The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Outline at least three steps common to pert and cpm, QUESTION (a) Feasi...

QUESTION (a) Feasibility Study is a preliminary study undertaken before a real work of a project start what factors should the project manager take into consideration while con

Third elaboration iteration, Perform a status assessment of the third Elabo...

Perform a status assessment of the third Elaboration iteration. DO NOT GENERALISE. Assess each activity separately and assess it against the outcomes specified for the activity. Ge

Contract process cycle , Contract process cycle  Contract process goes ...

Contract process cycle  Contract process goes through the following stages to complete the contract documentation cycle:    Pre tender documentation stage.    Approval

Explain what deming meant by the following statements, Question: (a) Ex...

Question: (a) Explain what Deming meant by the following statements? What happens if you do not fulfill those principles? (i) Institute leadership. (ii) Drive out fear.

Explain the procedure of modi method, Q1.  Explain the procedure of MODI me...

Q1.  Explain the procedure of MODI method of finding solution through optimality test. Q2.  a. Explain the steps in Hungarian method. b. Solve the following assignment proble

NETWORK DIAGRAMS, AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROB...

AHOW TO FIND THE VARIANCE OF AN ACTIVITY AND THE THE PROBABILTY THAT A WORK WILL BE FINISHED IN A GIVEN NUMBER OF DAYSsk question #Minimum 100 words accepted#

Value engineering, Value Engineering Value Engineering is not a program...

Value Engineering Value Engineering is not a program but a process. It is a systematic method used to improve the "value" of the goods or the products and services through exam

How much time should planning take, Q. How much time should planning take? ...

Q. How much time should planning take? T imes taken for individual projects differ considerably frequently due to circumstances beyond the project manager's control such as ch

Project lifecycle for the training centre project, T Company has identified...

T Company has identified a need for, and made a decision to open, a new training centre in one of the major cities in E Country. This is a large scale project for T Company and it

Calculate the elapsed time of the critical path project, Calculate the elap...

Calculate the elapsed time of the critical path project when A Critical path of ACDEFGIJ is given below and the elapsed time of the project is 25 weeks. Th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd