Use plain dumb-bell type and center-bulb sort, Civil Engineering

Assignment Help:

Question

While selection of waterstop, shall engineers use plain dumb-bell type , center-bulb sort?


Answer

Plain dumb-bell kind is used for joint site where small movements are anticipated. So, construction joints are desirable sites of this type of waterstop. On other hand, center-bulb type waterstop is appropriate for growth joints or locations anywhere lateral and shear movements happen due to settlement.

 


Related Discussions:- Use plain dumb-bell type and center-bulb sort

What is moisture-dry density, Describe why soils are compacted in the field...

Describe why soils are compacted in the field. How is the degree of compaction ensured in the field (i.e., control of field compaction)? Distinguish among 'compaction' and 'consoli

Calculate benefit cost ratio for government project, Calculate the Benefit-...

Calculate the Benefit-Cost Ratio for Municipal Government Project With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:   Initia

Assignment, Need assignment for structure concrete work

Need assignment for structure concrete work

What do you mean by shallow gradient of pipes, Q. Colebrook White formula s...

Q. Colebrook White formula suitable for shallow gradient of pipes? Manning's Equation is commonly used for rough turbulent flow while Colebrook-White Equation is adopted for t

Concrete mix proportions, Concrete Mix Proportions Concrete mix proport...

Concrete Mix Proportions Concrete mix proportions should be chosen in such a way that concrete of adequate workability is obtained. Workability of concrete mix should be such t

Premix carpet open graded, what is premix carpet open graded and where is i...

what is premix carpet open graded and where is it used and what are its limitations ?

Postensioning in raft foundation, how can we post tension a raft foundation...

how can we post tension a raft foundation? what design procedure should we follow to post tension raft foundation in order to decrease the concrete and steel volume and increase th

Scheming thermal reinforcement, Question What is importance of critical...

Question What is importance of critical steel ratio in scheming thermal reinforcement ? Answer Execution of critical steel ratio resources that in construction joints,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd