Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Automated storage and retrieval systems, Automated Storage and Retrieval Sy...

Automated Storage and Retrieval Systems Automated  storage  and retrieval systems(SASRS) are system  for receiving  orders for  materials  from  anywhere  in  operations colle

Organization of material management, Organization of Material Management: ...

Organization of Material Management: To  facilitate  planning direction  control and co ordination of  various activities  related to material in an  enterprise  thee should

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

Risk management enhancement , Risk management enhancement  There is sco...

Risk management enhancement  There is scope for risk management scenario and the following are some of the methods suggested:   Bringing increased awareness of risks:  Imp

Identify characteristics of effective project team members, Question 1: ...

Question 1: (a) Identify and explain the major roles of a Project Manager with illustrations where necessary. (b) Identify and Explain the different types of Project Organ

How is inventory procurement costs expenditure connected, How is Inventory ...

How is Inventory procurement costs expenditure connected? Inventory procurement costs that consists of expenditure connected along with as a. Its Receiving quotations b.

Explain the development process, Question 1: "Total Quality Management ...

Question 1: "Total Quality Management is regarded as a quick fix solution by many organizations.This has led many companies to start on the road to total quality improvement in

Strategy for project implementation, A strategy for project implementation ...

A strategy for project implementation Projects involving  small number  of  activities,  resources,  constraints  and inter-relationship can be visualized easily by the human m

Definition of quality in projects, Definition of Quality in Projects Th...

Definition of Quality in Projects The way to achieve project quality is to make a meaningful and effective transfer of proven quality methods to the project management domain.

Steps of project manager to enhance likelihood of project, Ideally, the nee...

Ideally, the need for an IS project would be given in some detail before planning begins. When the requirement is not detailed adequate, what steps can the project manager take to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd