Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

How to measures re-work for the product, Re-work effort (hours, as a percen...

Re-work effort (hours, as a percentage of the creative coding hours) Re-worked LOC (source lines of code, as a fraction of the total delivered LOC) Re-worked software compone

Two primary stages of risk management of a project, Question Using a pr...

Question Using a project drawn from your own experience, discuss the following (a) What are the two primary stages of risk management of a project? (b) What are the four

Participative management, PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMEN...

PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMENT: Like most other organizations, libraries and information centres have the dual social responsibility of satisfying the needs

What should be the main concern of the project manager, Question 1: Hos...

Question 1: Hospitality management is an area of constant evolution, renovation, changes in trends and fashion. According to you how could proper planning and design help in

Computerized relative allocation of facilities technique, Computerized Rela...

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

What is critical path in job operation of a project, What is critical path ...

What is critical path in job operation of a project? Critical Path: This is that sequence of activities that decide the total project duration. This Path is formed throu

Help on project from henley, The Integrated Management Project is a demandi...

The Integrated Management Project is a demanding piece of work requiring initiative, energy and application. It is our desire to support you and help you in this process as much as

Explain what is public-private-partnership, Question : (a) Explain wha...

Question : (a) Explain what is public-private-partnership (PPP)? (b) What are the benefits of public-private-partnership? (c) Explain the different forms PPP arrangeme

Explain any two benefits of an erp implementation, Question 1 Differentiat...

Question 1 Differentiate between Commercial and Open Source ERPs software packages Question 2 For a successful MRP system three types of information are very essential. Descr

Aspects to good project management, Q. Is that all there is to project mana...

Q. Is that all there is to project management? A. That is by no way all. There are several aspects to good project management that require attention. In summary these perhaps

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd