Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Conflicts arise between project manager and ppso staff, What are conflicts ...

What are conflicts probable to arise between project managers and PPSO staff? PPSO (Project and Programme support office) staff can, when they are not careful or when they are

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Explain the event and the ideal target group, Question 1: a) As an eve...

Question 1: a) As an event organiser you need to target the right audience/visitor group. Taking a festival [local, regional or national] - explain the event and the ideal t

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

National competitive bidding (ncb) , Steps for National Competitive Bidding...

Steps for National Competitive Bidding (NCB)  Similar to ICB, we have two ways involved in NCB: one with pre-qualification, another without prequalification. Steps for NCB are

Process selection - tqm, Once the process capabilities of available proc...

Once the process capabilities of available processes are known the process selection is then just a question of matching the process capability with the tolerance specified

How are conceptual skills required for a successful manager, How are the co...

How are the conceptual skills required for a successful manager? Conceptual skill is the capability to observe the organization as an entire, to recognize inter-relationships i

Functional requirements for an exhibition management system, Question: ...

Question: (a) Consider the following quality goals and provide a way to make the goal more tangible such that it can be easily verified: i. Software should be user friendl

Risk breakdown structure (rbs) , Risk Breakdown Structure (RBS)  R isk...

Risk Breakdown Structure (RBS)  R isk Breakdown Structure (RBS) is a tool developed by Dr. David Hillson that is used to guide the risk management process. He describes RBS as

Explain the tool of total quality improvement, Question: As the Managin...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd