Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Policies-planning function, Policies are general statements to guide...

Policies are general statements to guide subordinate thinking in the decision making process. policies define the area within which a subordinate may make a decision. In

Identify the critical path by activities and duration, Identify the critica...

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

Pm, short note on partnering

short note on partnering

Why does the public sector exist, Question 1: a) Why does the public s...

Question 1: a) Why does the public sector exist? b) Discuss 5 ways in which the public sector is different from the private sector. c) The public sector is a clo

Identification of customers - implementing tqm techniques, Identification o...

Identification of Customers: Who are the external and internal customers? Can customers be segmented either on the basis of the service that they require, or their attitudes t

Definitions of management, Definitions of management Several definition...

Definitions of management Several definitions of management have been given by different scholars. Mary Follet defined management as "having work done through others." Another

Family planning research center of nigeria, 1. Some of the tasks in this pr...

1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the proj

Evaluation of current organisational culture, It is gradually recognised th...

It is gradually recognised that culture, although difficult to measure precisely, it is a real and very powerful force in organisations. Organisational behaviour is related to cult

Components of strategy, Components of Strategy Strategy has four basic ...

Components of Strategy Strategy has four basic components: Scope: which refers to the position the firm wants to have in relation to its environment. Resource deploym

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd