What are rules for working of dip lorries, Civil Engineering

Assignment Help:

Q. What are rules for working of Dip lorries and their protection arrangements on a single line section explain with sketches?

Ans.-Rules for working of Dip lorries -

i. Subject to their being certificate comp lent the all inspectors of engineering and signal and tele communication departments are permitted to us Dip lorri.

ii. No Railway servant shall use a lorry unless he is in a possession of a permit.

iii. The permit will only be issued after examined and valid for a period of one year.

iv. Each Lorry must have marked on it the number designation and code initials of the HQ.

v. Whenever lorry be placed on P.F. for loading on a train it should be placed paralleld to the Track.

vi. Lorry shall always be pushed and not pulled.

vii. When ever a lorry has to work within station section the PWI will advise the station master in writing.

viii. A lorry may be worked with out block protection when the PWI before putting a lorry on the line has as certained from the station master on duty.

ix. When the PWI intents to place the lorry on the line in mid section he shall issue a message on field telephone to the Station Master.


Related Discussions:- What are rules for working of dip lorries

Calculation of deformation, Calculation of deformation For calculation ...

Calculation of deformation For calculation of deformation at some stage before the total creep is reached,  it may be assumed that about half the total creep takes place  in  f

Estimation of discharge, Estimation of Discharge: The estimation of d...

Estimation of Discharge: The estimation of discharge of a stream is necessary for determining the waterway, clearance and foundation details. Discharge is estimated from :

What is diamond crossing, Q. What is Diamond Crossing? Diamond Crossing...

Q. What is Diamond Crossing? Diamond Crossing is provided when two tracks cross each other either of the same gauge or of different gauges. It consists of two acute crossing (

Reason of skin reinforcement for deep beams, Question What is reason of sk...

Question What is reason of skin reinforcement for deep beams ? Answer In BS8110, it declares that secondary reinforcement have to be provided for beams greater than 750mm deep

Present worth of an infinite series of annual amount, The construction of a...

The construction of a new bakery requires the property development firm to pay the municipality the cost to expand its sewage treatment plant. In addition to the expansion costs, t

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd