The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

What are the questions of the initiation phase, What are the questions of t...

What are the questions of the initiation phase? Questions to be answered in the initiation phase include the given as: • Why only project management? • Is this feasible?

Microsoft Project Management, Greeting, Do you use Microsoft Project Manage...

Greeting, Do you use Microsoft Project Management software for project management assignments if needed

Project execution plan, A project execution plan (written and graphical rep...

A project execution plan (written and graphical report) developing the strategy covering FIVE key areas: Some guidelines for each subject area are listed below, but the report s

Implementation risks in cost of quality approaches, I mplementation risks ...

I mplementation risks There    are    many    problems   which    have   caused    the    cost-of-quality approaches to fail. It is unwise to achieve too much too fast. For ex

Differences between wbs and product breakdown structure, a) Draw a work bre...

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels. b) Explain the main differences bet

Scatter diagrams, S catter diagrams The possible relationships between...

S catter diagrams The possible relationships between two variables are identified using scatter diagrams. In order to understand data as a whole, it is very important to under

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

Contract process cycle , Contract process cycle  Contract process goes ...

Contract process cycle  Contract process goes through the following stages to complete the contract documentation cycle:    Pre tender documentation stage.    Approval

What is memory virtualization, 1. Enterprises always seek to enhance the q...

1. Enterprises always seek to enhance the quality of service delivered to customers and end users. Justify. 2. Describe briefly the concept of capital budgeting for information

Costs of quality, Costs of Quality Quality management is not only c...

Costs of Quality Quality management is not only concerned with maintaining the quality characteristics of a product but also with doing the same at least cost. The

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd