ÷ 10)     = 10 

Alternative Method 

Above mentioned method is long. Once you understand the concept of Unitary Method, you can directly apply this method in following ways :- 

5 workers complete the given works in days = 20 

1 worker complete the given works in days = (20 × 5) 

10 workers complete the given works in days = (20 × 5) ÷ 10     = 100 ÷ 10     = 10


Related Discussions:- What is unitary method

ALGEBRA, FIND PRODUCT (-41)*(102)

FIND PRODUCT (-41)*(102)

Partial derivatives, So far we have considered differentiation of functions...

So far we have considered differentiation of functions of one independent variable. In many situations, we come across functions with more than one independent variable

Find the shortest paths in the digraph, 1. a) Find the shortest paths from ...

1. a) Find the shortest paths from r to all other nodes in the digraph G=(V,E) shown below using the Bellman-Ford algorithm (as taught in class).  Please show your work, and draw t

Explain that odd positive integer to be a perfect square, Show that for odd...

Show that for odd positive integer to be a perfect square, it should be of the form 8k +1. Let a=2m+1 Ans: Squaring both sides we get a2 = 4m (m +1) + 1 ∴ product of two

Applications of de moiver, what are the applications of de moiver''s theore...

what are the applications of de moiver''s theorem in programming and software engineering

Determine matrix of transformation for orthogonal projection, Determine the...

Determine the matrix of transformation for the orthogonal projection onto the line L that passes through the origin and is in the direction Û=(3/13 , 4/13 , 12/13). Determine the r

Probability that a leap year will have 53 sunday?explain, A leap year has 3...

A leap year has 366 days, therefore 52 weeks i.e. 52 Sunday and 2 days. The remaining 2 days may be any of the following : (i) Sunday and Monday (ii) Monday and Tuesday (iii)

Explain set intersection, Q. Explain Set Intersection? Ans. Set I...

Q. Explain Set Intersection? Ans. Set Intersection Suppose your school needs to know which students are taking both art and business this year. If A is the set of studen

What is median number of tries it took these participante, The operator of ...

The operator of an amusement park game remain track of how many tries it took participants to win the game. The subsequent is the data from the ?rst ten people: 2, 6, 3, 4, 6, 2, 8

Compound interest, some experts estimate that the cost of education in the ...

some experts estimate that the cost of education in the US increases by 6% p.a. An Ivy League college currently costs $24,502 for one year''s study today. Using compound interest r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd