Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

How do i get my project organized, Q. How do I get my project organized? ...

Q. How do I get my project organized? Every project that involves surplus to one person requires a project team to get the work done. With no doubt building a motivated project

PMP, critical analysis of the pmp

critical analysis of the pmp

Work breakdown structure, Work breakdown structure: The work breakdown ...

Work breakdown structure: The work breakdown structure, as its name suggests, represents an organised and logical break down of the project into its component parts. Thus break

Outline at least three steps common to pert and cpm, QUESTION (a) Feasi...

QUESTION (a) Feasibility Study is a preliminary study undertaken before a real work of a project start what factors should the project manager take into consideration while con

What are the contents of project planning document, What are the contents o...

What are the contents of project planning document? Contents of a PPD (project planning document): a. Project resource plans b. Quality control and quality policies proce

Project risk profile owners, Project risk profile owners  Project risk ...

Project risk profile owners  Project risk profile owners must make sure that they deal with each and every risk of the project. The responsibilities of the project risk owners

Management of utilities for a estate complex, Question 1: (i) What are...

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

You are a Project manager at the Department of Public Works, Describe how y...

Describe how you, as a project manager in a Matrix Organisation, will set up your project r=team for the building of the community. Project team members names, and reason why they

Important role that the corporate level strategy, Strategy is developed at ...

Strategy is developed at different levels in large organisations. The process starts with the corporate strategy which is then translated into the strategy for the business divisio

Measures of success of project management, M eas ures of Success The ...

M eas ures of Success The most important objective of project management is to meet or exceed expectations of the sponsors of the project. These prospects are typically expre

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd