Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Project sceening, explain the reason for the divergence of opinion from one...

explain the reason for the divergence of opinion from one technique to the next?

Explain portfolio management in project, Question: (a) Project plans ar...

Question: (a) Project plans are created in knowledge areas throughout the different phases of the project life cycle and are subsidiary components of the overall project manag

Explain about term performance management systems, Explain about the term p...

Explain about the term performance management systems in brief. Performance management systems: Measurement processes of frequently assessing a projects progress in oppos

Project management process, Project management Process According to PMB...

Project management Process According to PMBoK, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed

The Walsham Hotel, Compare and Contrast the KN346 investment and the "plain...

Compare and Contrast the KN346 investment and the "plain vanilla" alternative.

Explain about the economic order quantity and total cost, Explain about the...

Explain about the Economic Order Quantity and Total Cost with diagram. Economic Order Quantity and Total Cost: The total of Inventory procurement cost and also inventory carryi

Risk management enhancement , Risk management enhancement  There is sco...

Risk management enhancement  There is scope for risk management scenario and the following are some of the methods suggested:   Bringing increased awareness of risks:  Imp

Implementation of a quality program, Question: (a) Any project has a be...

Question: (a) Any project has a beginning and an end; without a formal closure process, project teams can fail to recognize the end and this can drag the project into unnecessa

Graphs, G raphs The purpose of graphs is to organise, summarise and di...

G raphs The purpose of graphs is to organise, summarise and display data. The different types of graphs are line graphs, bar graphs, and circle graphs. The steps involved in p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd