Q. What is Chamfering of rail?

Chamfering of rail holes has been done for the life of rail hole is increased and chances of the rail hole developing any crack is eliminated.

To operate the equipment chamfering bits are fixed on either side of the hole of the rail with the help of bolt and packing pieces. The torque is set on the torque wrench to a valve of 370 Lbs ft for 52 kg rails. The nut is then tightened progressively till the designed torque is reached and the torque wrench slips. The nut bolt arrangement is then unscrewed and the equipment is back in normal position.

The manufacturer claim that time taken for chamfering the hole is only about 1½ minute.


Related Discussions:- What is chamfering of rail

Deflectin of beam, simply supported beam with point load at the centre

simply supported beam with point load at the centre

Vacancy for teaching?, I am a civil engineer and interested to teach.Is the...

I am a civil engineer and interested to teach.Is there any vacancy?

Asphalt mix design – durability and stability, Q. Asphalt mix design - dura...

Q. Asphalt mix design - durability vs. stability? The main aim of asphalt mix design is to achieve a mix with economical blending of aggregates with asphalt to achieve the foll

Timer, grading classification

grading classification

PORTAL FRAME, EXPLAIN SITUATION OF THE PORTAL FRAME CAN CAUSE SWAY WITH THE...

EXPLAIN SITUATION OF THE PORTAL FRAME CAN CAUSE SWAY WITH THE AID OF A DIGRAM

Arches, construction of arches

construction of arches

What is function of mortar in brick walls, Q. What is Function of mortar in...

Q. What is Function of mortar in brick walls? A distinctive brick wall structure generally comprises the subsequent components:  (i)  Coping on top of the brick wall to prot

# bnm.l/j, what does oxymoron mean

what does oxymoron mean

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd