Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Help on project from henley, The Integrated Management Project is a demandi...

The Integrated Management Project is a demanding piece of work requiring initiative, energy and application. It is our desire to support you and help you in this process as much as

Define why the concept of ppso arose into the first place, Define why the c...

Define why the concept of PPSO arose into the first place. The basses of the PPSO lie into the provision of administrative maintain for project managers, to look after several

Organisational style - participative management , Organisational Style: ...

Organisational Style: Whether the participative approach can  really work depends upon the type of organisation and its' functioning. An open organisation is more likely to en

Enterprise architecture project, The following diagram describes the a...

The following diagram describes the architecture development process prescribed by the The Open Group Architecture Framework (TOGAF).  The bi-directional arrows link

Production and purchasing management, A) Hierarchical planning in Operation...

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

The purpose of project management, QUESTION a) The purpose of project m...

QUESTION a) The purpose of project management is to achieve successful project completion with the resources available. Regardless of the method that is used to handle a projec

What is delegation of authority, What is delegation of authority? Del...

What is delegation of authority? Delegation: There is a restriction to what an individual can do single-handed. After a point, another person working within the organisat

Explain about the project management systems, Explain about the project man...

Explain about the project management systems. Project management systems: Each project must have a plan and a set of goals or performance measures to achieve this. Contro

Processes as production systems, Processes as Production Systems A ...

Processes as Production Systems A production system refers to how an organization   organizes material flow using different process technologies. There are five major types

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd