Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain what the average inventory be for this lot size, 1.What would the a...

1.What would the average inventory be for this lot size? (Round your intermediate calculations to 2 decimal places and final answer to the nearest whole number.) 2. Determine th

Explain could speed up a floor buffing machine, Consider this situation: Jo...

Consider this situation: Joseph had an idea that he could speed up a floor buffing machine by putting a different motor on it. After about 25 tries he was able to make a buffer run

Explain what is the agency problem, What is the agency problem? What steps ...

What is the agency problem? What steps can be taken to solve it? Why is it important for managers and organizations to behave ethically?

Determine the implementation of lean, 1. To what extend does lean manufactu...

1. To what extend does lean manufacturing help GM to control production to meet customer needs, and how does this help to make GM competitive? 2. Do you think the implementation

Explain proposed investment in the warehouse extension, What overall recomm...

What overall recommendations would you make to Francis Lamouche about the proposed investment in the warehouse extension?

Routing procedure, Routing Procedure For a new product or part the rout...

Routing Procedure For a new product or part the routing procedure consists of seven principle steps: 1.The first step is to analyze the product or articles and fabricate int

Provide two insights on conflict in organizations, Provide 2 insights on co...

Provide 2 insights on conflict in organizations. Is conflict in organizations good or bad? Can conflict be avoided? Should all potential issues that can lead to increased conflict

Linebalancing, what do you understand by "line balancing"? What happens if ...

what do you understand by "line balancing"? What happens if balance doesn''t exist ?

Explain measures that the government could employ, What are some of the mea...

What are some of the measures that governments can take to deter, detect, and prevent terrorists organized in small groups, bunch of guys (BOG) groups, cellular organizations, or a

Explain the system utilization rate and the probability, Sid Das Brick Dist...

Sid Das Brick Distributors currently employs 1 worker whose job is to load bricks on outgoing company trucks. An average of 24 trucks per day, or 3 per hour, arrive at the loading

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd