Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

What is the important role of Controlling in the management, What is the im...

What is the important role of Controlling in the management? Controlling: Controlling is described as which managerial function that seeks to make sure an absolute c

Management of change, Problem 1: a) ‘Project Management is closely link...

Problem 1: a) ‘Project Management is closely linked with the management of change' Explain why. b) Elaborate on two models of change. Explain the relevance, applicability

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

What do you mean by improving productivity, What do you mean by Improving P...

What do you mean by Improving Productivity? Improving Productivity: The concentrate of production is creation of goods, might be by the transformation of raw materials or

Produce a project management plan - gantt chart, For this unit (Computer Pr...

For this unit (Computer Project), you are required to plan, analyse, design, implement, test, document and demonstrate a prototype of your choice.  Once you have identified a fo

A comparative literature review, a comparative literature review on project...

a comparative literature review on project management in small businesses (2000 words)

Evaluate cost estimation, Prepare a 1-page Cost Estimate in MS Excel for th...

Prepare a 1-page Cost Estimate in MS Excel for the project similar to the example provided below. Use the WBS items provided below, and be sure to document assumptions you make in

Commercial project negociation, I want to make a report on this topic by to...

I want to make a report on this topic by tomorrow morniing

Procurement , Functions of Purchasing Department

Functions of Purchasing Department

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd