Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Describe how many bags per run are optimal, A chemical firm produces sodium...

A chemical firm produces sodium bisulfate in 100-pound bags. Demand for this product is 20 tons per day. The capacity for producing the product is 50 tons per day. Setup costs $100

Hill approach to manufacturing operations, Hill Approach to Manufacturing O...

Hill Approach to Manufacturing Operations - Operation Management  Hill's five step approach to developing manufacturing operations illustrated in table below (Hill, 1993). A

What are the characteristics of total quality management, Q. What are the c...

Q. What are the characteristics of total quality management? Characteristics of total quality management: 1. Get this right first time philosophy 2. Continuous enhancemen

Explain is not one of the three types of specifications, Which of the follo...

Which of the following is not one of the three types of specifications discussed in the text? Answer Design specifications Material specifications Performance specifica

Location analysis, explain the series of steps involved and various factor...

explain the series of steps involved and various factor effecting location decion?

Lean Synchronisation, Examples of organisations that practice Lean synchron...

Examples of organisations that practice Lean synchronisations

Explain each component and final scissor assembly, Prepare an MRP for sciss...

Prepare an MRP for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. 634 pairs of scissors are needed on Day 6. No

Explain why is strategic management critical to the success, Why is strateg...

Why is strategic management critical to the success of an organization in meeting its goals and mission?

Flexible work schedules in their organizations describe, What can HR manage...

What can HR managers do to help facilitate flexible work schedules in their organizations?

Sequencing Method, Please Give question & answer of Sequencing Method Solut...

Please Give question & answer of Sequencing Method Solution

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd