Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

Level 6 Project Management, Ask question #Minimum 10You are employed as an ...

Ask question #Minimum 10You are employed as an Office Manager in a company based in the centre of London. The company provides consultancy services to businesses around the world,

Accadmic report, I need assignment at least in 10000 words. on above topic ...

I need assignment at least in 10000 words. on above topic also i would like send you sample report only for understanding

Explain products which typically result by project stages, Explain the prod...

Explain the products which typically result by the given project stages: Project Start-up; Analysis of Needs; Design Integration and Testing. Typical products include: •Pro

Back to school crunch at global green books publishi, what risks can you id...

what risks can you identify? why are they risk to global green books publishing?

Cycle time, Cycle time and Assign work elements and Delete the assigned ele...

Cycle time and Assign work elements and Delete the assigned elements A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in th

Describe the follow-up phase, Describe the follow-up phase, in short. ...

Describe the follow-up phase, in short. Follow-up phase: Although this is extremely significant, the follow-up phase is frequently neglected. Throughout this phase, the w

#title.Discountingw., what is the principle of discounting and what issues ...

what is the principle of discounting and what issues are critical in this process

Explain how culture influences global product development, Question 1: ...

Question 1: (a) Critically evaluate joint venture and licensing as global market entry methods. (b) Explain and illustrate how a geocentric approach to global marketing i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd