Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

What are the benefits of doing a job safety analysis, Question: A sewer...

Question: A sewer line is to be connected to a school. This work will be carried out in a 2.4 meters deep excavation and will be routed through the playground, which was once

Changing customer demands and strong competition, In response to changing c...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

Why do i need project management, Q. Why do I need project management? ...

Q. Why do I need project management? One more way of asking this question is What if I do not bother with project management? The reality is all projects demand some extent of

Define the critical path analysis in risk management, Define the critical p...

Define the critical path analysis in risk management. Critical path analysis (CPA) or network analysis: Gantt charts are a poor time management tools while projects are l

Parameters of facilities planning and design, Question 1: Distinguish b...

Question 1: Distinguish between innovation and renovation within the parameters of facilities planning and design. Question 2: Although security and safety at the work

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

Describe problems with functional project coordination, Question 1: "Ma...

Question 1: "Matrix structures are becoming more common and are likely to continue to do so in the future" (Field and Keller, 1998). a) Describe likely problems with functio

Feasibility study for the exploitation of the oil reserves, Question: I...

Question: In the year 2015, the price of petrol has gone up so much that the oil reserves of the Republic of Mauritius start to look interesting to exploit. The oil reserves ar

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

Audits, A udits Audits are independent examinations to determine wheth...

A udits Audits are independent examinations to determine whether processes and procedures achieve the specified objective. They are an essential tool to identify problem areas

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd