Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

What are the disadvantages of critical path analysis, What are the disadvan...

What are the disadvantages of critical path analysis? Disadvantages of critical path analysis (CPA): a. Supposes a trade off among time and money but most staff cost coul

Project risk, Identifying Project Risk  Risk identification is a proces...

Identifying Project Risk  Risk identification is a process which determines the types of risks that have potential impact on a project. The risk identification is an ongoing pr

Management of utilities for a estate complex, Question 1: (i) What are...

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

Matrix organisation structure, M a t r i x organisation A matrix o...

M a t r i x organisation A matrix organisation is a combination of functional and project organisation. A weak matrix organisation has most of the characteristics of a fun

Llean management, Arvin Automotive, a company that makes muffler assemblies...

Arvin Automotive, a company that makes muffler assemblies for the Big Three, is committed to the use of Kanban to pull material through its manufacturing cells. Arvin has designed

Risk management responsibilities, Risk Management Responsibilities   Ea...

Risk Management Responsibilities   Each and every person in the project team has a responsibility of performing a particular task and must indulge in risk management process. T

Concept of project risk audit , Define the Concept of Project Risk Audit  ...

Define the Concept of Project Risk Audit  Audit can be defined as an evaluation of a person, organisation, system, process, enterprise, project or product. Quality risk audit i

Process selection - tqm, Once the process capabilities of available proc...

Once the process capabilities of available processes are known the process selection is then just a question of matching the process capability with the tolerance specified

What do you mean by line balancing in management, What do you mean by Line ...

What do you mean by Line Balancing in management? Line Balancing: It means balancing the line among the product lines or assembly lines. This aims at grouping assists an

Explain the different service delivery gaps, Question: (a) The findings...

Question: (a) The findings of Parasuraman et al have demonstrated that there are gaps in the service delivery leading to several misunderstandings between customer expectations

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd