Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain what is the negative impact on that stakeholder, Which stakeholders...

Which stakeholders that was affected by the bp spill situation in America. What is the negative impact on that stakeholder?

Explain differentiate between validity and reliability, Differentiate betwe...

Differentiate between validity and reliability of a selection test. In other words, provide definitions of (1) validity and (2) reliability of a test.

Explain the categories of problems in six sigma methodology, Describe the c...

Describe the categories of problems that have been found to be approached by Six Sigma methodology Type your question here

Define what would the average inventory be for this lot size, A chemical fi...

A chemical firm produces sodium bisulfate in 100-pound bags. Demand for this product is 30 tons per day. The capacity for producing the product is 50 tons per day. Setup costs $100

Small organizations or large organizations differ in design, How do small o...

How do small organizations and large organizations differ in design?

Explain accommodations for employees with mental illness, What do you think...

What do you think constitutes reasonable accommodations for employees with mental illness? Please support your responses. cited and reference. Is there a place in the workforce for

When manager focus the progress of an affirmative action, when manager moni...

when manager monitors the progress of an affirmative action program to advance minorities within the corporation; reviewing progress on changing in staff attitude; calls a special

Define why is project management popular tool in recent year, Why is projec...

Why is project management popular tool in recent years?

Explain a principle within a health care organization, What is a principle ...

What is a principle within a health care organization?

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd