Types of cross-drainge structures, Civil Engineering

Assignment Help:

Types of Cross-drainage Structures:

The following are the types of cross-drainage structures :

(a) Culverts, having waterway upto 6 m.

(b) Minor Bridges, having waterway in the range of 6-30 m.

(c) Medium size Bridges, having waterway in the range of 30-100 m.

(d) Major Bridges, having waterway greater than 100 m.

(e) Paved dips and Causeway which allow water to flow over the roadway.


Related Discussions:- Types of cross-drainge structures

Calculate the percent grade of line, 1. The topography of a local valley is...

1. The topography of a local valley is shown. The horizontal distance between point P and Q is 11,456-ft. The percent grade (%) of line P-Q .     2. Based on the info

Fluid mechanics , i have three civil engineering fluid mechanics. 1 manomet...

i have three civil engineering fluid mechanics. 1 manometer problem 2 estimate the discharge for a channel 3 pipe system - direction of flow in line and what the value of flow in l

Chain surveying, Explain me about obstacles in chain surveying and what is ...

Explain me about obstacles in chain surveying and what is meant by cross staff,offsets?

I am expert i this field, i require a workquestion #Minimum 100 words acce...

i require a workquestion #Minimum 100 words accepted#

Measurement of cement and aggregates, Measurement of cement and aggregates ...

Measurement of cement and aggregates - by weight vs. by volume Measurement of constituents for concrete is usually carried out by weight since of the following reasons: (i)

Surveying, Distance ABC was measured with a 30m. Chain tested and found to ...

Distance ABC was measured with a 30m. Chain tested and found to be correct in the beginning of the work .after measuring AB=1.2 km chain was found to be 10 cm. To long chaining was

Types of surveys and investigations, Types of Surveys and Investigations: ...

Types of Surveys and Investigations: For preparing a good road project, the following surveys and investigations are needed: (a)        Traffic Surveys (b)       Topogr

Calculate roller production, Calculate Roller Production An excavating ...

Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd