Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Explain the elements of a service level agreement, Problem 1: (a) What...

Problem 1: (a) What do you meant by Life Cycle Costing? (b) Explain briefly the methodology for Life Cycle Costing. (c) Why might a procurement officer consider procuri

Scope and initial planning, Develop a work breakdown structure (WBS) for th...

Develop a work breakdown structure (WBS) for the project based on the Summary of Project Deliverables in the scope statement. Recall that a WBS is a set of deliverable-oriented gro

Responsibilities of an event manager, Question 1: a) Outline the key r...

Question 1: a) Outline the key responsibilities of an Event Manager b) Give THREE clear working examples of possible event objectives for either a country, a resort, an or

Maintenance job planning, Question 1: (a) What are the factors that y...

Question 1: (a) What are the factors that you would consider to determine the causes of Equipment failures during its life cycle? (b) Explain clearly the failure patter

Functional project structure, QUESTION (a) The project lifecycle refers...

QUESTION (a) The project lifecycle refers to a logical sequence of activities to accomplish the project's goals and objectives. Regardless of the scope or complexity any projec

What are the pros and cons of a pure project organisation, What are the pro...

What are the pros and cons of a ‘pure’ project organisation compared along with a project operating into a matrix structure? A ‘pure’ project organisation comprises into itself

Processes by market orientation , Processes by Market Orientation Pro...

Processes by Market Orientation Processes can  also be categorized on the basis  of four  marker orientations: Make to Stock (MTS): the goods usually are standard mat

History of iso, ISO 9000 series of standards on quality system was formu...

ISO 9000 series of standards on quality system was formulated by international organization for standards in order to meet the requirements of internationally uniform q

Describe the factors that lead to the project failure, Question: a) Des...

Question: a) Describe lessons or best practices that could be learned from the above case study? b) Describe the factors that lead to the project failure? c) What is acc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd