Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Evaluate the net work done by the gas, An ideal gas is heated at fixed volu...

An ideal gas is heated at fixed volume until its temperature is 3 times the original temperature. It is then expanded isothermally till it reaches original pressure. The gas is t

Two UVL loads on a beam, Hi there. I am stuck on a problem. I am working ...

Hi there. I am stuck on a problem. I am working out the section of 2 beams for the floor of an elevator. Thus far the critical conditions are made up of a beam that is 1.8m long

Projection welding, Projection Welding   This is a modified method o...

Projection Welding   This is a modified method of making single or multiple spot welds. Projection welds are made by providing an embossment or projection on one or both of

Engine, Single Cylinder Vertical Engine has a bore of 30cm and a stroke of ...

Single Cylinder Vertical Engine has a bore of 30cm and a stroke of 40cm. The connecting rod is 100cm long. The mass of the reciprocating parts is 140Kg on the expansion stroke with

Dust collector, Dust Collector:             Dust collector system is to...

Dust Collector:             Dust collector system is to collect the blast burrs or waste particle created during the blasting process. During the blasting process, this dust co

Location of centre of gravity of a hemisphere, Location of centre of gravit...

Location of centre of gravity of a hemisphere: Find out the location of centre of gravity of a hemisphere of radius a. Solution Figure shows the cross-section of the h

Determine the location of any zero crossings, Determine the Location of Any...

Determine the Location of Any Zero Crossings For the loaded as shown below a. Draw the V & M diagrams on the grid below. b. Determine the location of any zero crossings

Question.., Two concentric perforared plates are seperated by a 200mm laund...

Two concentric perforared plates are seperated by a 200mm launder and form the flow exit for a clarifier (figure 1). The inlet water flow of 1200 mcubed/hour into the clarifier is

Principal planes and principal stresses, Principal Planes and Principal Str...

Principal Planes and Principal Stresses: Define the Principal Planes and Principal Stresses. Sol.: When an element in strained body is under action of plane stresses, it i

Thermophyics, The steam that leaves the super-heater is expanded from 130ba...

The steam that leaves the super-heater is expanded from 130bar at 535°C to 25.2bar at 310°C in a high pressure turbine. The steam from the exit of the HP turbine is reheated to 535

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd