The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Verification and validation process, Verification is the process by which o...

Verification is the process by which one can ensure that a model is performing as expected or intended. The process of verification is a challenging one for the project concerned a

What is the use of critical path analysis as a tool, What is the use of cri...

What is the use of critical path analysis as a tool? The use of critical path analysis as a tool: a. It is good visual communication and planning tool for effectual time man

Explain the time-cost optimization algorithm, Question 1: What do you m...

Question 1: What do you mean by crash duration? Explain the Time-Cost Optimization algorithm crash duration/crash time - explanation including figures  Steps of Time-C

Characteristics of flexible manufacturing system, Characteristics of Flexib...

Characteristics of Flexible Manufacturing System An FMS is a process technology that can product a moderate variety of products in modest volumes and can do so quickly and wit

What are the primary objectives of transferring risks, Question : (a) ...

Question : (a) Define risk as per the Public Private Partnership Guidance Manual. (b) What are the primary objectives of transferring risks from a contracting authority to

Explain cost effective design, Question 1: "One of the main challenges ...

Question 1: "One of the main challenges of hotel management today is the rapid changes in customer requirements, trends and tastes, resulting in the necessity for frequent exte

Scheduling in program management, Scheduling  Once a program plan is ap...

Scheduling  Once a program plan is approved, good scheduling is the heart of the program management process. Program schedules provide adequate time to ensure that the work bre

Define the resource histograms in short, Define the Resource Histograms in ...

Define the Resource Histograms in short. Resource histograms A resource histogram is a column (or bar) chart which demonstrates the number of resources allocated to a pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd