Traditional marine piling system of steel tubular pile, Civil Engineering

Assignment Help:

Question

What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures?


Answer

In designing of marine piles of steel tubular piles with concrete infill, loads from pier deck are occupied up by steel tubular piles before occurrence of corrosion of steel piles above seabed. It is assumed that steel piles above seabed level will all be corroded after a sure year. Load transfer mechanism after complete corrosion of steel pile over seabed is as follows-

Loads from pier deck are taken up by concrete infill above seabed level. Below seabed level, loads would be transferred to steel piles through frictional forces between concrete infill and steel casings.

Yet, substantial radial shrinkage and contraction arises after concreting of concrete infill and this would hinder load transfer from the concrete infill to steel piles because bond might be ruptured by radial shrinkage. It is in hesitation if frictional forces be able to be correctly developed in this situation. To solve this problem, shear keys can be installed at normal spacing inside steel piles to ensure their rigid connection with concrete infill. Alternatively, expanding agents could be adopted in concrete mixes to make sure that there is no shrinkage after concreting process.

 


Related Discussions:- Traditional marine piling system of steel tubular pile

Underwater inspection procedures - inspection of bridge, Explain the Underw...

Explain the Underwater inspection procedures - inspection of bridge? Under-water bridge inspection, especially the initial inspection, requires careful planning to ensure that

Use of PFA and GGBS, Q. Use of PFA and GGBS? Both PFA and GGBS are by-p...

Q. Use of PFA and GGBS? Both PFA and GGBS are by-products of industry and use of them is ecologically friendly. Most significantly, with PFA and GBS adopted as partial replacem

Screw pumps and pump trough, Question In structure of pump troughs for ...

Question In structure of pump troughs for accommodation of screw pumps, what is major construction process to ensure close contact between screw pumps and pump trough ? An

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

Modern trends in transportation, Modern Trends in Transportation: Rapi...

Modern Trends in Transportation: Rapid urbanization that is taking place in India is putting severe strain on the road system. Modern systems like exclusive bus lanes, light r

Bituminous macadam, What is the working capacity of a road paver per hour f...

What is the working capacity of a road paver per hour for bituminous macadam

Angular messurement using total stations, write a short note on angular mes...

write a short note on angular messurement using stations?

Reciprocal ranging, what do you mean by reciprocal ranging explain with a n...

what do you mean by reciprocal ranging explain with a neat sketch

Define hammer efficiency and coefficient of restitution, Q. Define Hammer e...

Q. Define Hammer efficiency and coefficient of restitution? Hammer efficiency refers to ratio of kinetic energy of hammer to the rated energy (or potential energy). Basically i

Paint, Description of paint

Description of paint

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd