Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Engineering Mechanics, How do we calculate BMD for the all type of beams?

How do we calculate BMD for the all type of beams?

Magnitude of the centripetal acceleration of the car, A car travels at a co...

A car travels at a constant speed around a circular track whose radius is 2.2 km. The car goes once around the track in 400 s. What is the magnitude of the centripetal acceleration

Tensile stress, T ensile Stress: The stress induced in a body, when ...

T ensile Stress: The stress induced in a body, when subjected to two equal and opposite pulls as shown in figure (a) as a result of which there is an increase in length,

The dimension text edit command-autocad, The Dimension Text Edit command is...

The Dimension Text Edit command is used to modify the text position of any single dimension.                                    The command can be used to position the tex

Spray transfer, Spray Transfer In a gas shield of argon or argon rich m...

Spray Transfer In a gas shield of argon or argon rich mixture [i.e., Ar+CO 2 gas mixture containing more than 80 % argon] the metal transfer changes from globular to spray typ

Explain tee joints, Tee joints -The square tee joint requires a fillet weld...

Tee joints -The square tee joint requires a fillet weld that can be made on one or both sides. It can be used for light or fairly thick materials. For maximum strength, considerabl

Find out the amount of energy spent, Find out the amount of energy spent: ...

Find out the amount of energy spent: 6 cubic metre of water is to be lifted to a height of 40 metres and delivered having velocity of 4 metres/sec. If this operation takes 12

Wind induced vibration of vertical vessels, Q. Wind Induced Vibration of Ve...

Q. Wind Induced Vibration of Vertical Vessels? Vertical vessels having a height-to-diameter ratio (h/D) (does not include insulation thickness but does include skirt height) gr

Electron beam welding-aerospace applications, AEROSPACE APPLICATIONS   ...

AEROSPACE APPLICATIONS   The need for EBW as a critical fabrication process in realising elements and assemblies for spacecraft and launch vehicle programmes due to the foll

Pressure and temperature in unfired pressure vessels, Q. Pressure and Tempe...

Q. Pressure and Temperature in Unfired pressure vessels? The design pressures and coincident maximum and minimum metal temperature, shall be determined by carefully considering

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd