Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Barriers to implementing tqm, BARRIERS TO IMPLEMENTING TQM: The implem...

BARRIERS TO IMPLEMENTING TQM: The implementation of TQM in library organisations provides an opportunity to update and enhance the abilities of the staff to work effectively,

Reporting style, The Integrated Management Project is not intended to be an...

The Integrated Management Project is not intended to be an academic research report and the markers will not normally expect inclusion of a literature review or hypothesis testing.

What are necessary features of the earned value management, What are the ne...

What are the necessary features of the Earned Value Management? Necessary features of EVM systems: a. A quantified project plan which identifies work or activities to be

Policy requirements, Policy requirements The following are the policy r...

Policy requirements The following are the policy requirements: A c countability for projects: For adequate definition and responsible implementation of projects the

A Grid Analysis (Weighted Scoring Model) to, I need a decision matrix- a Gr...

I need a decision matrix- a Grid Analysis (Weighted Scoring Model) to Help Make the North American Plant Location Decision for the RX 330 I need the acual model calculated based

Developing a project plan, You are creating a customer database for the Win...

You are creating a customer database for the Winston-Salem Warthogs

Project communication management processes, Question: (a) The greatest ...

Question: (a) The greatest threats to many projects are failures to communicate effectively. (i) Elaborate on the Project Communication Management processes (ii) Briefly

Risk management , Introduction to Risk Management Let us begin with def...

Introduction to Risk Management Let us begin with defining Risk. Risk, is an integral part of the business scenario, and can be termed as a potential event that can have opport

Concept of project risk audit , Define the Concept of Project Risk Audit  ...

Define the Concept of Project Risk Audit  Audit can be defined as an evaluation of a person, organisation, system, process, enterprise, project or product. Quality risk audit i

Explain products which typically result by project stages, Explain the prod...

Explain the products which typically result by the given project stages: Project Start-up; Analysis of Needs; Design Integration and Testing. Typical products include: •Pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd