The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

What are the benefits of using work breakdown structure, What are the benef...

What are the benefits of using work breakdown structure? The benefits of using WBS (work breakdown structure): a. It can be used to assign and delegate responsibility to ass

A comparative literature review, a comparative literature review on project...

a comparative literature review on project management in small businesses (2000 words)

How to achieve competitive benefit, DF Company, a relatively new company, i...

DF Company, a relatively new company, is in the business of designing and building farm equipment and machinery. Whilst it has been winning in its first few years of operation, sal

Explain portfolio management in project, Question: (a) Project plans ar...

Question: (a) Project plans are created in knowledge areas throughout the different phases of the project life cycle and are subsidiary components of the overall project manag

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

Explain about the economic order quantity and total cost, Explain about the...

Explain about the Economic Order Quantity and Total Cost with diagram. Economic Order Quantity and Total Cost: The total of Inventory procurement cost and also inventory carryi

Llean management, Arvin Automotive, a company that makes muffler assemblies...

Arvin Automotive, a company that makes muffler assemblies for the Big Three, is committed to the use of Kanban to pull material through its manufacturing cells. Arvin has designed

Network, charateristics of a good network

charateristics of a good network

What is the estimated cost of the whole project, Question 1: (a) Using...

Question 1: (a) Using information from Table 1, build a network diagram for the project. (b) Perform a Forward Pass on the network diagram and deduce the duration of the p

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd