Q. What are rules for working of Dip lorries and their protection arrangements on a single line section explain with sketches?

Ans.-Rules for working of Dip lorries -

i. Subject to their being certificate comp lent the all inspectors of engineering and signal and tele communication departments are permitted to us Dip lorri.

ii. No Railway servant shall use a lorry unless he is in a possession of a permit.

iii. The permit will only be issued after examined and valid for a period of one year.

iv. Each Lorry must have marked on it the number designation and code initials of the HQ.

v. Whenever lorry be placed on P.F. for loading on a train it should be placed paralleld to the Track.

vi. Lorry shall always be pushed and not pulled.

vii. When ever a lorry has to work within station section the PWI will advise the station master in writing.

viii. A lorry may be worked with out block protection when the PWI before putting a lorry on the line has as certained from the station master on duty.

ix. When the PWI intents to place the lorry on the line in mid section he shall issue a message on field telephone to the Station Master.


Related Discussions:- What are rules for working of dip lorries

Raport, CASTE DISCRIMANIMATION

CASTE DISCRIMANIMATION

Angle measurment, calculating included angle and bearing

calculating included angle and bearing

Chain surveying, Chain Surveying: In the chain surveying, you have stu...

Chain Surveying: In the chain surveying, you have studied the basics of chain surveying. In chain surveying, various equipment and instruments are used for measuring distances

Two layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures   The level of damage in spatial trusses has also been classified into three different levels based on the t

State the increase in earth pressure at rest, A wall with a smooth vertical...

A wall with a smooth vertical back and 9 metres high retains a moist cohesionless soil with a horizontal surface. The soil weighs 15 kN/m3 and has an angle of internal friction of

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

Simple stresses and strains, SIMPLE STRESSES AND STRAINS: The concepts...

SIMPLE STRESSES AND STRAINS: The concepts of strain, stress, elastic modulus & the basic concepts in application to analysis of deformation and stresses in simple solids. Any

Track design for line speed improvements, The objective of this module is:-...

The objective of this module is:- For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibil

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd