Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Die design, #question calculate bending force

#question calculate bending force

Grinder-tool and equipment , Grinder: Grinders are used to sharpen the cut...

Grinder: Grinders are used to sharpen the cutting edges of the tools. They are basically fast rotating grinding wheels carried at one or two ends of a shaft. The grinding wheel ar

Evaluate crippling load, A column of timber section 15cm x 20cm is 6 meter ...

A column of timber section 15cm x 20cm is 6 meter long both side being fixed. If the youngs modulus for timber is 17.5 KN/mm 2 , Evaluate: a) Crippling load and b) Safe load

Iterature review, I have literature review and the title is "the effect of...

I have literature review and the title is "the effect of fluid cooling on the performance of building integrated photovoltaic thermal systems. Using some BIPVT prototypes measure

Types of buildings required for plant, Q. Types of buildings required for P...

Q. Types of buildings required for Plant? The following types of buildings may be required: • Control rooms / Motor Control Centers (MCC) / Equipment rooms. • Electrica

Tributary lateral load, Tributary lateral load:   The question is on a f...

Tributary lateral load:   The question is on a fictitious 1965 building in Albany, NY. It was designed using the 1964 State Building Construction Code, in which Allowable Stress

Derive the stability condition of a four wheel vehicle, Derive the stabilit...

Derive the stability condition of a Four wheel Vehicle AND Two wheel Vehicle moving in a curved Path? Explain with working, measurement and construction of brake power by Rope b

Specifications - boilers, SPECIFIC A TION S:    The boilers are s...

SPECIFIC A TION S:    The boilers are specified as per following parameters : -     Steam Generation Rate : for instance 50 000 kg /hr. -     Maximum Pressure: for

Derive the characteristic equations of motion, Derive the characteristic eq...

Derive the characteristic equations of motion for the underdamped, critical damped and overdamped free damped vibration system. Write short notes on i. Fourier series and har

Calculate the motor efficiency, A 4- pole DC motor is known to have an arma...

A 4- pole DC motor is known to have an armature resistance of 0.5 Ω, and is operated as a separately excited motor. (a)  When the motor is connected to a 250V DC supply with no

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd