Treatment plant - sewer construction, Civil Engineering

Assignment Help:

Treatment plant - sewer construction:

Problem:

How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant?

Solution

An amount of solids processed from the basic sedimentation tanks equals the variance in suspended solids concentrations measured across the sedimentation tanks multiplied by the plant flow rate. Thus,

33.75 × 106 l/day (200 mg SS/l - 100 mg SS/l) × kg/1,000,000 mg = 3375 kg primary solids per day.

We are not provided with the concentration difference of suspended solids across the secondary sedimentation tanks so we can determine the amount of secondary solids produced daily in the same manner that we used for primary solids. Therefore, careful examination of the expression of solids retention time displays in which the term Qw Xw could be estimated as the following:

4 days = V =X/Qw×Xw = 5,000,000 l (4,300 mg SS/l)/Qw × Xw

Solve for Qw Xw which equals 5375 kg or say 5400 kg secondary dry solids per day.


Related Discussions:- Treatment plant - sewer construction

Calculate roller production, Calculate Roller Production An excavating ...

Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in

Steel work design, 1) A building constructed from steelwork requires the fo...

1) A building constructed from steelwork requires the following sections to be designed: a. A beam carrying a characteristic permanent load of 11kN/m and a characteristic variable

Strength of rivet joints, Ask question #Minimum 100 Please help me to...

Ask question #Minimum 100 Please help me to write a c program to determine strength and efficiency of single cover butt joint, lap joint, double cover butt joint . words ac

#title Design a gravity-flow sanitary sewer , i have to Design a gravity-f...

i have to Design a gravity-flow sanitary sewer to serve and i need it to be done asap

Timber, charring of timber

charring of timber

Water control for sheet pile walls, Q. Water control for sheet pile walls? ...

Q. Water control for sheet pile walls? Ground water flow into excavations constructed by sheet pile walls must be minimized in order to save the cost of the provision of pumpin

Describe about the prestressed concrete, Describe about the Prestressed con...

Describe about the Prestressed concrete Civil engineering structures, such as buildings, bridges, dams, towers etc. and their structural components such as beams, columns, slab

Helical reinforcement designed instead of regular links, Question For colum...

Question For column reinforcements, why is helical reinforcement sometimes designed instead of regular links with reasons? Answer The utilization of links for column designi

What are the causes of building collapse, The Passage of time is single rea...

The Passage of time is single reason. Buildings also collapse because of weak foundations. Earthquakes, hurricanes and other natural disasters can also damage the structure of the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd