The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Characteristics and goals of organizational development, Question 1: Wh...

Question 1: What are the characteristics and goals of organizational development? Describe organizational development Characteristics and goals of organizational developmen

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

Show the product formulation, Q. Show the product formulation? One shou...

Q. Show the product formulation? One should also see the kind of infrastructure available in the laboratory and use the techniques which can be easily standardized for example,

International/global competitive bidding (icb), Steps involved for Internat...

Steps involved for International/Global Competitive Bidding (ICB)      Now that we are aware of the requirements of ICB, let us understand the steps involved in ICB. There can b

Develop a integrated management project, You are not expected to submit a f...

You are not expected to submit a formal proposal. However, you will be able to access Subject Tutors via HenleyConnect and you may seek feedback from them as to the suitability and

Use of both innovative approach in development process, Q. Use of both inno...

Q. Use of both innovative approach in development process? There are many major aspects that will sway the future trends in the development of new products. In the new millenn

Factors affecting process design - nature of product, Factors affecting Pro...

Factors affecting Process Design - Nature of Product The operations management has to design the production systems to produce products/ service of the kind that customers wan

Calculate the net present value for each opportunity, Question: A brill...

Question: A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choose between them. One is a job offer with a salary of Rs15,000

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd