Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Total quality management approach within 2jn, 2JN is a large manufacturing ...

2JN is a large manufacturing organisation which is structured with a number of supervisors every responsible for their own work production unit. Supervisors report to a team of sen

Objectives of a procurement system, Question 1: (a) Enumerate five obje...

Question 1: (a) Enumerate five objectives of public procurement systems contained in the UNCITRAL Model Law on Procurement of Goods and Construction. (b) Compare and c

NETWORK DIAGRAMS, AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROB...

AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROBABILTY THAT A WORK WILL BE FINISHED IN A GIVEN NUMBER OF DAYSsk question #Minimum 100 words accepted#

Elaborate the four possible choices in allocating the risk, QUESTION Ri...

QUESTION Risk is inherent to all projects. With increasing market competition, technology and globalisation, risk management is continuously gaining wider acceptance and import

Factors can make competitive rivalry between organisation, DF Company, a re...

DF Company, a relatively new company, is in the business of designing and building farm equipment and machinery. Whilst it has been winning in its first few years of operation, sal

Project management functions, Project Management Functions Let us now d...

Project Management Functions Let us now discuss the project management functions. Project management process consists of five core functions to utilise resources to accomplish

Define the term earned value management in short, Define the term Earned Va...

Define the term Earned Value Management in short. Earned Value Management (EVM): Earned Value Management (EVM) is a project management system which combines schedule and

Components of participative management, COMPONENTS OF PARTICIPATIVE MANAGEM...

COMPONENTS OF PARTICIPATIVE MANAGEMENT: The involvement of staff in the decision making process of the organization and having increased awareness of the organization's purpos

Explain the sources of conflict, In response to changing customer demands a...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd