Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Procurement , Functions of Purchasing Department

Functions of Purchasing Department

Explain the integration of the work breakdown structure, Question: (a) ...

Question: (a) Risk has always been an intrinsic part of project management. With increasing market competition, technology, and globalization, risk management is continuously

Article delivery over network information system, Article Delivery Over Net...

Article Delivery Over Network Information System (ADONIS): ADONIS is a consortium of biomedical journal publishers that supplies full-text journals on CD-ROM for document deli

Explain dupont formula, While the industry average ROE is about 15%, averag...

While the industry average ROE is about 15%, average profit margin of 50%, asset efficiency of 10%, and leverage ratio of 3, the ROE for ABC, Inc., using data from January 2011, wa

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Marketing project, Step 1 Advise the instructor in writing if you will be w...

Step 1 Advise the instructor in writing if you will be working on the project individually or with another class member(s). Choose your team member (s),carefully, as you will have

Pareto charts, P areto charts It is a very helpful tool to identify th...

P areto charts It is a very helpful tool to identify the greatest opportunity for improvement among  various  possibilities  and  to  identify  the  small number  of  most inf

Explain the different service delivery gaps, Question: (a) The findings...

Question: (a) The findings of Parasuraman et al have demonstrated that there are gaps in the service delivery leading to several misunderstandings between customer expectations

Project, can make two project for me?

can make two project for me?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd