Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Feasibility study for the exploitation of the oil reserves, Question: I...

Question: In the year 2015, the price of petrol has gone up so much that the oil reserves of the Republic of Mauritius start to look interesting to exploit. The oil reserves ar

What are the contents of project planning document, What are the contents o...

What are the contents of project planning document? Contents of a PPD (project planning document): a. Project resource plans b. Quality control and quality policies proce

Identify and comment on the causes of such poor performance, Question : ...

Question : a) "Total Quality Management is regarded as a quick fix solution by many organizations. This has led many companies to start on the road to total quality improvemen

Layout planning and analysis, Layout Planning and Analysis Designing a...

Layout Planning and Analysis Designing and installing a layout for the first time and subsequent revision may be looked after by the. Engineering or planning department. Not i

Define the term scenario planning in risk management, Define the term Scena...

Define the term Scenario Planning in risk management. Scenario planning: It is about perceiving uncertainties for example identification of risks and the growth of pre-em

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

Precedence Diagrams, I know how to construct a precedence diagram but i am ...

I know how to construct a precedence diagram but i am asked the question :use the largest candidate rule to assign work elements to stations using a service time of 1.5 min how do

History of iso, ISO 9000 series of standards on quality system was formu...

ISO 9000 series of standards on quality system was formulated by international organization for standards in order to meet the requirements of internationally uniform q

Main items present in the risk log or risk register, QUESTION (a) Risk ...

QUESTION (a) Risk has always been an intrinsic part of project management. With increasing market dynamic conditions, Safety and Health in workplaces, changing technology and g

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd