Transitional jacks designed in pipe jacking projects, Civil Engineering

Assignment Help:

Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Define major ions present in the water, Define Major Ions present in the wa...

Define Major Ions present in the water  Cations:  Calcium, Magnesium, sodium, potassium Anions: Bicorabonate, sulfate, chloride Other ions present: Iron. Manganese, Fluor

Survey.., collect the field deta manualy and drw the drawing as per scale

collect the field deta manualy and drw the drawing as per scale

Define mechanical tool for underwater inspection of bridge, Define Mechanic...

Define Mechanical tool for underwater inspection of bridge? Mechanical devices that involves a Schmidt Test Hammer for computing concrete surface hardness, and rotary coring eq

Surveying, define principles of survey

define principles of survey

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

Cement, List the ingredients of cement And their functions

List the ingredients of cement And their functions

Evaluate the length of guide bund, Q. Evaluate the Length of guide bund? ...

Q. Evaluate the Length of guide bund? For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream

Compute the skin friction resistance, A 30 cm diameter pile penetrates a de...

A 30 cm diameter pile penetrates a deposit of soft clay 9 m deep and rests on sand. Compute the skin friction resistance. The clay has unit cohesion of 0.6 kg/cm 2 . Suppose

Whole base of mat, Question In modeling a nonrigid mat foundation by us...

Question In modeling a nonrigid mat foundation by using elastic springs, have a uniform modulus of subgrade reaction be used along whole base of mat ? Answer A bed of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd