Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
The supplier is reliable and maintains a constant lead time of 5 days. The cost of placing an order is $10 and the cost of holding inventory is $0.50 per unit per year. There are n
1. Show graphically, and explain, the relationship between the different levels of management, types of problems, and types of decisions. What do we mean by the term "bounded ratio
A grocery store needs to sell 3,000 cartons of 2L 2% milk per month. The sales is relatively constant throughout the month. The owner of this grocery store purchases milk from a su
Type your question here Four-step process for setting a price on a product, and using 2,000 custom-printed t- shirts as your product (at a cost of $12.25 each to produce), calculat
Why is basic instruction valuable? When should it be used?
Calculate the minimum replenishment time to build 2500 Model A fountains given the following beginning inventories?
The project manager is normally directly accountable for the project result, schedule and budget.
1. What are the key characteristics that would classify Wheeled Coach as a repetitive focus process strategy? 2. Let's assume you are a new hire at Wheeled Coach. Your manager a
How would an OD (organizational practitioner) attempt to change an organizations culture?
Ask que Prepare Paul Jordan’s report to John Smithers using regression analysis. Provide a summary of the cell phone industry outlook as part of Paul’s response. stion #Minimum 100
Line Balancing- Line: an assembly line composed of various work stations, at which particular operations are performed.- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.Goals:1. To meet production goals,2. Maximize output.General Approaches to Line Balancing Technique1. Estimating number of operators for a specific number of stations,2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)
Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.When is line Balancing is Done· When the line is initially set-up· When the changes are made in process / desired output rateDifficulty associated with LB – Not feasible to combine certain activitiesNecessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously(Draw Precedence Diagram)Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)CT = 1 min(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 WorkstationsRules in Assigning task1. Choose new WS ifa. All preceding tasks are completedb. Task Time is less than or equal to Time Remaining2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.3. For every new WS, always start with cycle timeWS Time Remaining Eligible Assign Task Revised Time remaining WS Idle Time1 1.0 A,C C(0.7) 0.3 (1.0-0.7) 0.3 A A(0.1) 0.2 0.22 1.0 B B(1.0) 0 03 1.0 D D(0.5) 0.5 0.5 E E(0.2) 0.3 0.3Total Idle time = 0.2 + 0.3 = 0.5 minutesBalance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)=0.5*100/(3*1) = 16.7%Line efficiency = 100% - Balance delay% = 83.3%Other considerations in line-balancing1. Technical considerations –a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstationb. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other2. Variable tasks by human –a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.b. Absenteeism can also affect the balanceOther approaches to achieve smooth flow of production1. Make parallel workstations – They increase the workflow and provide flexibility2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd