Time to remove formwork to cater for early thermal movement, Civil Engineering

Assignment Help:

Q. Time to remove formwork to cater for early thermal movement?

Let's take a circular column as an illustration to explain effect of internal restraint to thick sections. 

When temperature is increasing, temperature in the core is higher than outer zone. The inner core would have a higher expansion and exert pressure to the outside. Induced compressive stress will yield the formation of radial cracks near the surface of concrete.

When temperature drops, concrete at outside drops to surrounding temperature whereas the concrete at central region continues to cool down. Contraction associated with inner concrete persuades tensile strains and forms cracks tangential to circular radius. 

It is advantageous for thick sections (say >500mm) to have late removal of formwork to decrease early thermal cracking. This is to enable more time for the centre of concrete section to cool down progressively to decrease the risk of thermal cracking. It is effective in controlling thetemperature differential across the cross section of concrete structures and decreasing the potential of internal cracking because of early thermal movement.


Related Discussions:- Time to remove formwork to cater for early thermal movement

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Two layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures   The level of damage in spatial trusses has also been classified into three different levels based on the t

Abrasion test - tests on stones, Abrasion Test:   This test is carri...

Abrasion Test:   This test is carried out on stones used as aggregates for road construction. The test result shows the suitability of stones against   the grinding action u

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Wbm work, ratio of moorum and aggregate

ratio of moorum and aggregate

Auto cad drawing , im looking for someone to do drawing in autocad 3D 2013 ...

im looking for someone to do drawing in autocad 3D 2013 with report

Define inspection of pier or abutment, Define Inspection of Pier or Abutmen...

Define Inspection of Pier or Abutment? Inspection of pier/abutment may then be carried out as under: i. Conduct visual inspection of the entire surface using up and down swe

Find the maximum stress, Find the maximum stress: A circular bar rigid...

Find the maximum stress: A circular bar rigidly fixed at both ends is 1 m long and tapers uniformly from 20 cm diameter at one end to 10 cm diameter at the other end. Find the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd