Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

What is the purpose of the post completion review, What is the purpose of t...

What is the purpose of the post completion review? The purpose of a PC (post completion) review: • Assist continuous improvement for example review procedures to design bett

Introduction to syringe management plan, Introduction The project 'Syri...

Introduction The project 'Syringe Management Plan' is created to protect the community against misplace of syringe that causes accidental needle injury. This project is introdu

Define the process of critical path analysis, Define the process of critica...

Define the process of critical path analysis. Process of critical path analysis: 1. Break down project within a logical sequence of activities to be finished. 2. Appro

Define the design phase of the project management, Define the Design phase ...

Define the Design phase of the project management. Design phase:   The list of needs which is developed within the definition phase can be utilized to make design alte

Linear programming methods of line balancing, Linear Programming Methods of...

Linear Programming Methods of Line Balancing Assume that a job is broken down into elements tasks and the total duration of all such tasks is 28 minutes. The cycle time i, e,

521, HUSKY AIR ASSIGNMENT—PILOT ANGELS The Quality Management Pla

HUSKY AIR ASSIGNMENT—PILOT ANGELS The Quality Management Plan

Project management faces a lot of risks, QUESTION a) Major project mana...

QUESTION a) Major project management activities have their operational specificities. List the distinguishing characteristics of a project? b) Project management faces a lot

Benefits of having a clear mission for pv company, T has recently been appo...

T has recently been appointed as the new Chief Executive of PV Company which manufactures cosmetics and toiletries. She has spent the first three months meeting with her senior man

Earliest time the recruitment campaign can start, ST is the operations dire...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

What must be the responsibility of the project manager, What must be the re...

What must be the responsibility of the project manager into relation to the business case? Idyllically, the project manager must be appointed early adequate to give to the deve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd