Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Participative management, PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMEN...

PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMENT: Like most other organizations, libraries and information centres have the dual social responsibility of satisfying the needs

Advantages of three dimensional models, Advantages of Three Dimensional Mod...

Advantages of Three Dimensional Models Layouts made of models are easier to understand by laymen. It is easy to explain to the management. Models can be shifted eas

Relationship-reporting arrangements of manager with sponsor, What type of r...

What type of relationship and reporting arrangements must the project manager have with the sponsor? The sponsor of a project shows the management of the organisation which com

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Work breakdown structure, I have a project that I would like to have a work...

I have a project that I would like to have a work breakdown structure developed for.

Project management the managerial process, Are you able to assist with assi...

Are you able to assist with assignments mid terms finals at a masters level

Explain the development phase in the project management, Explain about the ...

Explain about the development phase in the project management. Development phase During the development phase, everything that will be needed to implement the project is

Events Management, We are two partners, starting a new business "Events Man...

We are two partners, starting a new business "Events Management" and we have to prepare the business plan with 7P''s, how could you help us?

Why do projects need planning, Q. Why do projects need planning? A basi...

Q. Why do projects need planning? A basic of managing projects is first to plan and then to accomplish. Obviously good project management is lots more complex as we shall see s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd