Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Lack of specialized supervision, Lack of Specialized Supervision There...

Lack of Specialized Supervision There will be greater difficulty in securing specialized supervision. Because line layout consists of several machines requiring a wide range o

Why is project monitoring important, Question: (a) Why is project monit...

Question: (a) Why is project monitoring important? (b) Outline the aspects you would check in a project monitoring meeting? (c) What corrective actions can be taken in th

Critical analysis, Need to get critical analysis of the Document, Project M...

Need to get critical analysis of the Document, Project Management Body of Knowledge 1996 by the Standard committee of the PMI 8 pages. how much would this cost?

Crucial component of project management, Question: (a) Describe why ris...

Question: (a) Describe why risk management is a crucial component of project management. (b) Critically show the different responses to risks that should be developed ear

How could huge supermarket chain use in information system, When you knew a...

When you knew about an organisation’s strategy, that could you suggest IS applications which would support this? For illustration, how could a huge supermarket chain utilize inform

Explain about the term project planning document, Explain about the term pr...

Explain about the term project planning document. A project planning document (PPD): Project planning document will usually consist of a project technical and resource pl

Implementation of a quality program, Question: (a) Any project has a be...

Question: (a) Any project has a beginning and an end; without a formal closure process, project teams can fail to recognize the end and this can drag the project into unnecessa

State the principle of extrapolating, The analysis effort and programming m...

The analysis effort and programming methods both rest onto the principle of extrapolating the total development effort by detailed evaluates of one phase of the project. Define the

Contract process cycle , Contract process cycle  Contract process goes ...

Contract process cycle  Contract process goes through the following stages to complete the contract documentation cycle:    Pre tender documentation stage.    Approval

PMP, A good leader is not necessarily a good manager.” Discuss this stateme...

A good leader is not necessarily a good manager.” Discuss this statement & compare leadership With management.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd