What do you mean by depth of scour, Civil Engineering

Assignment Help:

Q. What do you mean by Depth of Scour?

The maximum scour depth in a stream can be ascertained when ever possible by actual sounding at or near the site proposed for the bridge during or immediately after a flood. Before the scour holes have had time to silt up due to allowance should be made in the observed depth for increase in scour resulting from-

  1. The designed discharge being greater than the flood discharge during which the scour was observed.
  2. The increase in velocity due to the obstruction in flow caused by construction of the bridge.

Where the above practical method of determining scour is not possible the following theoretical method may be used as a guide when dealing with natural streams is alluvial beds.      

D = 0.473 [ Q / F ]? 

Where D = Depth of scour below HFL for regime conditions in a stable channel in meters.

           Q = Design discharge in cumecs.  

           F= Silt factor = 1.76 √m , m is the mean diameter of particles in mm.


Related Discussions:- What do you mean by depth of scour

Explain standard penetration test used in soil exploration, Explain the "St...

Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio

Simply calculation, If i want to find D, and D=2a, then a=1-5 how can i s...

If i want to find D, and D=2a, then a=1-5 how can i show the ans is:2&4&6&8&10

Show the functions of sleepers in railway, Q. Show the Functions of sleeper...

Q. Show the Functions of sleepers in railway? Functions of sleepers in railway works are as below:  (i)  The primary function of a sleeper is to grip the rail to gauge and t

Determine about the tensile stresses, Determine about the tensile stresses ...

Determine about the tensile stresses Unifody prestressed members designed for equal flexure in opposite directions,without permitting tensile stresses under working loads, requ

Maintenance of concrete roads, Maintenance of Concrete Roads: The mai...

Maintenance of Concrete Roads: The main defects that show up in a concrete road are : (a) cracks (b) loss of sealant (c) spalling at joints (d) loss of texture

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Mapping, how to understand maps easily?

how to understand maps easily?

Pcc, Specific Gravity & Water Absorption of Fine Aggregate

Specific Gravity & Water Absorption of Fine Aggregate

Determine the active thrust on the wall by culmann method, A retaining wall...

A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the

Unsymmetrical bending, An 8 kN.m moment is applied at the end of a block fi...

An 8 kN.m moment is applied at the end of a block fixed into the ground as illustrated in thefigure below. The moment vector (double arrow head representation) acts in line with th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd