Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Maintenance job planning, Question 1: (a) What are the factors that y...

Question 1: (a) What are the factors that you would consider to determine the causes of Equipment failures during its life cycle? (b) Explain clearly the failure patter

How are technical skills required for a successful manager, How are the tec...

How are the technical skills required for a successful manager? Technical skill consider to the proficiency in handling processes, methods and techniques of an exact kind of in

Illustrate the division of work in economics, Illustrate the division of wo...

Illustrate the division of work in Economics? Division of Work (or Labour): It s a famous principle of Economics, invented through the traditional economist as defined by

Communication strategy, Communication Strategy: Communication str...

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Competitive priorities, Explain the basic competitive priorities considered...

Explain the basic competitive priorities considered while formulating operations strategy by a firm?

Techniques of project management tools, Over the years, E has had a number ...

Over the years, E has had a number of business successes in the building trade and property development. Her latest venture is to build a hotel in YX town. E has already gained the

What are the benefits of work study?, Question 1) Describe any ten overall...

Question 1) Describe any ten overall functions of the purchasing department Question 2) Describe any five principles of plant layout Question 3) Describe the any

What is a project life cycle, Q. What is a project life cycle? If a pro...

Q. What is a project life cycle? If a project is well prearranged it will progress logically through several phases. There are four standard stages to a typical project. The fi

Factor affecting process planning - choice of plant layout, Factor Affectin...

Factor Affecting Process Planning - Choice of Plant Layout While deciding the sequence of operations the plant layout is to be taken into consideration. The sequence of operat

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd