Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Define product mix, Problem Define Product mix. Explain the factors det...

Problem Define Product mix. Explain the factors determine the decisions of the Product mix. Factors: Expansion of Product mix Contraction of Product mix Alteration

Syndicate report and presentation, A 2000 word report due electronically 12...

A 2000 word report due electronically 12 pm Wednesday 13 May for those presenting findings in Week 11 or 12 pm Wednesday 20 May for those presenting findings in Week 12) This wi

Why does the public sector exist, Question 1: a) Why does the public s...

Question 1: a) Why does the public sector exist? b) Discuss 5 ways in which the public sector is different from the private sector. c) The public sector is a clo

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Steps of heuristic method, Steps of Heuristic Method The heuristic ap...

Steps of Heuristic Method The heuristic approach involves following procedural steps: Identify the work ( job) Break down the work into elemental tasks or steps for

Internal factors of syringe management , Internal Factors Strengths ...

Internal Factors Strengths Strengths of the Syringe management plan are to increase people's manner to use the syringe. Secondly it would reduce the injury of needle ar

Entities and variables, There are three main entities in our model. There i...

There are three main entities in our model. There is Ambulance Patients entity which represents all patients coming to the hospital by ambulance cars. The second entity indicates t

Determine what are the delphi technique, The Delphi technique intends to at...

The Delphi technique intends to attain a consensus evaluates by the efforts of a number of estimators. How is this attained and what is the advantage of the Delphi technique over,

State the principle of extrapolating, The analysis effort and programming m...

The analysis effort and programming methods both rest onto the principle of extrapolating the total development effort by detailed evaluates of one phase of the project. Define the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd