Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Evaluating initial architecture, o Are the goals and philosophy of the arch...

o Are the goals and philosophy of the architecture explained? o Are assumptions and dependencies influencing the architecture identified? o Are architecturally significant re

Advantage of in-house project management service, Question: Using the e...

Question: Using the example of Back~to~Future International, a newly setup organization and taking advantage of in-house project management service as set out in Question (

Crucial component of project management, Question: (a) Describe why ris...

Question: (a) Describe why risk management is a crucial component of project management. (b) Critically show the different responses to risks that should be developed ear

Incremental approach to testing by integration test, Explain the incrementa...

Explain the incremental approach to testing represented by the orderly integration test. Integration test: The integration test is looking for to determine whether the mo

How do i get my project organized, Q. How do I get my project organized? ...

Q. How do I get my project organized? Every project that involves surplus to one person requires a project team to get the work done. With no doubt building a motivated project

Define balance of payments, Balance of Payments A summary of balance o...

Balance of Payments A summary of balance of payments in the statement of international transactions between U.S. residents and residents of foreign nations serves as a measure

Explains the product life cycle, Question: You have been appointed as c...

Question: You have been appointed as consultant to advise a small company of your choice about its product portfolio. Write a report which: a) explains the product life cycl

ASF Mobile App Development, Australian’s Speleological App Project Speleolo...

Australian’s Speleological App Project Speleology is the scientific study of caves and other

Combined layout, Combined Layout The application of the principle of p...

Combined Layout The application of the principle of product layout, process layout or fixed location layout in their strict meanings is difficult to come across. A combination

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd