Project specifications require a relative compaction of 95% (modified Proctor). Construction of a highway embankment requires 10,000-yd3 of fill. The borrow soil has an in-situ dry density of 94-PCF and a laboratory maximum dry density of 122.5-PCF. The total volume of soil that must be excavated from the borrow area is most nearly:
Solution: The most common method of assessing the quality of field compaction is to calculate the Relative Compaction (RC) of the fill, defined as:
RC = 100 * (field dry density, PCF) / Laboratory maximum dry density (PCF)
Apply the equation using the given data:
RC = 100 x 94-PCF / 122.5-PCF = 76.73%
Calculate the required volume of soil that must be excavated from the borrow area:
(Required Fill) x (Compaction %) x (Relative Compaction)-1 = Excavated Volume (borrow)
10,000-yd3 of fill x (95%) x (76.73%)-1 = 12,380-yd3
how does vectors apply mathamatical in civil engineering
Explain the important factors affecting the design of pavement?
Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi
Q. Show the Design of Howe truss? Design of Howe truss is the opposite to that of Pratt truss in that the diagonal members are slanted in the direction opposite to that of Prat
what are the basic two division of surveying
Question For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement? Answer Becau
Q. Constriction of waterway at bridges? Constriction of waterway at bridges is effected by extending the approach banks to cover spill area or, in addition, part of active chan
triangle of force
Concrete Mix Design: Concrete mix design is done in a laboratory to achieve the desired strength and workability. The mix design is done to achieve strength slightly higher t
Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd