Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Inlet manifold-basic components of engine , Inlet Manifold: The pipe whic...

Inlet Manifold: The pipe which connects the intake system to the inlet valve of the engine through which air or air-fuel mixture is drawn into the cylinder is called the inlet ma

The velocity distribution in the gap is linear, A 10 kg block slides down a...

A 10 kg block slides down a smooth inclined surface as shown in Figure. Show the terminal velocity of the block if the 0.1 mm gap among the block and the surface have SAE30 oil at

Introduction and over view of various manufacturing process, Introduction A...

Introduction And Over View Of Various Manufacturing Process The main aim behind advances in engineering and technology has been to raise the standard of living of man and to ma

Working principle of the petrol engine, W orking Principle of the Petrol E...

W orking Principle of the Petrol Engine: OTTO CYCLE     5-1 Suction Stroke 1-2 Adiabatic Compression Stroke 2-3 Heat Addition at the constant Volume.

Determine m.i. of i section about 2 centroidal axes, Q.  An I section has d...

Q.  An I section has dimensions Top flange = 8 cm × 2 cm; Bottom flange = 12 cm  × 2 cm; Web = 12 cm × 2 cm; Over all the depth of section = 16 cm. Determine M.I. of  I s

Force on rigid body - non rigid body, Force on Rigid body - Non Rigid body:...

Force on Rigid body - Non Rigid body: As Rigid body cannot change its shape on application of any force, It will begin moving in the direction of applied force without any

Design for dynamic and wear loads, A gear drive is needed to transmit a max...

A gear drive is needed to transmit a maximum power of 22.5KW. The velocity ratio is 1:2 and r.p.m. of the pinion is 200. The centre distance between the shafts can be taken as 600m

Finite element method, need help with mu assignment . urgent have to submit...

need help with mu assignment . urgent have to submitted it by tomoroww morning

WELDING, WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

WHAT IS DIFFERENCE BETWEEN POROSITY AND BLOW HOLE

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd