The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Tools for collecting data, T ools for collecting data Improper or inco...

T ools for collecting data Improper or incomplete collection of data is a fundamental error which has an effect on all the subsequent actions. Data may be collected at the tim

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

What do you mean by improving productivity, What do you mean by Improving P...

What do you mean by Improving Productivity? Improving Productivity: The concentrate of production is creation of goods, might be by the transformation of raw materials or

Case let, Do you think Acorn’s solution was good? Why or why not?

Do you think Acorn’s solution was good? Why or why not?

Explain the flexibility plans, Question 1: In order to meet the constan...

Question 1: In order to meet the constant changing requirements of the modern business world, organisations are compelled to develop flexibility plans. (a) Explain the vario

Manufacturer''s promotional activity, Explain how a manufacturer's promotio...

Explain how a manufacturer's promotional activity might vary depending upon the sort of distribution channel that operates. Distribution includes getting the right products to

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

What are the costs involved with respect to quality, Question 1: Descri...

Question 1: Describe Total Quality Management. What are the Costs involved with respect to ‘Quality'? Cost of Quality Meaning of TQM Quality Control Costs

Explain about the project management systems, Explain about the project man...

Explain about the project management systems. Project management systems: Each project must have a plan and a set of goals or performance measures to achieve this. Contro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd