Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Scheduling in program management, Scheduling  Once a program plan is ap...

Scheduling  Once a program plan is approved, good scheduling is the heart of the program management process. Program schedules provide adequate time to ensure that the work bre

Perform a status assessment of the project iteration, Perform a status asse...

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the it

What are the steps for benchmarking, Question 1: (a) ISO 9000:2008 spec...

Question 1: (a) ISO 9000:2008 specifies the requirements for a Quality Management System. The standard is based on eight quality management principles upon which to develop an

Relationship-reporting arrangements of manager with sponsor, What type of r...

What type of relationship and reporting arrangements must the project manager have with the sponsor? The sponsor of a project shows the management of the organisation which com

Management parts, Discuss the management part of project management

Discuss the management part of project management

Design and implementation of the pms, Question: Performance appraisal (...

Question: Performance appraisal (PA) and management play an important role in the effective management of employees in every viable organisation. However, for many Human Resour

Explain about the changing information technology, Explain about the changi...

Explain about the changing information technology. Changing Information Technology: Challenges and Prospects There is no suspicion that information technology has create

JJ Electronics Product Development Case, i need an assignment to be done by...

i need an assignment to be done by microsoft project 2010 . it should contain all details like critical path,and gantt chart etc in .mpp .

Discuss the objectives of performance appraisal, Question 1: a) What ...

Question 1: a) What is performance appraisal and discuss the objectives of performance appraisal? b) Elaborate on the different techniques of performance appraisal an

Scoping a project, QUESTION While scoping a project, as much informatio...

QUESTION While scoping a project, as much information as possible should be gathered about the wants and concerns of sponsors and end-users. What are the useful channels of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd