What is the probability of having more units in the system, Operation Management

Assignment Help:

1. Consider a single-line, single-server waiting line system. Suppose that there is only physical space for 2 units in the system (one in line and one being served). The arrival rate is 80 people per hour. The manager, Johnny Three Toes, has the choice among workers of different speeds to be the server. He wants to save money by hiring the slowest server that will result in an average number of units in the system (L) equal to 2.

a) Using Johnny Three Toes strategy, what will the server service rate per hour need to be?

b) What is the probability of having 3 or more units in the system?

c) What is wrong with Johnny Three Toes strategy?


Related Discussions:- What is the probability of having more units in the system

Explain unobtrusive surveillance, What legitimates intruding into others li...

What legitimates intruding into others lives' through unobtrusive surveillance, through market research, or by whatever means?

Explain organizations need to calculate a threshold, Why do organizations n...

Why do organizations need to calculate a threshold for a reorder? How could this affect sales?

Explain network technologies to gain a competitive advantage, 1. How could ...

1. How could Denver B-cycles use other wired or wireless network technologies to gain a competitive advantage? 2. What Information not described in the case can Denver B-cycle u

Explain what is the probability that you will make money, The owner of Fire...

The owner of Firewood-2-Go is considering buying a hydraulic wood splitter which sells for $50000. He figures it will cost an additional $80 per cord to purchase and split wood wit

Siting departments for process layout - manufacturing, Siting Departments f...

Siting Departments for Process Layout - Manufacturing One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even

What impacts are there if any of the project team is leftout, There are 3 m...

There are 3 main components to the systems implementation process, which are, organizing the team, determining project scope and expectations and establishing a project plan. Each

Define the minimum and maximum cycle times, An assembly line with 11 tasks ...

An assembly line with 11 tasks is to be balanced. The longest task is 2.7 minutes, the shortest task is 0.4 minutes, and the sum of the task times is 18 minutes. The line will oper

Explain cat5 utp with segments that use fibber optic cable, What kind of ro...

What kind of router could connect network segments that use CAT5 UTP with other segments that use fibber optic cable?

Practice Question.., 4. (32 points) You and your roommate are planning to o...

4. (32 points) You and your roommate are planning to open “Pizza In The Dorm” to make and distribute fresh pizza from your dorm room. You plan to provide 100% fresh, high quality p

Explain web-based appraisal systems, What do you think are the pros and con...

What do you think are the pros and cons of using a web-based appraisal systems?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd