Perform a status assessment of the third Elaboration iteration. DO NOT GENERALISE. Assess each activity separately and assess it against the outcomes specified for the activity. Generate a detailed iteration plan for the fourth Elaboration iteration (EIP4). As usual, plan the next iteration AS IF all work items were completed successfully and then ADD incomplete items to the next iteration plan.
Aim to achieve the Life Cycle Architecture Milestone (LCAM) in this fourth iteration. This milestone involves demonstration of the executable architecture - ie end-to-end support for the most difficult, risky, critical, core use case identified in the system. It also involves a ‘snapshot' of existing requirement, architecture, and design documentation, and the establishment of a robust and realistic implementation plan for the Construction phase to be carried out next semester.
Ideally, you should not be planning to complete all the items listed above in the last iteration of the Elaboration phase: some of them should have been completed in earlier iterations.
Remember to plan production of an Elaboration Phase Status Assessment, and an overall Project Status Assessment.
S is enrolled on T Company's management development programme. Although S has a financial background, the aim of the management development programme is to help him to gain a bett
2JN is a large manufacturing organisation which is structured with a number of supervisors every responsible for their own work production unit. Supervisors report to a team of sen
how do I create a risk management plan
Compare and Contrast the KN346 investment and the "plain vanilla" alternative.
Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj
Failure Cost of failure may result from either internal failure or external failure. Internal failures are those that occur before the product is delivered, internal failure co
Costs of Quality Quality management is not only concerned with maintaining the quality characteristics of a product but also with doing the same at least cost. The
Network diagrams and bar charts have different parts to play within planning a project. Where each of such tools used is and what does this demonstrate? The network diagram dis
The product development cycle starts with the assessment of the customers needs and ends when the design is finally released for bulk production. The main steps in th
Greater Possibility of Space Utilization There will be a greater productive utilization of the floor area under this type of layout. Due to lesser need for temporary storage o
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd