Various operations involved in maintenance by beater packing, Civil Engineering

Assignment Help:

Q. Explain in details the various operations involved in Through Packing - conventional Maintenance by beater packing.

Explain the various operations as per the Permanent Way Manual for through packing.

Ans.-

Through Packing consists of following operations in sequence -

i. Opening of the road - Opening of ballast by shovel or Phawrah for Through Packing is 450 mm in side the track and up to end of sleeper on the out side and to a depth of 50 mm.

ii. Examination of rails, sleepers and fastenings - All rail and sleeper fittings are examined for fitness and good conditions and replaced as required.

iii. Squaring of sleepers - On base line sleepers to be spaced correctly and on the opposite rail to be squared with T square.

iv. Slewing - To be done as per the base rail as required.

v. Gauging - To be done as per the track depending on straight or degree of curvature.
following tolerances of gauge, provided generally uniform gauge can be maintained over long lengths:

a) On straight -6mm to +6mm

b) On overs with radius 350mm or more -6mm to +15mm

c) On curves with radius less than 350m up to +20mm

vi. Packing - Base rail to be packed for two rail lengths to bring longitudinal level by lifting sags packing and then cross checked by level instrument if necessary / possible.

vii. Re packing of joints - All joints and shoulder sleepers to be repacked and at other locations if any settlement and correction to cross level is to be done.

viii. Boxing of ballast - Ballast to be brought back by wire claws to correct profile and rammed for consolidation.


Related Discussions:- Various operations involved in maintenance by beater packing

Earth fill dams, Ask question #Minimum 100E. The regulations and specificat...

Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#

Surveying, WCB from included angle

WCB from included angle

Road maintenance, find the details of road maintenance in our project work

find the details of road maintenance in our project work

Interface between base plates and footings, Interface between base plates a...

Interface between base plates and footings Surface of footings is generally quite rough so that some levelling has to be carried out for base plates. Interface between base pl

Purpose of tar in bituminous materials, Q. Purpose of tar in bituminous mat...

Q. Purpose of tar in bituminous materials? Tar is usually incorporated in bituminous materials due to the below reasons: (i)  Blending of tar with bitumen possesses better b

Integration of the strain settlement, All soils subjected to stress undergo...

All soils subjected to stress undergo strain. This will be taking place within the soil skeleton. This strain is caused by rolling, slipping, sliding and crushing at the particle c

Surveying, obstacles in chain surveying

obstacles in chain surveying

Industrial steel floor fire proof, i want to know the construction details ...

i want to know the construction details of industrial steel floor?

Strength of Materials, How can I get theratio of the maximum deflections of...

How can I get theratio of the maximum deflections of a beam simply supported at its ends with an isolated central load and that of with a uniformly distributed load over its entire

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd