What is a feasibility study, Civil Engineering

Assignment Help:

In order to make wise investments in a marketplace experiencing enhancing levels of risk, companies are turning to feasibility studies to verify if they should offer new products, services or undertake a new business endeavour. The purpose of a feasibility study is to verify if a business opportunity is possible, practical, and viable. When faced with a business opportunity, many optimistic people tend to focus on just the positive aspects.

A feasibility study enables a realistic view at both the positive and negative aspects of the opportunity. A feasibility study is a significant tool for making the right decisions. A wrong decision often leads to business failure. For example, only 50% of start-ups are still in business after 18 months and only 20% are in business after 5 years.

 


Related Discussions:- What is a feasibility study

Steel truss 15 m span, types of truss of 15 m cantilever with 1000 kg on fr...

types of truss of 15 m cantilever with 1000 kg on free end. May be steel or any lightest material aluminium anodized truss. thanks

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Position of shear keys under retaining walls, Installation of shears keys a...

Installation of shears keys assists to increase sliding resistance of retaining walls without the necessity to widen the base. Effect of shears keys enhances the deepening of the s

Show method of greasing, Method of Greasing : Greasing of fixed end require...

Method of Greasing : Greasing of fixed end requires 20 to 25 minutes. The lifting is hardly 10 mm, ensuring that the gap is created between saddle block and knuckle pin. Saddle is

Distortion energy theory, Distortion energy theory: Let us now conside...

Distortion energy theory: Let us now consider the solid shown in Figure. (a)        By inspection we may see that the solid is safe according to principal stress theor

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Water treatment, what is filtration membrane, is it''s type mechanism

what is filtration membrane, is it''s type mechanism

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd