Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

What are the causes of poor industrial relations, What are the Causes of Po...

What are the Causes of Poor Industrial Relations? Purposes of Poor Industrial Relations situation for good IR are as follows: a. Inadequate fixation of wages and wage struct

Internal factors of syringe management , Internal Factors Strengths ...

Internal Factors Strengths Strengths of the Syringe management plan are to increase people's manner to use the syringe. Secondly it would reduce the injury of needle ar

Drawbacks of poor planning and designs, Question 1: Explain why hotel m...

Question 1: Explain why hotel managers today are expected to be well-versed in Facilities Planning and Design Management. What according to you could be the drawbacks of poor

What is a project plan and what does it involve, Q. What is a project plan ...

Q. What is a project plan and what does it involve? A well incorporated project plan is the primary tool for effective coordination of the work and for tracking and steering pr

Project integration management, You work for Point-Of-Sale Solutions (POSS)...

You work for Point-Of-Sale Solutions (POSS), an international point of sale company, which has decided to provide an Internet enabled menu ordering system delivered on the iPad as

Benefits of Group Technology, Benefits of Group Technology 1.Reduced F...

Benefits of Group Technology 1.Reduced Flow Times: Compared to the earlier process layout, there are very few halts. Hence flow times are reduced considerably. 2.Process Tim

Explain the levels of conventional planning, Question: (a) A team is ...

Question: (a) A team is any group of persons organised to work together or interdependently in order to cooperatively meet the needs of their customers by accomplishing a pu

Explain about the implementation phase, Explain about the implementation ph...

Explain about the implementation phase. Implementation phase: The project takes shape throughout the implementation phase. It includes the construction of the real projec

What is the role of strategy in project management, Problem 1: a) What ...

Problem 1: a) What is the role of strategy in project management? b Explain the importance of aligning H.R projects with the organizational strategy. c) What are the impa

Histograms, H i stograms Histograms show a visual summary of the data...

H i stograms Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd