Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Project lifecycle for the training centre project, T Company has identified...

T Company has identified a need for, and made a decision to open, a new training centre in one of the major cities in E Country. This is a large scale project for T Company and it

Dimensions of business excellence, D i mensions of business excellence ...

D i mensions of business excellence Business excellence is a continuously evolving process and no organisation can be thought of as -excellent performer in all four dimension

Critical analysis, Need to get critical analysis of the Document, Project M...

Need to get critical analysis of the Document, Project Management Body of Knowledge 1996 by the Standard committee of the PMI 8 pages. how much would this cost?

Explain the sources of conflict, In response to changing customer demands a...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

Events Management, We are two partners, starting a new business "Events Man...

We are two partners, starting a new business "Events Management" and we have to prepare the business plan with 7P''s, how could you help us?

Mbo process, MBO process MBO is the process of collaborative goal setti...

MBO process MBO is the process of collaborative goal setting between the manager and his or her subordinates. It assumes that goals are consistent or compatible from the highes

Explain phases of group development, Question 1: (a) While managing HR...

Question 1: (a) While managing HR projects, explain the different stages that ultimately lead to ‘crisis' in a conflict situation. (b) Despite that fact that conflicts bre

Define deterministic model of inventory control, Question 1: Define det...

Question 1: Define deterministic model of inventory control. Explain inventory costs and relationships Description of deterministic model of inventory control Invento

Use of both innovative approach in development process, Q. Use of both inno...

Q. Use of both innovative approach in development process? There are many major aspects that will sway the future trends in the development of new products. In the new millenn

Project management and leadership, Scenario Even ‘well run' organisations c...

Scenario Even ‘well run' organisations can fail to stay atop of their industries when they are challenged by certain market or technology change. Change is an imminent part of busi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd