Transitional jacks designed in pipe jacking projects, Civil Engineering

Assignment Help:

Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Aluminium sliding window detail drawings, what are the details of aluminium...

what are the details of aluminium sections and how are they connected for making a door or window

Theory of elasticity and plasticity, derivation for strain energy stored in...

derivation for strain energy stored in a body due to torsion

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Afflux in rivers with non scourable bed, Q. Afflux in rivers with non scour...

Q. Afflux in rivers with non scourable bed? Afflux is defined as rise of flood level of the river upstream of a bridge as a result of the obstruction to natural flow caused by

Plants aeration period, Plants aeration period: Problem: What i...

Plants aeration period: Problem: What is the plant's aeration period? Solution The plant's aeration period is the number of hours that the wastewater is aerated

#civil, what is whole circle barring

what is whole circle barring

Softening test point, the importance of softening point of a bitumen materi...

the importance of softening point of a bitumen material in the design of a pavement

Stop dead restriction, With a clear sketch indicate the system of protectio...

With a clear sketch indicate the system of protection of line for works of short duration where ‘ Stop dead restriction' need to be observed on a single line section on a BG track.

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd