Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Describe the major stages of hearts and minds programme, You should design ...

You should design a ‘hearts and minds’ programme associated with the implementation of a modern system for the recording and management of stock within a book-publishing company an

Cost benefit analysis, How to determine which project have larger net benef...

How to determine which project have larger net benefit between two projects

Describe the factors that lead to the project failure, Question: a) Des...

Question: a) Describe lessons or best practices that could be learned from the above case study? b) Describe the factors that lead to the project failure? c) What is acc

Computerized relative allocation of facilities technique, Computerized Rela...

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

Importance of power in project management, Probelm 1: a) Elaborate on t...

Probelm 1: a) Elaborate on the Verma;K(1996) model for effective human resource management and explain its importance in managing projects. b) According to the Verma; K(1996

Basic tools used by a project manager, When someone says project managemen...

When someone says project management tool, the first thing that comes to mind is Microsoft Project. Microsoft Project is just one of the many tools available to and required by p

Use of operational approach in development process, Q. Use of Operational a...

Q. Use of Operational approach in development process? It has been defined as the application of scientific methods, technology and tools to operation of system with optimum s

Cost analysis, After analyzing the three models, and comparing all three us...

After analyzing the three models, and comparing all three using a paired-t test, we found out that the results of the modifications to the base model were statistically significant

Calculate the net present value for each opportunity, Question: A brill...

Question: A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choose between them. One is a job offer with a salary of Rs15,000

Search and remove modules, Seven process modules are placed on our model, a...

Seven process modules are placed on our model, and they represent the basic functions in the model. These process modules simulate important operations such as specifying wheel cha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd