Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Increasing interest in employ of application development, Increasing intere...

Increasing interest is being taken in the employ of quick application development. Why is that, and are there any dangers related with the RAD approach? RAD has come to promine

Project process cycle , Project process cycle  Any project professional...

Project process cycle  Any project professionally planned will target specified goals within the framework of time with available resources. The project passes through the foll

Key performance indicators of success of business or project, K e y perfo...

K e y performance indicators The key to success of a business is dependant on superior management information. Consequently while monitoring profitability and cash flows, a b

Peril database, PERIL Database   The Project Experience Risk Information...

PERIL Database   The Project Experience Risk Information Library (PERIL) is a database, which provides a basis for the analysis of high-tech project risk.  A project can have

Project management, Project management: a. Describe a project you are ...

Project management: a. Describe a project you are currently working on for school or work or your personal hobbies and interests that would benefit from Project Management con

Project dess igne, think a project of your own and formulate a questionnair...

think a project of your own and formulate a questionnaire

Project management project for project managemen class, I have project assi...

I have project assignmet for project management and the submition due date is 5th may can you help me with it ?

Types of sampling risks, T y pes of Sampling Risks A guarantee that e...

T y pes of Sampling Risks A guarantee that every defective item in a lot would be found cannot be stated by neither sampling nor 100% inspection, 100% inspection has the risk

Project management plan of Reverse osmosis plant, Scope Work breakdown str...

Scope Work breakdown structure Gantt chart Scope cchange management Project budget Project ccash flow

What is memory virtualization, 1. Enterprises always seek to enhance the q...

1. Enterprises always seek to enhance the quality of service delivered to customers and end users. Justify. 2. Describe briefly the concept of capital budgeting for information

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd