Traffic Surveys:

The following traffic surveys are needed for preparing a good road project:

Classified Volume Counts

This survey is normally carried out for 7 days, 24 hours a day. The number of vehicles of different types is counted:

PCU Factor

Cars/jeeps, vans                                                                  1

Two-wheelers                                                                       0.5

Three-wheelers                                                                     0.75

Light Commercial Vehicles/Agricultural Tractor         1.5

Buses                                                                                      3

Heavy Commercial Vehicles                                             3

Multi-axled Vehicles                                                           4.5

Tractor-trailers, Truck trailers                                            4.5

Cycles                                                                                                0.5

Cycle rickshaws                                                                   2.0

Bullock carts                                                                         6.0

Horse carts                                                                            4.0

The PCU factor (Passenger Car Unit) is the multiplying factor for each class of vehicle to express the traffic in PCUs per day.


Related Discussions:- Traffic surveys

Write briefly for trolley permits, Q. Write briefly for Trolley Permits? ...

Q. Write briefly for Trolley Permits? It is the permit given to the Moter Trolley / Push Trolley, Cycle / Moped Trolley. It is essential to have Trolley Permit before taking t

Cargo handling facilities, Cargo Handling Facilities: All water transp...

Cargo Handling Facilities: All water transport terminals require cargo handling facilities. Cranes of various sizes are used. In docks, traveling cranes are popular (Figure).

Sinle flumesh bound.., ADVANTAGES AND DISADVANTAGES OF SINGLE FLUMESH BO...

ADVANTAGES AND DISADVANTAGES OF SINGLE FLUMESH BOUND

Use single lock nuts or double lock nuts, Question In linking fenders t...

Question In linking fenders to pier organizations, would single lock nuts or double lock nuts be used? Answer In pier structures connection offenders to piers is a

Standard mixes of concrete, In some nations such as Britain, specification ...

In some nations such as Britain, specification for concrete doesn'tusually require cube tests for standard mixes of concrete. Quality control of standard mixes in Britain is achiev

Zeroth law of thermodynamics, Two systems which are equal in temperature to...

Two systems which are equal in temperature to a third system are equal in temperature to each other

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd