Total volume of soil that excavated from the borrow area, Civil Engineering

Assignment Help:

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd3 of fill.  The borrow soil has an in-situ dry density of 94-PCF and a laboratory maximum dry density of 122.5-PCF.  The total volume of soil that must be excavated from the borrow area is most nearly:

Solution: The most common method of assessing the quality of field compaction is to calculate the Relative Compaction (RC) of the fill, defined as:

RC = 100 * (field dry density, PCF) / Laboratory maximum dry density (PCF)

Apply the equation using the given data:   

RC = 100 x 94-PCF / 122.5-PCF = 76.73%

Calculate the required volume of soil that must be excavated from the borrow area:  

(Required Fill) x (Compaction %) x (Relative Compaction)-1 = Excavated   Volume (borrow)

 10,000-yd3 of fill x (95%) x (76.73%)-1 = 12,380-yd3

 


Related Discussions:- Total volume of soil that excavated from the borrow area

What is the role of sunfilter in building, QUESTION (a) Using an illu...

QUESTION (a) Using an illustration, describe what happens to sunrays when it passes through the atmosphere to reach the ground. (b) What is the role of a sunscreen/sunfil

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

Define reactivity - hazardous waste, Define Reactivity - Hazardous Waste ...

Define Reactivity - Hazardous Waste - Undergoes violent Change w/o detonating - reacts violently with water - Forms potentially explosive mixtures with water - generat

Foundation, What are different type of foundation and their suitablity

What are different type of foundation and their suitablity

Define the concept of creep of concrete, Define the concept of Creep of Con...

Define the concept of Creep of Concrete Creep of concrete is another important characteristic. It represents progressive strains in concrete which occur at constant value of st

Column estimat, how maney point in columan parking estimate

how maney point in columan parking estimate

Packing resources in joint of concrete pipes in pipe jacking, Question ...

Question What is key function of packing resources in joint of concrete pipes in pipe jacking ? Answer Packing resources are about 10 to 20mm broad and are usually mad

#title.roads., metal sizes required and adopted question #Minimum 100 words...

metal sizes required and adopted question #Minimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd