Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain what is the forecast error, The numbers of patient arrivals to the ...

The numbers of patient arrivals to the ER department at a local hospital for the past 5 weeks are: week: 1 , 2 , 3 , 4 , 5 arrivals: 405 ,420 , 400 , 380 , 411 a) Compute a three-w

Span of process - process design, 1. What 'span of process' choices do you ...

1. What 'span of process' choices do you think have been made by the Graduate School of Business? Answer: Most core administrative processes are carried out by GSB staff; some,

Compute expected value for the add assembly line option, Howard Weiss, Inc....

Howard Weiss, Inc., is considering building a sensitive new airport scanning device.His managers believe that there is a probability of 0.40 that the ATR Co. will come out with a c

Transportation problem, Calculate row or column penalty we take two values ...

Calculate row or column penalty we take two values namely the minimum and 2nd minimum? If 4 4 5 occurs in a problem, we choose 4 as a minimum and 5 the 2nd minimum why not another

Explain project management body of knowledge, Definition of a Project" •Acc...

Definition of a Project" •According to the Project Management Body of Knowledge (PMBOK), explain one of the major knowledge areas and why it is important to project management. Eva

Explain conscience in spite of the consequences, Suggest some reasons why a...

Suggest some reasons why a person may go against his /her conscience in spite of the consequences. Provide examples with your response.

What is pension plan funding, What are four safeguards that the ERISA legis...

What are four safeguards that the ERISA legislation specified to address the many obstacles employees faced with pension plan funding? How did the Pension Protection Act add additi

Evolutipn of operation management, discuss the evolution of operations mana...

discuss the evolution of operations management in the last 10 years

Explain how much water can be transported per hour, The network in figure b...

The network in figure below shows the pipeline transportation system for treated water from the treatment plant to a city water supply system. The arc capacities represent millions

What liabilities does gm have towards its employees, What responsibility do...

What responsibility does GM have towards its employees? Does GM have the same responsibility to the employees of its suppliers?

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd