Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Seven forces and the body of knowledge, T he seven forces and the body of ...

T he seven forces and the body of knowledge A root cause is a basic causal factor, which if corrected or isolated will stop recurrence of a situation .There is honest disagree

Internal and external customers - elements of tqm, Internal and external cu...

Internal and external customers: The library shall be functioning as a "learning and resource centre" in its efforts to stay abreast of changes in its internal and external en

Client master plan, The Client Masterplan includes introduction, rationale,...

The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines

Leadership - participative management, Leadership: Leadership behaviou...

Leadership: Leadership behaviours lead to  highly  motivated staff. Subordinates rely upon the leadership skills of their  superiors to  show them  how to achieve their needs

The purpose of a project initiation document, S Company has been awarded th...

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this s

What is production, What is Production? Production: Production is...

What is Production? Production: Production is any procedure or process developed to transform a set of input tools as men, capital, materials, information and energy with

What limitations should be considered in project beginning, What limitation...

What limitations should be considered in the beginning of a project? limitations of project: The central question into the follow-up phase concerns while and where the pro

Contract management, Contract Management  There are many things involve...

Contract Management  There are many things involved in a project risk policy. One of them is contract management. Various kinds of contract can have an impact on the success of

Importance of power in project management, Probelm 1: a) Elaborate on t...

Probelm 1: a) Elaborate on the Verma;K(1996) model for effective human resource management and explain its importance in managing projects. b) According to the Verma; K(1996

Organization design-managerial function of organizing, Organization design ...

Organization design Organization design refers to the overall configuration of positions and interrelationships among positions within the organization. Design therefore mainly

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd