Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Explain the utility of base costs, Question 1: (a) ‘One of the most pow...

Question 1: (a) ‘One of the most powerful concept as advocated by Total Quality Management is that of the internal customer and supplier.' With reference to examples you ar

Scope and initial planning, Develop a work breakdown structure (WBS) for th...

Develop a work breakdown structure (WBS) for the project based on the Summary of Project Deliverables in the scope statement. Recall that a WBS is a set of deliverable-oriented gro

key dimensions of management, Influence of Organization culture on key dim...

Influence of Organization culture on key dimensions of management

Explain dupont formula, While the industry average ROE is about 15%, averag...

While the industry average ROE is about 15%, average profit margin of 50%, asset efficiency of 10%, and leverage ratio of 3, the ROE for ABC, Inc., using data from January 2011, wa

Cost of failure of quality, Failure Cost of failure may result from eit...

Failure Cost of failure may result from either internal failure or external failure. Internal failures are those that occur before the product is delivered, internal failure co

Critical path, Critical Path about wedding planning

Critical Path about wedding planning

Audits, A udits Audits are independent examinations to determine wheth...

A udits Audits are independent examinations to determine whether processes and procedures achieve the specified objective. They are an essential tool to identify problem areas

System and simulation specifications, Input Data Collection The input d...

Input Data Collection The input data for the model was collected accurately to be as close as possible to a typical emergency room. We expected that the number of patients comi

Management of change, Problem 1: a) ‘Project Management is closely link...

Problem 1: a) ‘Project Management is closely linked with the management of change' Explain why. b) Elaborate on two models of change. Explain the relevance, applicability

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd