The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Advantage of in-house project management service, Question: Using the e...

Question: Using the example of Back~to~Future International, a newly setup organization and taking advantage of in-house project management service as set out in Question (

IT Project Management Task #1, IT Project Management Task #1, I need help w...

IT Project Management Task #1, I need help with my course.

Microsoft Project Management, Greeting, Do you use Microsoft Project Manage...

Greeting, Do you use Microsoft Project Management software for project management assignments if needed

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

#title.Risk management and procurement, Critically evaluate the use of comp...

Critically evaluate the use of complex models of Project Risk and Procurement Management; systematically and creatively making sound judgements based on the systematic analysis and

Describe the follow-up phase, Describe the follow-up phase, in short. ...

Describe the follow-up phase, in short. Follow-up phase: Although this is extremely significant, the follow-up phase is frequently neglected. Throughout this phase, the w

Caselet, what action should be taken by various functioal managers to meet ...

what action should be taken by various functioal managers to meet the scheduled dates

Budgeted cost of work performed (bcwp), Budgeted cost of work performed (BC...

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a p

Combined layout, Combined Layout The application of the principle of p...

Combined Layout The application of the principle of product layout, process layout or fixed location layout in their strict meanings is difficult to come across. A combination

Disadvantages of product layout - demerits of breakdown, Disadvantages of P...

Disadvantages of Product Layout - Demerits of Breakdown The production line is vulnerable to interruption and shutdowns. A breakdown of a machine will render the entire line i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd