Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Organizing-process management, Organizing Which is the process of group...

Organizing Which is the process of grouping resources and activities in a logical fashion. The function of organizing involves: grouping similar activities together (depa

Develop an action plan based on your findings, Question: As a newly app...

Question: As a newly appointed rector of your school, you have received many complaints from students .It is your aim to " democratise quality ", that is to make quality contro

What are claimed benefits in use of structured methods, Some critics have s...

Some critics have said that the utilization of structured methods, as like SSADM, raises both delivery time and bureaucracy. Do you imagine these criticisms are justified and what

leadership theories, Discuss three contemporary leadership theories and ou...

Discuss three contemporary leadership theories and outline the conditions under which each of these theories is most effective.

What must be the responsibility of the project manager, What must be the re...

What must be the responsibility of the project manager into relation to the business case? Idyllically, the project manager must be appointed early adequate to give to the deve

JJ Electronics Product Development Case, i need an assignment to be done by...

i need an assignment to be done by microsoft project 2010 . it should contain all details like critical path,and gantt chart etc in .mpp .

Quantitative layout analysis - load distance analysis method, Quantitative ...

Quantitative Layout Analysis - Load Distance Analysis Method Load distance analysis is useful in comparing alternative layouts to identify the one with the least product or ma

Essential pre-requisites of a grievance procedure, Problem 1: Show the ...

Problem 1: Show the essential pre-requisites of a grievance procedure. Essential pre-requisites of a grievance procedure Problem 2: What are the objectives of Trade

Production planning, PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUF...

PRODUCTION PLANNING AND SCHEDULING OF A GARMENTS MANUFACTURING COMPANY 1. Introduction TREND SHOPS SDN BHD is a manufacturing unit of (mid-upmarket) ladies garments.  It

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd