The 3M incorporate produces solar cell panels, and the production rate can be 8,000 pieces per day. The demand for the solar panel is 30,000 pieces per month. The fixed cost of setting up a production run is $1,500. The variable cost of production is $100 per item. The holding costs are based on 25% annual interest rate. Assume there are 250 working days a year.
a) What is the optimal size of production run for this kind of solar cell panel?
b) what proportion of each production cycle consists of uptime and what proportion consists of downtime?
Process Technology Life Cycle Process technologies have life cycles related to product life cycles as shown in figure below. Over time unit manufacturing costs diminish for ma
What is queuing theory in operation management? Queuing theory is usually seems a branch of operations management since the results can be used to plan for resources require
What are the advantages and disadvantages for a U.S.-based company entering a mature market economy?
Discuss the long-run consequences of your decision.
Cunningham Performance Auto, Inc., modifies 375 autos per year. The manager, Peter Cunningham, is interested in obtaining a measure of overall performance. He has asked you to prov
Explain tech theme for smartphones. Give some examples
Explain Job Evaluation. A combination of short statements which describe both the necessary requirements of the particular job and the work to be performed is termed as Job Eva
A system program that combines the separately compiled modules of a program into a form suitable for execution A. assembler B. linking loader C. cross compiler D. load
Hatten (2009) discusses the of credit. What are they and how do lenders use them? As you consider the possibility of being an entrepreneur, which of the 5 Cs is most important for
1. What kind of warning signals would you like fed back from PAC to MRP? 2. Lead times are sometimes called rubbery. What accounts for this concept of elasticity in lead times?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd