The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Saving culture and project development, student in project management reque...

student in project management request topic on saving

Performance management report, Review assignment  and the macro map you pre...

Review assignment  and the macro map you prepared. How are your transformational processes monitored? Identify the critical success factors that are both necessary and sufficien

Aspects to good project management, Q. Is that all there is to project mana...

Q. Is that all there is to project management? A. That is by no way all. There are several aspects to good project management that require attention. In summary these perhaps

How do i get started, Q. How do I get started? At one as well as the sa...

Q. How do I get started? At one as well as the same time this step is possibly the most important and least understood of all the steps in the project management process. Entir

What are the major characteristics of a project, Question: (a) What ar...

Question: (a) What are the factors to consider while choosing an appropriate Project Management Structure? (b) What are the major characteristics of a Project? (c) Out

How is inventory control worked for an optimum balance, How is Inventory co...

How is Inventory control worked for an optimum balance between competing objectives? Inventory control is related with achieving an optimum balance in between two competing obj

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

Objectives of iso 9000, Objectives of ISO 9000 The basic objectives o...

Objectives of ISO 9000 The basic objectives of ISO 9000are : 1. To facilitate international trade of goods and services. 2. To obtain competitiveness by obtaining

What must be the responsibility of the project manager, What must be the re...

What must be the responsibility of the project manager into relation to the business case? Idyllically, the project manager must be appointed early adequate to give to the deve

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd