Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Contract process cycle , Contract process cycle  Contract process goes ...

Contract process cycle  Contract process goes through the following stages to complete the contract documentation cycle:    Pre tender documentation stage.    Approval

Project Risk Management, I have been in chemo after surgery, and have misse...

I have been in chemo after surgery, and have missed quite a bit of Project Risk Management. I was wondering if you guys are able to complete a few assignments that could catch me

Describe problems with functional project coordination, Question 1: "Ma...

Question 1: "Matrix structures are becoming more common and are likely to continue to do so in the future" (Field and Keller, 1998). a) Describe likely problems with functio

Virtual museum project, Building design - You can select any building to ho...

Building design - You can select any building to house your museum.  It may be a historical building that we study (i.e. the Pantheon), it may be a current museum anywhere in the w

What do you mean by variable costs, What do you mean by variable costs? ...

What do you mean by variable costs? Variable costs conversely, tend to vary directly along with the volume of output. Illustrations of variable cost are as given below: direct

Nancy, explain the main typical data input errors that affect deliver of pr...

explain the main typical data input errors that affect deliver of project

Differential costing, application of differential costing in project

application of differential costing in project

What do you mean by psychological tests, What do you mean by psychological ...

What do you mean by psychological tests? Psychological Tests: These Tests are conducted along with a view to ascertaining the mental suitability of the candidate for perf

Design defect, However proving a design defect can be difficult. Some of th...

However proving a design defect can be difficult. Some of the factors used by the jury to asses s whether a product design is defective and unreasonably dangerous are: 1.The utili

A comparative literature review, a comparative literature review on project...

a comparative literature review on project management in small businesses (2000 words)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd