The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

You are a Project manager at the Department of Public Works, Describe how y...

Describe how you, as a project manager in a Matrix Organisation, will set up your project r=team for the building of the community. Project team members names, and reason why they

Developing a safe system of work, Question: (a) With reference to the ...

Question: (a) With reference to the Confined Space Regulations 1997. (i) Give the meaning of ‘confined space', providing TWO workplace examples (ii) What are the speci

Illustrate an example of a critical path given by activity, Illustrate an e...

Illustrate an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Precede

Scheduling in program management, Scheduling  Once a program plan is ap...

Scheduling  Once a program plan is approved, good scheduling is the heart of the program management process. Program schedules provide adequate time to ensure that the work bre

Benefits from quality efforts, Benefits from Quality Efforts The benefi...

Benefits from Quality Efforts The benefit obtained from quality is creation of more efficient and effective operations. It helps to increase the customer satisfaction and their

Two primary stages of risk management of a project, Question Using a pr...

Question Using a project drawn from your own experience, discuss the following (a) What are the two primary stages of risk management of a project? (b) What are the four

Llean management, Arvin Automotive, a company that makes muffler assemblies...

Arvin Automotive, a company that makes muffler assemblies for the Big Three, is committed to the use of Kanban to pull material through its manufacturing cells. Arvin has designed

Search and remove modules, Seven process modules are placed on our model, a...

Seven process modules are placed on our model, and they represent the basic functions in the model. These process modules simulate important operations such as specifying wheel cha

Information resources and selection principle, INFORMATION RESOURCES AND SE...

INFORMATION RESOURCES AND SELECTION PRINCIPLE:   The main objective of a library can be stated as" "To provide for the information needs of a given group of users in relation t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd