Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Explain the new performance management system, Question 1: (a) How does...

Question 1: (a) How does Training differ from Development? (b) Elaborate on the different training methods, highlighting their relative advantages and disadvantages. Ques

Scoping a project, QUESTION While scoping a project, as much informatio...

QUESTION While scoping a project, as much information as possible should be gathered about the wants and concerns of sponsors and end-users. What are the useful channels of

Management skills required for a successful manager, How are the management...

How are the management skills required for a successful manager? Management Skills: The skills needed of a successful manager, while he is working into a industry,

Describe the follow-up phase, Describe the follow-up phase, in short. ...

Describe the follow-up phase, in short. Follow-up phase: Although this is extremely significant, the follow-up phase is frequently neglected. Throughout this phase, the w

Roles of b as the project sponsor and r, DG Company has made a significant ...

DG Company has made a significant investment in a project to develop a new client management IT system, which when implemented should help give the company a competitive edge.  How

What is project management methodology, Question 1: (a) What is project...

Question 1: (a) What is project management methodology ? (b) Why do you say that project management is the best method of implementing change ? Question 2: (a)

Identify the critical path by activities and duration, Identify the critica...

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Draw a control chart for the number of defects, Explain the concepts involv...

Explain the concepts involved in Product Layout and its advantages and disadvantages vis-a-vis process layout. 18 carpets were observed closely and the number of defects in thei

What is meant by lean management, X began his engineering apprenticeship wi...

X began his engineering apprenticeship with CM8 manufacturing ten years ago before moving abroad to work for other companies. He has now returned to work for CM8 as Operations Mana

Different stages in the negotiation process, In the face of rising costs, t...

In the face of rising costs, the senior management in PT Company has decided that significant cuts will be needed in the budgets of some of its departments. The promotional budget

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd