Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

., discussthe nine project management knowledge areas

discussthe nine project management knowledge areas

Identify the critical path by activities and duration, Identify the critica...

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Traditional definitions of quality, T raditional definitions of Quality ...

T raditional definitions of Quality There are various definitions of quality. According to quality pioneer Joseph M. Juran quality has two meanings that are very important for

Work breakdown structure, I have a project that I would like to have a work...

I have a project that I would like to have a work breakdown structure developed for.

Communication-coordination beneficial in project management, How are commun...

How are communication and coordination beneficial in project management software? Communication and coordination: Project software can give automatic report templates al

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Factors affecting process planning-size of raw material, Factor Affecting P...

Factor Affecting Process Planning Size and form of Raw Materials: Process planning actually starts with the blank selection. The blank or initial raw material may be ava

Explain theoretical principles of the resource based view, Normal 0 ...

Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

Develop an action plan based on your findings, Question: As a newly app...

Question: As a newly appointed rector of your school, you have received many complaints from students .It is your aim to " democratise quality ", that is to make quality contro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd