Verify the magnification and transmitted force, Civil Engineering

Assignment Help:

The exciting force in a constant force type of excitation was 120 kN. The natural frequency of the machine foundation is 4 Hz. The damping factor is 0.36.

Verify the magnification and transmitted force at an operating frequency of 10 Hz.

 


Related Discussions:- Verify the magnification and transmitted force

Main function of followers in driven h-piles, Question What is main fun...

Question What is main function of followers in driven H-piles ? Answer A follower is an extension between pile head and hammers which transfers blow to pile in which

Sulphate-resisting cement not used in marine concrete, Question Explain...

Question Explain the reason why is sulphate-resisting cement not used in marine concrete ? Answer Major components of Portland cement are tricalcium silicate, dicalciu

Explain the dynamic or vibration tests, Explain the Dynamic or Vibration Te...

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

Binder, Binder: Normally 60/70 penetration grade, and provides cohesio...

Binder: Normally 60/70 penetration grade, and provides cohesion to the mixture and increases its stability. The mix design is done by the Marshall test, in which a specimen

Surveying, define surveying and where it is involved

define surveying and where it is involved

Define equipments required for conducting uwmt, Define Equipments required ...

Define Equipments required for conducting UWMT? Equipments required for conducting UWMT are: Inspection Equipment: a) Electronic yoke with power cable b) Ground fault interr

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd