The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

What do you mean by improving productivity, What do you mean by Improving P...

What do you mean by Improving Productivity? Improving Productivity: The concentrate of production is creation of goods, might be by the transformation of raw materials or

How is inventory control worked for an optimum balance, How is Inventory co...

How is Inventory control worked for an optimum balance between competing objectives? Inventory control is related with achieving an optimum balance in between two competing obj

What are the steps in organisation design, What are the steps in organisati...

What are the steps in organisation design? Steps comprised in Organisation Design are as illustrated below: a. Understand and formulate the goals and things of the organisat

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

What is cost benefit analysis, What is Cost Benefit Analysis? Cost Be...

What is Cost Benefit Analysis? Cost Benefit Analysis: This analysis is a mathematical technique for decision-making. This is a quantitative technique used to calculate th

Which tools are best for you to evaluate team performance, Q. You have been...

Q. You have been hired by a contractor, who wants you to organize a construction project for one of their clients. The project team has been working for six weeks. You need to eval

Production control system, Question 1: What is understand by a producti...

Question 1: What is understand by a production control system and how are the elements of control systems categorized? Description of production control system Catego

Participative management, PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMEN...

PARTICIPATIVE  MANAGEMENT IN LIBRARIES MANAGEMENT: Like most other organizations, libraries and information centres have the dual social responsibility of satisfying the needs

Risk management techniques and project timeplan creation, I have an assignm...

I have an assignment to submit in the above mentioned topics. Please respond me as soon as possible with the required info and i will send you the assignment details after our mutu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd