Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
1. A stock out occurs when an item that is typically stocked is not available to satisfy a demand the moment it occurs. 2. A backorder occurs when a customer order cannot be fil
One day a teller of a bank was robbed. When the robber ran the teller ran after him. Well over taking the robber, the teller was shot in the leg. The teller was given an award for
At a border vehicles arrive at the rate of 9 per minute in a Poisson distribution. For simplicity in this problem assume that there is only one lane and one inspector who can inspe
Scenario 2: A supervisor discovers a design flaw, which she believes is a safety hazard. She informs the company through the proper channels. The company declines to correct the fl
would you give an example ? haw it calculate.?
National Scan, Inc., sells radio frequency inventory tags. Monthly sales for a seven-month period were as follows: Month/Sales (000) Units Feb 16 Mar.17 Apr. 11 May. 29 Jun. 19 Jul
do you have a writer in area of category management from procurement and contracting perspective ? phD level
Explain Lead Time. Lead Time : Lead Time is the time that takes the stock to reach from Re-order point to minimum stock level. This may be also defined as the time as elapses
Which of the following rules maximizes the number of orders processed in a center and minimizes the number orders waiting in the queue? Shortest operation next First-come/fir
How do I find solutions to questions in operations management 10th edition by jay heizer?
Line Balancing- Line: an assembly line composed of various work stations, at which particular operations are performed.- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.Goals:1. To meet production goals,2. Maximize output.General Approaches to Line Balancing Technique1. Estimating number of operators for a specific number of stations,2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)
Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.When is line Balancing is Done· When the line is initially set-up· When the changes are made in process / desired output rateDifficulty associated with LB – Not feasible to combine certain activitiesNecessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously(Draw Precedence Diagram)Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)CT = 1 min(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 WorkstationsRules in Assigning task1. Choose new WS ifa. All preceding tasks are completedb. Task Time is less than or equal to Time Remaining2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.3. For every new WS, always start with cycle timeWS Time Remaining Eligible Assign Task Revised Time remaining WS Idle Time1 1.0 A,C C(0.7) 0.3 (1.0-0.7) 0.3 A A(0.1) 0.2 0.22 1.0 B B(1.0) 0 03 1.0 D D(0.5) 0.5 0.5 E E(0.2) 0.3 0.3Total Idle time = 0.2 + 0.3 = 0.5 minutesBalance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)=0.5*100/(3*1) = 16.7%Line efficiency = 100% - Balance delay% = 83.3%Other considerations in line-balancing1. Technical considerations –a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstationb. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other2. Variable tasks by human –a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.b. Absenteeism can also affect the balanceOther approaches to achieve smooth flow of production1. Make parallel workstations – They increase the workflow and provide flexibility2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd