Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Life cycle objectives milestone, Submit all required artefacts necessary to...

Submit all required artefacts necessary to achieve the ‘Life Cycle Objectives Milestone' (LCOM). These are: A Vision document setting out the business objective and business cas

Software project, Scenario: You are a member of the Project Review team for...

Scenario: You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM)

What is a project plan and what does it involve, Q. What is a project plan ...

Q. What is a project plan and what does it involve? A well incorporated project plan is the primary tool for effective coordination of the work and for tracking and steering pr

Explain about the break even analysis, Explain about the Break Even Analysi...

Explain about the Break Even Analysis. Break Even Analysis: Break even Analysis means that at some point within the operations, total revenue equivalent to total cost. Break ev

Revolution advantages of changing in information technology, What are the a...

What are the advantages of the revolution of changing in information technology? The positive side of the strides made within the realm of information technology is more benefi

What communication do i need, Q. What communication do I need? Communic...

Q. What communication do I need? Communication is possibly one of the most important functions of a project manager and yet sometimes the least understood. With no people there

Importance of materials management, Importance of Materials Management ...

Importance of Materials Management The  primary  and secondary  objectives  listed  above  should  themselves give us clear idea about  the  importance of materials management

Macro environment, The influence an organisation will normally have over it...

The influence an organisation will normally have over its macro environment will be Limited or non existent

Principle of total quality management, 1. Objective ( Theme ) : Continuous...

1. Objective ( Theme ) : Continuous quality improvement at every level at every place and at every stage. 2. Approach :Management involvement and leadership, Empowering s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd