Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain cross-cultural repatriation, Preparing employees to work across nat...

Preparing employees to work across national and cultural boundaries is known as: Answer (1) cross-cultural repatriation. (2) Cross-cultural preparation. (3) Culture shock. (4) Reve

Explain preparation and analysis of balance sheet, Explain preparation and ...

Explain preparation and analysis of balance sheet. Preparation and Analysis of Balance Sheet: Balance Sheet is one of the significant financial statements of a company provid

Process Model - Serivces, Apply a proces smodel to a services industry proc...

Apply a proces smodel to a services industry process that experiences problems with either internal or external customers. Discuss all elements

Explain less of each of the inputs of production, All else constant, as the...

All else constant, as the price of petroleum increases relative to the prices of other inputs to the production process, in their effort to minimize their total costs of production

Problem, a firm isconsidering replacement of a machien, whoes cost price is...

a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below year running cost 1 200 2 50

Explain what are the issues of management, What are the issues of managemen...

What are the issues of management does Whole Foods Market in 2010 needs to address? Analyze and evaluate the issues identified

Explain biggest challenges are to a hpt professional, What do you think the...

What do you think the biggest challenges are to a HPT professional in the Analysis phase of a project? Why?

Explain what is the opinion on the rapid reflection model, What is your opi...

What is your opinion on the Rapid Reflection model? Do you believe it could be implemented in today's hectic corporate world? Elaborate.

Depict an aon diagram of the project, The following is a table of activitie...

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede- Activity Duration (weeks) Prece

Explain the forecasted demand for fudge, The forecasted demand for fudge fo...

The forecasted demand for fudge for the next four months is 140, 160, 90 and 70 pounds. A) What is the recommended production rate if a level strategy is adopted with no back order

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd