Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

History of iso, ISO 9000 series of standards on quality system was formu...

ISO 9000 series of standards on quality system was formulated by international organization for standards in order to meet the requirements of internationally uniform q

Techniques of project management tools, Over the years, E has had a number ...

Over the years, E has had a number of business successes in the building trade and property development. Her latest venture is to build a hotel in YX town. E has already gained the

Components of participative management, COMPONENTS OF PARTICIPATIVE MANAGEM...

COMPONENTS OF PARTICIPATIVE MANAGEMENT: The involvement of staff in the decision making process of the organization and having increased awareness of the organization's purpos

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Elaborate those stages in a project life cycle, QUESTION (a) The projec...

QUESTION (a) The project organization structure clearly identifies the relationship between project team members through defining their duties, responsibilities and lines of au

Projectplanning, #question.what is project planning.

#question.what is project planning.

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

Continuous improvement - total quality management, Do it Right First Tim...

Do it Right First Time : TQM adopt the policy of zero defect. There is no scope for rework and rejection. The right first time or zero defect is the result of an empha

What do you mean by the term dependency, What do you mean by the term depen...

What do you mean by the term dependency? How can project dependencies be shown for planning reasons? Dependency arises when, for illustration, task or deliverable 'A' should be

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd