Time to remove formwork to cater for early thermal movement, Civil Engineering

Assignment Help:

Q. Time to remove formwork to cater for early thermal movement?

Let's take a circular column as an illustration to explain effect of internal restraint to thick sections. 

When temperature is increasing, temperature in the core is higher than outer zone. The inner core would have a higher expansion and exert pressure to the outside. Induced compressive stress will yield the formation of radial cracks near the surface of concrete.

When temperature drops, concrete at outside drops to surrounding temperature whereas the concrete at central region continues to cool down. Contraction associated with inner concrete persuades tensile strains and forms cracks tangential to circular radius. 

It is advantageous for thick sections (say >500mm) to have late removal of formwork to decrease early thermal cracking. This is to enable more time for the centre of concrete section to cool down progressively to decrease the risk of thermal cracking. It is effective in controlling thetemperature differential across the cross section of concrete structures and decreasing the potential of internal cracking because of early thermal movement.


Related Discussions:- Time to remove formwork to cater for early thermal movement

Write short note on pressure filter, Q. Write short notes on Pressure filte...

Q. Write short notes on Pressure filter for drinking water supply. What are pressure filters and what are its advantages / disadvantages over the normal filter bed. What is p

Open foundation, what is savest foundation in the soft sanded earth

what is savest foundation in the soft sanded earth

Levelling, what is the types of levelling

what is the types of levelling

Concrete, what is the heat of hydration and gel space ratio?

what is the heat of hydration and gel space ratio?

Explain the allowable strength design (asd), Allowable Strength Design (ASD...

Allowable Strength Design (ASD) Process: - Apply service loads with no load factors - Assume linear elastic analysis of structure - Calculated stresses shall not excee

Water bound macadam, Water Bound Macadam: Water Bound Macadam (WBM) i...

Water Bound Macadam: Water Bound Macadam (WBM) is a dense and compact course of a road pavement composed of stone aggregates held together by a film consisting of gravel or s

Matrices, How to invert a matrix

How to invert a matrix

Surveying, describe two fundamentals purposes of surveying.

describe two fundamentals purposes of surveying.

How should reservoir floors be designed, Question In designing of servi...

Question In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements ? Answer I

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd