The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Explain the tool of total quality improvement, Question: As the Managin...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Program manager roles , Program Manager Roles   The following is the r...

Program Manager Roles   The following is the role of the Program manager:   Responsible for meeting customer requirements.  Manage risk.  Deliver the program, the p

Production improvement - materials management, 1. Reciprocal Relations: W...

1. Reciprocal Relations: When  a company deliberately buys  as much  as possible  from its own  customers  it is  said  to practice reciprocity. In consumer goods industries reci

System engineering and deployment of Envirobat, i need a 5000 words report,...

i need a 5000 words report, i have already submitted a project plan from a material. i want report from already available material and some portion from yours as well.

Benefits of value management over entire project lifecycle, Question: (...

Question: (a) Project Value Management has gained significant acceptance in different fields of business and is regarded as a useful tool for promoting project sustainability

Appraisal process to help staff appreciate, KS, the Finance Manager of TZY ...

KS, the Finance Manager of TZY Company's Finance Department, is aware that it is approaching the time of year when he requirements to conduct staff appraisals. However, he is consc

What value does project management add, Q. What value does project manageme...

Q. What value does project management add? This is extremely difficult to answer in traditional accounting terms for the reason that the real value is in the quality of the end

What are the advantages of division of labour, What are the Advantages of D...

What are the Advantages of Division of Labour? Advantages of Division of Labour: As very similar worker does the same work frequently:- a. It gains proficiency and ski

What is organizational culture and its characteristics , Organization's cul...

Organization's culture is the shared perception that organizational members have about its characteristics.As stated earlier, an organization's competitive advantage depends largel

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd