Q.What do you mean by Slip Siding?

If the Station yard is in a gradient steeper than 1 in 260 or there is a continuous falling gradient away from the station there is a possibility of vehicles standing in the yard entering or escaping into the block section and cause accidents to prevent such escaping of vehicles into the block section slip siding are provided.

At a station where there is a gradient 1 in 100 falling away from the station within 45 meters beyond the outer most points at either end a slip siding should be provided.

As per the schedule of dimensions no station yard should be constructed nor should any siding join a passenger line on a steeper grade than 1 in 260 except where it is unavoidable and then only with the previous sanction of the railway board obtained through the commissioner of Railway safety when a slip siding is made sufficient prevent accident.


Related Discussions:- What do you mean by slip siding

Define pavement design - transportation, Define Pavement Design - Transport...

Define Pavement Design - Transportation 1. Asphalt surface a. Estimate Design Traffic b. Determine the Structural Number (SN) for the given traffic, roadway, and soil cha

Define limitations of radiography - inspection of bridge, Define Limitation...

Define Limitations of Radiography - Underwater Inspection of Bridge? i. Radiography is a costly and time consuming method, which re- quires extensive safety measures to be adop

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Determine the value of the coefficient of permeability, Determine the value...

Determine the value of the coefficient of permeability A glass cylinder 5 cm internal diameter with a screen at the bottom is used as a falling head permeameter. The thickness

Practice to form washout regulators, Question Why are two gate regulato...

Question Why are two gate regulators necessary in regular practice to form washout regulators ? Answer In fact, situation is analogous to that of fire hydrants in tha

Track structure on broad gauge, Q. What is the minimum prescribed track str...

Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge? Ans.- 1. General - The minimum length of LWR depends upon - i. Range of temporary variati

Handheld inspection tool for underwater inspection of bridge, Explain Handh...

Explain Handheld Inspection tools for Underwater Inspection of Bridge? Handheld tools such as flash lights, rulers, and tape measures for documenting areas; small or large hamm

Write important factors that affect permeability of a soil, Determine the i...

Determine the important factors that affect the permeability of a soil. A permeameter of 8.2 cm diameter having a sample of soil of length 35 cm. It can be used either for const

Major considerations in selecting marine plants, Question What are majo...

Question What are major considerations in selecting marine plants and land plants for fitting of band drains? Answer For fitting of band drains by marine plants,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd