Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Why undertaking competitive analysis is important, S is enrolled on T Compa...

S is enrolled on T Company's management development programme.  Although S has a financial background, the aim of the management development programme is to help him to gain a bett

Help on project from henley, The Integrated Management Project is a demandi...

The Integrated Management Project is a demanding piece of work requiring initiative, energy and application. It is our desire to support you and help you in this process as much as

Identify the critical path, Please note that the exam is an individual effo...

Please note that the exam is an individual effort (NOT a group effort). Please be sure that all the submitted work is your own. You cannot discuss the test with your classmates or

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

Project management requires three important activities, Question (a) Pr...

Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj

Graphs, G raphs The purpose of graphs is to organise, summarise and di...

G raphs The purpose of graphs is to organise, summarise and display data. The different types of graphs are line graphs, bar graphs, and circle graphs. The steps involved in p

Budgeted cost of work performed (bcwp), Budgeted cost of work performed (BC...

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a p

How is economic order quantity depended on costs, How is Economic Order Qua...

How is Economic Order Quantity depended on costs? Economic Order Quantity depends on two costs as illustrated below: - Inventory procurement costs that consist of expenditur

Short note acceptance theory-line organization, 1. Differentiate between 'A...

1. Differentiate between 'Administration' and 'Management'. 2. What were the common drawbacks in classical and Neo classical theories of management? 3. Write a short note on "Line

Why does the public sector exist, Question 1: a) Why does the public s...

Question 1: a) Why does the public sector exist? b) Discuss 5 ways in which the public sector is different from the private sector. c) The public sector is a clo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd