What is the station at Point B?

70_What is the station at Point B.png

SOLUTION 3

Station at Point A = Sta 22+45 

Station at Point B = (Sta 22+45) + 1028' = 2245'+1028' =3273' 

= Sta 32+73


Related Discussions:- What is the station at point b

Types of cement, Types of Cement In addition to ordinary Portland ceme...

Types of Cement In addition to ordinary Portland cement there are various varieties of cement. Significant varieties are briefly explained below: (i) White Cement: The ce

Mr Kamal Saxena, What is WBM road. How it is constructed?

What is WBM road. How it is constructed?

What is n-value of standard penetration test, Define and discuss the variou...

Define and discuss the various factors that help decide the number and depth of bore holes needed for subsoil exploration. What is 'N-value' of Standard Penetration Test? How do

Designing sewer pipes, Question While designing sewer pipes , why vitr...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Draw sketch for track in a cutting on a mainline route, Q. Draw a neat dim...

Q. Draw a neat dimensioned cross-sectional sketches of a - i. New single Line B.G. track in a cutting on a mainline route. ii. New double Line B. G. track on a trunk route ha

Explain about differential settlement, Q. Explain about Differential settle...

Q. Explain about Differential settlement? Structural stability is not very much affected by uniform settlement of a structural system. Major amount of damages will be taking pl

Cavities under structures., This is the title for my thesis for masters in ...

This is the title for my thesis for masters in structural engineering. Is it possible to make for me the literature review? I already have my references.

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

Earth fill dams, Ask question #Minimum 100E. The regulations and specificat...

Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd