What is the estimated cost of the whole project, Project Management

Assignment Help:

Question 1:

(a) Using information from Table 1, build a network diagram for the project.

(b) Perform a Forward Pass on the network diagram and deduce the duration of the project.

(c) What is the estimated cost of the whole project?

(d) Perform a Backward Pass on the network diagram and deduce the float for each task.

(e) What can you say about flexibility in the project in the light of the above?

Question 2:

(a) What is the rationale behind earned value analysis in project monitoring and how is it helpful?

(b) Using information in Table 2, calculate the schedule variance and cost variance for each task in the project at timenow 30 days

(c) In light of calculations above, comment on the progress of the project with respect to the schedule. What is the expected duration of project if started (but incomplete) tasks continue on the same trend and if tasks which have not started yet proceed as per schedule?

(d) In light of calculations above, what is the expected cost of the project now?

(e) What corrective action would you recommend at this stage of the project?


Related Discussions:- What is the estimated cost of the whole project

Describe master service agreement, Problem 1: Is closing of a clinical ...

Problem 1: Is closing of a clinical trial as important as initiation? Justify your answer with suitable examples. Difference between closing of a clinical trial and initi

Cause-orientated organisations, Non-political, not-for-profit, cause-orient...

Non-political, not-for-profit, cause-orientated organisations drawn from more than one country are known as  Non-governmental organisations (NGOs).

Production management, what do you understand by the term analystical metho...

what do you understand by the term analystical methods of production

Program management process , Define the concept of Program Management Proce...

Define the concept of Program Management Process  As we learnt in the previous section Program?s process depends mostly on the characteristics of the product/service offered by

Project management plan of Reverse osmosis plant, Scope Work breakdown str...

Scope Work breakdown structure Gantt chart Scope cchange management Project budget Project ccash flow

Determine elapsed time of critical path, Determine elapsed time of critical...

Determine elapsed time of critical path when The critical path is given by points BCFG and the elapsed time 17 weeks. There D can over running by up to 3 weeks without

Balancing efficiency, Balancing Efficiency An efficient line balancing...

Balancing Efficiency An efficient line balancing will minimize the amount of idle time.  The balance efficiency can be calculated as Eff B = output of task time / in

How to measures defect ratios for the product, Defects found after product ...

Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio

Production and purchasing management, A) Hierarchical planning in Operation...

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

Essential pre-requisites of a grievance procedure, Problem 1: Show the ...

Problem 1: Show the essential pre-requisites of a grievance procedure. Essential pre-requisites of a grievance procedure Problem 2: What are the objectives of Trade

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd