Line Balancing, Operation Management

Assignment Help:
#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..

Related Discussions:- Line Balancing

Explain demand for each season is going to be, In the past, Arup Mukherjee'...

In the past, Arup Mukherjee's tire dealership in Pensacola sold an average of 1,000 radicals each year. In the past 2 years, 240 and 260, respectively were sold in fall, 360 and 30

Layout, what are the objectives that an operation should seek in order to e...

what are the objectives that an operation should seek in order to ensure a good layout?

Explain what is the makespan and machine idle time, Sequence the jobs shown...

Sequence the jobs shown below by using the Gantt chart. Assume that the move time between machines in one hour. Sequence the jobs in priority order 1,2,3,4. Job Work Center/Machine

Productivity challenge in organisations, Productivity Challenge in Organisa...

Productivity Challenge in Organisations Productivity is the ratio of outputs (goods and services) divided by the inputs (resources: labour, capital and services). It is one of

Problems that can plague groups as organizations is groupth, One of the rec...

One of the recognized problems that can plague groups and organizations is groupthink. Do some research on the groupthink phenomenon? What is it? When does it occur? What are some

Explain sources of power and any contingencies of power, 1. Does Clark have...

1. Does Clark have any sources of power and any contingencies of power? If so, list and discuss them. 2. To what degree were Clark's methods of influencing board members the most e

Function of dispatching, Function of Dispatching Under dispatching the ...

Function of Dispatching Under dispatching the following functions are included: 1. Assignment of work to individual machines or work places and men, 2. Movement of materi

Explain functions of marketing management, Explain functions of marketing m...

Explain functions of marketing management. Functions of Marketing Management: The broad functions of marketing management includes as in following : (i) Marketing Research

Explain decision making under uncertainty, Even though independent gasoline...

Even though independent gasoline stations have been having a difficult time, Susan Helms has been thinking about starting her own independent gasoline station. Susan's problem is t

Explain customers preferred bidders list for future contract, A customer is...

A customer is unhappy with the performance thus far on a project. The customer states that, unless scope changes are made at the contractors expense, the contractor would be remove

Daina

2/12/2013 7:08:07 AM

Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)

Diana

2/12/2013 7:09:42 AM

Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd