Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Scope of materials management, Scope  of Materials  Management Material...

Scope  of Materials  Management Materials  management  embraces all  functions  concerning  planning  purchasing  production  control  stores  traffic and physical distribution

Illustrate the term industrial relations briefly, Illustrate the term Indus...

Illustrate the term Industrial Relations briefly? Industrial Relations (IR): Industrial Relations are that aspect of management that deals along with the manpower of the e

Project Environment And Planning Assignment, Ask question #MinimuI am a Mas...

Ask question #MinimuI am a Master degree student in the UK. I am Taking a Master degree course in “Project Management”. I would like to make an order for one of the courses. The co

Process of development, Q. Process of development? Figure shows the pro...

Q. Process of development? Figure shows the process of new product development in the form of a flow chart. As is evident, the process of development starts with the idea gene

JJ Electronics Product Development Case, i need an assignment to be done by...

i need an assignment to be done by microsoft project 2010 . it should contain all details like critical path,and gantt chart etc in .mpp .

Describe the key characteristics of a good project, Question 1: a. How...

Question 1: a. How would you define a project? What are the different types of project that exist? (Please illustrate using a model with examples). b. Enumerate and descri

Commercial project negociation, I want to make a report on this topic by to...

I want to make a report on this topic by tomorrow morniing

Explain about the term management in brief, Explain about the term manageme...

Explain about the term management in brief. Management in words of LAWRENCE APPLEY: “Management is the accomplishment of outcomes by the efforts of many other people”.

Back to school crunch at global green books publishi, what risks can you id...

what risks can you identify? why are they risk to global green books publishing?

Design defect, However proving a design defect can be difficult. Some of th...

However proving a design defect can be difficult. Some of the factors used by the jury to asses s whether a product design is defective and unreasonably dangerous are: 1.The utili

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd