Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Production development flow diagram, The followings is a list of some of ...

The followings is a list of some of the common pitfalls to avoid if an organization is considering implementing quality by design: 1. Team members should be assigned to

Small project, Q. If I only have a small project, do I really need to bothe...

Q. If I only have a small project, do I really need to bother with all of that? In any of project of any size all of these ten attributes requires some degree of attention. But

Life cycle objectives milestone, Submit all required artefacts necessary to...

Submit all required artefacts necessary to achieve the ‘Life Cycle Objectives Milestone' (LCOM). These are: A Vision document setting out the business objective and business cas

History of iso, ISO 9000 series of standards on quality system was formu...

ISO 9000 series of standards on quality system was formulated by international organization for standards in order to meet the requirements of internationally uniform q

Organisational style - participative management , Organisational Style: ...

Organisational Style: Whether the participative approach can  really work depends upon the type of organisation and its' functioning. An open organisation is more likely to en

What are the major characteristics of a project, Question: (a) What ar...

Question: (a) What are the factors to consider while choosing an appropriate Project Management Structure? (b) What are the major characteristics of a Project? (c) Out

Roles of management, Roles of Management Management roles have been gro...

Roles of Management Management roles have been grouped into three major groups: 1) Interpersonal roles: which involves the manager collecting and disseminating informati

Layout planning and analysis, Layout Planning and Analysis Designing a...

Layout Planning and Analysis Designing and installing a layout for the first time and subsequent revision may be looked after by the. Engineering or planning department. Not i

Project process cycle , Project process cycle  Any project professional...

Project process cycle  Any project professionally planned will target specified goals within the framework of time with available resources. The project passes through the foll

Identify a governmental and a not-for-profit program, One of the characteri...

One of the characteristics unique to governmental and not-for-profit organizations is the inability to eliminate unprofitable activities. Clearly, in the case of these activities,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd