What are probable solutions to rectify the situation, Civil Engineering

Assignment Help:

Question

If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?


Answer

(i) Option 1 - Complete Removal of All Disturbed Mud
To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.

(ii) Option 2 - Accelerated consolidation of Disturbed Mud
This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.

(iii) Option 3 - Partial Removal of Disturbed Mud
This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.

 


Related Discussions:- What are probable solutions to rectify the situation

Define the arrow diagramming method, Define the Arrow Diagramming Method ...

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on

Calculate the modulus of elasticity of concrete, Calculate the Modulus of e...

Calculate the Modulus of elasticity of concrete A pre-stressed concrete beam, having a cross-section of 150 mm width and 400 mm depth, is used over a span of 8 m. Straight tend

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Briefly explain the concept of wind-driven ventilation, Problem (a) Br...

Problem (a) Briefly explain the concept of wind-driven ventilation and outlines its benefits over mechanical/electrical means of ventilation. (b) Various factors and guidel

Calculate the equivalent uniform annual cost, A contractor purchased an exc...

A contractor purchased an excavator for $100,000. The life expectancy is 10-years. With the annual interest rate at 7%, the annual cost for the excavator is most nearly: Solutio

Building material, what is grillege foundation and where are use

what is grillege foundation and where are use

Elaborate the term - prestressed concrete pipes, Elaborate the term - Prest...

Elaborate the term - Prestressed concrete pipes Liquid retaining structures, such as circular pipes, tanks and pressure vessels are suited for circular prestressing. The circum

Show the benefits of adopting marine fill, In reclamation involving large v...

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?  There are two

Rolling - binder, Rolling - Binder: The layer thickness is 40-50 mm. R...

Rolling - Binder: The layer thickness is 40-50 mm. Rolling is done in three stages : Initial Rolling By 80-100 kN smooth wheeled roller. Intermediate Rolling B

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd