Q. What do you mean by Shell and Tube Exchangers?
Shell and tube exchanger piping shall be arranged to provide clearance overhead at both bonnet and channel ends. Piping shall be designed with breakout spools at both bonnet and channel ends to enable removal by overhead lifting equipment. Sufficient space should be provided for the removal of tube bundles from shell and tube heat exchangers for maintenance, inspection or replacement.
Horizontal shell and tube exchangers can be stacked two or three high. If larger exchangers need to be stacked more than two high a structure should be considered with each shell separately supported. The following are rules of thumb for stacking:
• 1.2 m in diameter Stacked three high
• 1.2 to 1.8 m in diameter Stacked two high
• Over 1.8 m in diameter Shall not be stacked
Fixed tube shell exchangers require a clear space for in-situ roding out, or tube replacement. Where removal of tube bundles is specified, space should be provided for a crane or proprietary tube pulling equipment. Check the type of bundle pulling method used by the plant. The bundle removal area should not extend over main plant roads, although plot space can be saved if this is allowed by the Client. Shell and tube exchangers in structures need good access to both channel and rear end and may require lifting beams and lay down areas for channel head removal. This requirement must be checked for, early in the design.
Determine the parameter - Larson-Miller parameters: Larson-Miller parameters for an alloy at tests levels 10 MP a and 30 MP a are determined respectively as 18 × 10 4 and 1
Lubrication Complaints If the engine oil level is too low, check for the following things: External oil leaks Worn out piston rings Worn out valve guide and/o
what is the gt?
Q. Application of cold service insulation? Cold insulation shall be installed specifically in accordance with the Manufacturer's recommendations, and generally as outlined belo
A Perspex tank ure 1), which has parallel sides for the top part of its height and a 'V' shaped section for the bottom part and a constant width throughout, is used as a receptacle
Q. Steam Generator Piping? Control valves shall be Fisher or Purchaser-approved equal. All valves shall be detailed by size, rating, make, model number, and materials Two
Volume fraction of fibres: The epoxy material is prepared to be stressed to its full strength. What must be volume fraction of fibres? Solution Here σ′ = 1200 MPa,
explain
working
calculate the head required
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd