Transportation method, Operation Management

Assignment Help:

Transportation  Method

We  solve the transportation  problem using the followings steps in order:

a. Structuring the problem  into the  transportation  framework.

b. Finding an initial solution.

c. Moving from the initial  solution  to th e optimal solution suing the transportation  algorithm of the transportation  method & if solution  is not optimal.

d. Revising the solution  until an  optimal  solution is obtained.

Step1 :L Structure  the problem into  transportation framework  as explained in the  followings.

First  of all the given  information  can be  put into  the transportation  framework  as under:

2317_Transportation  Method.png

The  above  solution indicate  that first  of  we have  transport 13 units  to warehouse A from factory X and Y this way the demand of warehouse A is met with. The remaining  2 units  at factory X are Sent to warehouse Y and this meet the demand of warehouse B only partially but the  supply  of factory X is exhausted. Then  we take the supply  available at factory Y and  from it transport 10 units  to warehouse  B thereby meeting it demand completely and the remaining 14 units are sent to warehouse  C. Then  we take the supply  at factory Z and  from it  we send 2 units  to warehouse C and the remaining 19  units to warehouse D. This way we meet the requirement of all warehouse from  the available supply  at various  factories without  considering the cost factor. The  initial solution has been shown the above  table. The relevant transportation cost of this initial solution will  be as under:

1765_Transportation  Method1.png

Cost of transportation 13 units  from X to A @ Rs. 3 per  units   =Rs. 39

Cost of transportation 2 units  from X to AB@ Rs. 2 per  units   =Rs. 40

Cost of transportation 10 units  from Y to B @ Rs. 1 per  units  = Rs. 10

Cost of transportation 14units  from Y to C @ Rs. 4 per  units   = Rs.56

Cost of transportation 2 units  from Z to C@ Rs. 4per  units     = Rs. 80

Cost of transportation 19 units  from Z to C@ Rs. 4per  units   =  Rs. 57

                                                                                     Rs. 174

Warehouse

1765_Transportation  Method1.png

Total transportation cost if  the initial  transportation  schedule is adopted = Rs. 174


Related Discussions:- Transportation method

Mba0038, explain strategy as an organizational process

explain strategy as an organizational process

Explain assignment of contract rights, What is the difference between assig...

What is the difference between assignment of contract rights and delegation of contract duties? Illustrate your answer with examples.

How global businesses subscribe to a global code of conduct, Do you think g...

Do you think global businesses would be willing to subscribe to a global code of conduct?

Explain each component and final scissor assembly, Prepare an MRP for sciss...

Prepare an MRP for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. 634 pairs of scissors are needed on Day 6. No

Explain draw the project network using aon, Task time estimates for a produ...

Task time estimates for a production line setup project at Robert Klassens Ontario factory are as follows: Activity Time (in hours) Immediate Predecessors A 6.0 B 7.2 C 5.0 A D 6.0

Find how much does the airport need to set aside now to pay, Orlando Intern...

Orlando International Airport plans to extend passenger capacity of its existing terminal to accommodate its forecasted growth. A new terminal would be needed once the state's busi

Explain disadvantages of functional systems and briefly, In this case study...

In this case study, you will review a case involving a functional system. The Lynx Company uses a functional system for their sales system. It takes the orders from their salesm

Transportation problem, Calculate row or column penalty we take two values ...

Calculate row or column penalty we take two values namely the minimum and 2nd minimum? If 4 4 5 occurs in a problem, we choose 4 as a minimum and 5 the 2nd minimum why not another

Describe henry did tax work for joe electrician, Henry did tax work for Joe...

Henry did tax work for Joe electrician. Bill was $900, Hnery reduced it to $600. Joe did wrok for Henry at cost of $700. Henry gave Joe a check for $400, said remaining $300 was th

Operations Theories., Choose an Operations Management problem relating to a...

Choose an Operations Management problem relating to an organisation of your choice and undertake a critical review.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd