Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Objectives of quality control, To assesses the quality of the raw materials...

To assesses the quality of the raw materials semi finished goods and finished products at various stages of production process. To see whether the product conforms to the predet

Linear Programming Problem, Maximize Z= 3x1 + 2X2 Subject to the constraint...

Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Change in scope of statement, Q. Brandi is working as a project manager on ...

Q. Brandi is working as a project manager on a software project. About halfway through development, her team concludes that they had not estimated enough time for some of the techn

Tools for collecting data, T ools for collecting data Improper or inco...

T ools for collecting data Improper or incomplete collection of data is a fundamental error which has an effect on all the subsequent actions. Data may be collected at the tim

Project management and leadership, Scenario Even ‘well run' organisations c...

Scenario Even ‘well run' organisations can fail to stay atop of their industries when they are challenged by certain market or technology change. Change is an imminent part of busi

Corporate strategy of a multi-business organisation, Strategy is developed ...

Strategy is developed at different levels in large organisations. The process starts with the corporate strategy which is then translated into the strategy for the business divisio

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

Basic control elements in generic projects, QUESTION Implementation sh...

QUESTION Implementation should focus on the achievement of agreed outcomes, so that if a problem is encountered with the plan, other courses of action will be employed. Wha

Define the process of critical path analysis, Define the process of critica...

Define the process of critical path analysis. Process of critical path analysis: 1. Break down project within a logical sequence of activities to be finished. 2. Appro

What is culture of organisation where study and work done, Consider the org...

Consider the organisation which employs you or where you study. What is the culture of this organisation? Why does this have that exacting culture? What organisational culture woul

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd