Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Evaluate the fourth force, The resultant of four vertical forces is a coupl...

The resultant of four vertical forces is a couple moment 30 Nm acting counter clockwise. Three of the four forces are shown in fig given below. Evaluate the fourth force.

Vibration, A bump/impact test is a simple technique used to determine a str...

A bump/impact test is a simple technique used to determine a structure’s natural frequency. Sketch a typical time wave response curve of such a test, then label the impact point an

Construction activities for plant, Construction Activities for plant Co...

Construction Activities for plant Construction activities, such as shoring and bracing of excavations, lifting and rigging activities and scaffolding need to be considered as p

Define the methods of constructive solid-geometry, Constructive Solid-Geome...

Constructive Solid-Geometry Methods (CSG) Constructive models represent a solid as a combination of primitive solids. This modeling technique combine the volumes occupied by ov

Computer integrated manufacturing, the component of computer integrated man...

the component of computer integrated manufacturing with the diagram

What is value of drive chain slackness?, (a) What is value of drive chain s...

(a) What is value of drive chain slackness? (b) Write about cleaning procedure and adjustment of drive chain. (c) What is the wear of drive chain, sprocket and adjustment of

Desing, what is the maximum principle stress

what is the maximum principle stress

Basis of evaluation entrepreneurship development, The following form basis ...

The following form basis of evaluation : The unit has obtained all necessary clearances whether statutory or administrative, e.g. drug license under drug control order, NOC

Estimate future capacity requirements, Estimate Future Capacity Requirement...

Estimate Future Capacity Requirements: An electronic packaging centre operates 250 days per year, with one eight hour shift. Management believes that a capacity cushion of 15

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd