Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain what is the total cost of this policy, Rocky Mountain Tire Center s...

Rocky Mountain Tire Center sells 20,000 go-cart tires per year. The ordering cost for each order is $40, and the holding cost is 20% of the purchase price of the tires per year. Th

Explain competitors can be inferred by demonstration, Security Services, In...

Security Services, Inc. and Redline Protectors were the two predominant providers of home alarm systems in the Dallas area. They had become the two big businesses after the smaller

Explain city water supply system, The network in figure below shows the pip...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant (node 1) to a city water supply system (node 14). The arc capacities

Explain investment triple itself, At what rate of interest, compounded annu...

At what rate of interest, compounded annually, will an investment triple itself in (a) 8 years ? (b) 10 years? (c) 12 years?

Explain what do you think sally should do, Case 2 Individual or Team Reward...

Case 2 Individual or Team Reward? Jack Hopson has been making wood furniture for more than ten years. He recently joined Metropolitan Furniture and has some ideas for Sally Boston,

Principle of scheduling, Principle of Scheduling First Principle optim...

Principle of Scheduling First Principle optimum Task Size : scheduling tens to achieve its maximum efficient task sizes are small and all tasks are of the same order of magnit

Explain the standard working time, To determine the standard working time f...

To determine the standard working time for a special job, following observation data is collected. Observation 1 2 3 4 5 6 7 8 Time (in second) 17 18 15 14 13 15 16 13 a) If the pe

Assess the vital of completing post-project reviews, Assess the importance ...

Assess the importance of completing post-project reviews, and determine what project documentation must be updated as the result of the review meeting. Discuss the risks associated

Why user should be involved design of the database, We are agree that the u...

We are agree that the user should be involved in the design of the database. Class, how would you go about the process of designing a database? What processes are involved? And ple

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd