Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Construct a network diagram showing the critical path, ST is the operations...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

What are the processes of producing budgets, What are the processes of prod...

What are the processes of producing budgets? The process of producing budgets: • A budget manual is formed to provide instructions, delegate responsibilities, reporting line

Process planning, Process Planning Process planning is the systematic dete...

Process Planning Process planning is the systematic determination of method or process by which the product is to be manufactured economically and competitively within the limits

Case Study, Develop a work breakdown structure. 3. Make a list of the speci...

Develop a work breakdown structure. 3. Make a list of the specific activities that need to be done between now and the wedding day. 4. For each activity, identify the person (Tony,

Output analyzer, We used the output analyzer in order to compare the averag...

We used the output analyzer in order to compare the average waiting time spent in the urgent doctor queue in both the base model and alternative model 1 and between base model and

Level 6 Project Management, Ask question #Minimum 10You are employed as an ...

Ask question #Minimum 10You are employed as an Office Manager in a company based in the centre of London. The company provides consultancy services to businesses around the world,

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

Empowering the staff - element of tqm, Empowering the staff assists to acco...

Empowering the staff assists to accomplish optimal business results through team work. Empowerment occurs when employees are adequately trained, provided with all relevant inf

Quality movement, QUESTION 1: (a) Explain how TWO of the given gurus h...

QUESTION 1: (a) Explain how TWO of the given gurus have contributed to the Quality Movement, highlighting the major points of their philosophies: (i) Edward Deming (ii)

How you would organise a project team for rad-type project, Notice how you ...

Notice how you would organise your project team for RAD-type project. What leadership practices would this need by the project leader and what would the team members have to perfor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd