Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Project cost management, Your project sponsor has asked you and your team t...

Your project sponsor has asked you and your team to refine the existing cost estimate for the project so that there is a solid cost baseline for evaluating project performance. Rec

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

Manager’s personal values with team members, Managers can trace, diagnose, ...

Managers can trace, diagnose, analyze, quantify, and find timely solutions when they are familiar with organizational culture. Managers fail in implementing new strategies and new

Benefits of value management over entire project lifecycle, Question: (...

Question: (a) Project Value Management has gained significant acceptance in different fields of business and is regarded as a useful tool for promoting project sustainability

If i am empowered, Q. If I am empowered, why do I need project management? ...

Q. If I am empowered, why do I need project management? A. If you have been authorize it probably or must mean that you have been given the authority and responsibility to un

JJ Electronics Product Development Case, i need an assignment to be done by...

i need an assignment to be done by microsoft project 2010 . it should contain all details like critical path,and gantt chart etc in .mpp .

What is brainstorming, Question 1: (a) Mr Dupuy, the Chaiperson of the ...

Question 1: (a) Mr Dupuy, the Chaiperson of the Rose Flower Senior Citizen Association having its seat at 30 Avenue Des Loisirs Pointes-aux-sables wishes to call a meeting of m

Product/service and volume flexibility, Product/Service and Volume Flexibil...

Product/Service and Volume Flexibility Ability to respond fast to the customer's needs known as flexibility.Two forms of flexibility are product/ Service and volume flexibilit

Scoping a project, QUESTION While scoping a project, as much informatio...

QUESTION While scoping a project, as much information as possible should be gathered about the wants and concerns of sponsors and end-users. What are the useful channels of

Line balancing methods, Line Balancing Methods  The various line balan...

Line Balancing Methods  The various line balancing methods or techniques used are: Heuristic Methods Linear Programming Kilbride and waste Methods

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd