Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Define why the concept of ppso arose into the first place, Define why the c...

Define why the concept of PPSO arose into the first place. The basses of the PPSO lie into the provision of administrative maintain for project managers, to look after several

Professional boundaries, An enrolled nurse has been assigned to care for a ...

An enrolled nurse has been assigned to care for a close relative who she cares for deeply who has been admitted to hospital with chest pain.  Nobody knows that this patient is rela

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

How you would estimate the project management activity, Explain how you wou...

Explain how you would estimate the project management activity. Project management: This effort is dependent onto two things as whether a full-time project manager is to be

Feedback mechanism - element of total quality management, The customer fee...

The customer feedback and employee feedback mechanisms are the essential requirements to create customer oriented quality culture. These feedback mechanisms perspectives an ac

How do i organize and apply resources, Q. How do I organize and apply resou...

Q. How do I organize and apply resources? A. The first moreover most important step in the implementation phase is to re-visit the project plan (or the project brief) and to

Identify characteristics of effective project team members, Question 1: ...

Question 1: (a) Identify and explain the major roles of a Project Manager with illustrations where necessary. (b) Identify and Explain the different types of Project Organ

What is project management methodology, Question 1: (a) What is project...

Question 1: (a) What is project management methodology ? (b) Why do you say that project management is the best method of implementing change ? Question 2: (a)

Determine the progress and control status of the project, i) Explain the p...

i) Explain the project management control technique called earned value analysis and illustrate the fundamental concepts. Justify your answer. ii) Determine the progress and

Change management plan for an organisation, Change Management Plan for an O...

Change Management Plan for an Organisation Explain: (i) Background to organization (one page max) (ii) Analyse the organization situation by conducting a force field anal

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd