Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

How much time should planning take, Q. How much time should planning take? ...

Q. How much time should planning take? T imes taken for individual projects differ considerably frequently due to circumstances beyond the project manager's control such as ch

Varying utilization plan, Varying Utilization Plan The utilization of ...

Varying Utilization Plan The utilization of workers is varied keeping it he workforce size and inventory size constant. The number of workers is kept constant in this plan. Du

Projectplanning, #question.what is project planning.

#question.what is project planning.

Standardization of work processes, Standardization of Work Processes:   ...

Standardization of Work Processes:   The interrelated processes of an organization need to be standardized which help to determine how work is organized and how customer needs

Preparation of manufacturing drawings, This is one of the most tedious a...

This is one of the most tedious and difficult phases of design yet quality literally depend upon the correctness and completeness of the manufacturing drawings and specifica

Initial project plan, o Does the project plan clearly identify a set of fun...

o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and

Report and presentation, I want report on this article in 1500 words and pr...

I want report on this article in 1500 words and presentation my article is Huber, M., Van Boven, L., McGraw, A.P. and Johnson-Graham, L. 2011. Whom to help? Immediacy bias in judge

Characteristics and goals of organizational development, Question 1: Wh...

Question 1: What are the characteristics and goals of organizational development? Describe organizational development Characteristics and goals of organizational developmen

Process of delivering a presentation, Question : The process of deliver...

Question : The process of delivering a presentation is a systematic one that involves thorough planning as well as preparation and one of the main phases is preparing the prese

Evaluating the domain model, o Is the domain model a complete representatio...

o Is the domain model a complete representation of the relevant objects in the problem domain? o Are associations between problem domain objects captured? o Are specializatio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd