Three key types of reinforcement used in pre stressing, Civil Engineering

Assignment Help:

Question-What are three key types of reinforcement used in pre stressing?

 

Answer-(i)Spalling reinforcement -

Spalling stresses are established behind loaded area of anchor blocks and this causes breaking away of surface concrete. These stresses are induced by strain incongruity with Poisson's effects, by the shape of stress trajectories.

(ii)Equilibrium reinforcement -
Equilibrium reinforcement is necessary where there are several anchorages in which pre stressing loads are useful sequentially.

(iii)Bursting Reinforcement -
Tensile stresses are induced through pre stressing operation and maximum bursting stress occurs where stress trajectories are concave towards a line of action of load. Reinforcement is required to oppose these lateral tensile forces.

 


Related Discussions:- Three key types of reinforcement used in pre stressing

Explain the well drawdown equations - ground water, Explain the Well Drawdo...

Explain the Well Drawdown Equations Watch the units, especially if you use log 10 or ln.    h 1 = aquifer thickness minus the drawdown (ft)  r 1 = distance from well (ft

State the problem and phases of site investigation, State the Problem and p...

State the Problem and phases of site investigation The site investigation is to be performed to obtain the solution for the following problems: i)  Foundation problems ii

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Explain the term - moderate prestressing, Explain the term - Moderate Prest...

Explain the term - Moderate Prestressing In this form of prestressing, no limit is imposed on  the magnitude of tensile stresses which may be produced in a concrete member unde

Topographical survey and preparation of drawings, Topographical Survey and ...

Topographical Survey and Preparation of Drawings: Topographical Survey for a road project consists of three sequential stages: (a) Reconnaissance Survey, including a study

Univariate normal distribution, Univariate normal distribution: Let X ...

Univariate normal distribution: Let X = (X I , X 2 , ..., X n ,) has the multivariate normal distribution (5.26) of Section 5.4. Show that Y = a X ' follows a univariate norma

Explain the dynamic or vibration tests, Explain the Dynamic or Vibration Te...

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

Determine the latitude and departure - transportation, Determine the latitu...

Determine the latitude and departure of each side of the closed traverse ABCDA.  Total the latitudes and departures. TIP: For Closed Traverse, Sum of Latitudes is Z

Softening point test, Softening Point Test: The temperature at which ...

Softening Point Test: The temperature at which bitumen softens is determined by the "Ring and Ball" test (Figure). (a) Diagram of Apparatus at Beginning of Test  (b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd