Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Describe informative and persuasive presentations, Problem: (a) Describ...

Problem: (a) Describe the difference between informative and persuasive presentations and describe the key strategies for each of these types of presentations. (b) Why is it

Describe standards of data quality, Question 1: Describe any two standa...

Question 1: Describe any two standards of data quality Any two of the following Governance and Leadership Policies and Procedures Systems and Processes People

Describe quality control, Question 1 There cannot be a single ideal str...

Question 1 There cannot be a single ideal structure for all organisations as different organisations have different size, environment, resources, technologies, and goals. There

Flow charts, Flow Charts Flow chart is the most familiar tool to unders...

Flow Charts Flow chart is the most familiar tool to understand processes. It is used to identify a sequence of events in a process. Using flow charts require six deliberate act

Project management, A project manager desires a work breakdown structure th...

A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by

Purpose of automated storage and retrieval systems, Purpose of Automated St...

Purpose of Automated Storage and Retrieval Systems The main purposes of installing ASRS are as follows: 1. Increase Storage Capacity : ASRS ordinarily  increase the  stora

Operations and project management, Operations and project management: ...

Operations and project management: Operations and project management are very important functions in any organisation. Operations management is is concerned with the productio

External factors of syringe management , External Factors Opportunit...

External Factors Opportunity This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attrac

Benefits and caveats, (a) What are the benefits and caveats of adopting a ...

(a) What are the benefits and caveats of adopting a standard methodology (such as PRINCE2) for the management of an organization's projects? (b) How might the size of an organi

Saving culture and project development, student in project management reque...

student in project management request topic on saving

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd