Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Definitions of management, Definitions of management Several definition...

Definitions of management Several definitions of management have been given by different scholars. Mary Follet defined management as "having work done through others." Another

Tool of total quality improvement, Question: As the Managing Director o...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Define why the concept of ppso arose into the first place, Define why the c...

Define why the concept of PPSO arose into the first place. The basses of the PPSO lie into the provision of administrative maintain for project managers, to look after several

Explain the development process, Question 1: "Total Quality Management ...

Question 1: "Total Quality Management is regarded as a quick fix solution by many organizations.This has led many companies to start on the road to total quality improvement in

How much time should planning take, Q. How much time should planning take? ...

Q. How much time should planning take? T imes taken for individual projects differ considerably frequently due to circumstances beyond the project manager's control such as ch

Project management requires three important activities, Question (a) Pr...

Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj

Tools for collecting data, T ools for collecting data Improper or inco...

T ools for collecting data Improper or incomplete collection of data is a fundamental error which has an effect on all the subsequent actions. Data may be collected at the tim

Span of management-managerial function of organizing, Span of management ...

Span of management Span of management refers to the number of subordinates who directly report to one superior. If a manager has too many subordinates then his span is wide and

Advantages of product layout, Advantages of Product Layout Regulat...

Advantages of Product Layout Regulation of Production: Since  production  is planned  according  to an orderly sequence manufacturing  time  from the  initial  operations

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd