Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

How do i get my project organized, Q. How do I get my project organized? ...

Q. How do I get my project organized? Every project that involves surplus to one person requires a project team to get the work done. With no doubt building a motivated project

Relationship between values and behavior, Strong organisational values, eng...

Strong organisational values, engaging vision that is inspirational for employees as well as creating a sense of involvement with effective communication channels.Organizational va

Quantitative layout analysis - correlation chart, Quantitative Layout Analy...

Quantitative Layout Analysis - Correlation Chart  In this technique we draw a gird with rows presenting alternative solutions. Plant item can be a ground floor (G >F) First fl

Determine the supporting project activities for estimate, Describe differen...

Describe different types of supporting project activities for estimating. Estimate the given supporting project activities are as follows: 1.    Project management 2.    Team lea

Project integration management, You work for Point-Of-Sale Solutions (POSS)...

You work for Point-Of-Sale Solutions (POSS), an international point of sale company, which has decided to provide an Internet enabled menu ordering system delivered on the iPad as

What are the risk management strategies, What are the risk management strat...

What are the risk management strategies? Risk management strategies: • Retain the risk (Absorption) as like when the risk is small and won’t influence the project a great de

What are the benefits of project management software, What are the benefits...

What are the benefits of project management software? Project management (PM) software benefits are as follows: a. Project scheduling b. Budgeting and controlling cost

Describe what is a budget process, Question: (a) John Oakland says: ...

Question: (a) John Oakland says: "Day to day issues, often taken for granted, involve quality in some form or other. For example, the safety and conformity with accepted st

Define the process of critical path analysis, Define the process of critica...

Define the process of critical path analysis. Process of critical path analysis: 1. Break down project within a logical sequence of activities to be finished. 2. Appro

Performance management report, Review assignment  and the macro map you pre...

Review assignment  and the macro map you prepared. How are your transformational processes monitored? Identify the critical success factors that are both necessary and sufficien

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd