Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Explain how using a project management methodology, DG Company has made a s...

DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge.  How

Evaluating the project vision, o Is the business problem that the project a...

o Is the business problem that the project addresses clearly defined? o Is the list of stakeholders (ie people affected) by the project complete and correct? o Is the scope o

Definitions of management, Definitions of management Several definition...

Definitions of management Several definitions of management have been given by different scholars. Mary Follet defined management as "having work done through others." Another

Explain briefly the key characteristics of a good project, Question 1: ...

Question 1: i) How would you define a project? What are the different types of project that exist (please explain using a model with examples) ii) Enumerate and explain bri

Network, charateristics of a good network

charateristics of a good network

Launch a new school, how we launch a new school? which steps should keep in...

how we launch a new school? which steps should keep in mind? whats srategies and policies can apply? what is the history of ne school? i need urgent answer

Change in scope of statement, Q. Brandi is working as a project manager on ...

Q. Brandi is working as a project manager on a software project. About halfway through development, her team concludes that they had not estimated enough time for some of the techn

Differential costing, application of differential costing in project

application of differential costing in project

Inventory management, I nventory management: This refers to the met...

I nventory management: This refers to the method in which tangible resources and materials are handled by businesses in order to make sure resources are readily available f

Kaizen, what is a benefit of a kaizen event?

what is a benefit of a kaizen event?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd