The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Objectives of materials management, Objectives  of Materials Management: ...

Objectives  of Materials Management: 1. Low  prices: Obtaining  the least possible  price  for purchased materials is the  most  obvious  purchasing  objectives and certai

Communication strategy, Communication Strategy: Communication str...

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Earned value management is a systematic approach, Question: (a) Earned...

Question: (a) Earned Value Management is a systematic approach to the integration and measurement of cost, schedule, and technical accomplishments in a project. List the benef

What is the use of critical path analysis as a tool, What is the use of cri...

What is the use of critical path analysis as a tool? The use of critical path analysis as a tool: a. It is good visual communication and planning tool for effectual time man

Performance problem or challenge, • You also found that over the past 6 mon...

• You also found that over the past 6 months, the Senior Leadership had been very proactive in their attempt to drive a much different strategic vision and had communicated strong

Assignment 2 intro to project manage, Assignment #2 . Assignment #2 Yo...

Assignment #2 . Assignment #2 You will need to first develop a customer''s Request for Proposal (RFP), then go to the simplified Project Proposal on pages 76-78 of your text a

Macro environment, The influence an organisation will normally have over it...

The influence an organisation will normally have over its macro environment will be Limited or non existent

Production control system, Question 1: What is understand by a producti...

Question 1: What is understand by a production control system and how are the elements of control systems categorized? Description of production control system Catego

Develop and agree a process model for a project, Why is it significant that...

Why is it significant that the project team and the users develop and agree a process model for a project? Any project is a cooperative venture among the clients/users and the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd