The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Explain about the term project planning document, Explain about the term pr...

Explain about the term project planning document. A project planning document (PPD): Project planning document will usually consist of a project technical and resource pl

Initiation, How to initiate a project

How to initiate a project

Product characteristics and requirements, 1.  Main functions: The web based...

1.  Main functions: The web based site will be fully enabled for viewing via iPad and be fully accessible at the cafe seating only.  The menu will be fully automated to allow order

Describe fully the key constraints faced by any project, Question 1: (a...

Question 1: (a) What do you meant by a Project? (b) Describe Project Management and Project Manager. (c) Highlight the different types of activities involved in the management

Benefits of Group Technology, Benefits of Group Technology 1.Reduced F...

Benefits of Group Technology 1.Reduced Flow Times: Compared to the earlier process layout, there are very few halts. Hence flow times are reduced considerably. 2.Process Tim

Components of strategy, Components of Strategy Strategy has four basic ...

Components of Strategy Strategy has four basic components: Scope: which refers to the position the firm wants to have in relation to its environment. Resource deploym

Explain what deming meant by the following statements, Question: (a) Ex...

Question: (a) Explain what Deming meant by the following statements? What happens if you do not fulfill those principles? (i) Institute leadership. (ii) Drive out fear.

Use of operational approach in development process, Q. Use of Operational a...

Q. Use of Operational approach in development process? It has been defined as the application of scientific methods, technology and tools to operation of system with optimum s

Projects at times get delayed due to various factors, QUESTION a) Proje...

QUESTION a) Project management activities are carried out in a planned manner. List the distinguishing characteristics of a project? b) During project management meetings, t

Upward communication from subordinate to superior, How must be the upward c...

How must be the upward communication from subordinate to superior ? Upward Communication moves through subordinate to the superior within the form of feedback. This takes th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd