The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Program management process , Define the concept of Program Management Proce...

Define the concept of Program Management Process  As we learnt in the previous section Program?s process depends mostly on the characteristics of the product/service offered by

Factor affecting process planning - choice of plant layout, Factor Affectin...

Factor Affecting Process Planning - Choice of Plant Layout While deciding the sequence of operations the plant layout is to be taken into consideration. The sequence of operat

Tools and techniques of layout planning - line balancing, Tools and Techniq...

Tools and Techniques of layout planning - Line Balancing Line balancing is the phases of assembly line study that nearly equally divides the work to be done among the workers

Explain the sources of power of a project manager, Question 1: (a) Powe...

Question 1: (a) Power is one of the most important human variables in the project management process as it sets the framework for directing and influencing human resources. Exp

How important are the stakeholders, Q. How important are the stakeholders? ...

Q. How important are the stakeholders? The most significant stakeholder of course is your client or customer. Conversely that perhaps in excess of one person that the sponsor a

Research reports and design documents, Project management-related deliverab...

Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final pro

Tangible and intangible while applied to costs and benefits, What do you me...

What do you mean by the terms tangible and intangible while applied to costs and benefits? Tangible costs or benefits are those for that a plausible quantitative value can be

Contract process cycle , Contract process cycle  Contract process goes ...

Contract process cycle  Contract process goes through the following stages to complete the contract documentation cycle:    Pre tender documentation stage.    Approval

Processes by market orientation , Processes by Market Orientation Pro...

Processes by Market Orientation Processes can  also be categorized on the basis  of four  marker orientations: Make to Stock (MTS): the goods usually are standard mat

Risk managemet, How do I create a risk management plan

How do I create a risk management plan

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd