Test schedule - meter testing, Electrical Engineering

Assignment Help:

Test Schedule - Meter Testing

The test schedule as per the Central Electricity Authority Regulations on Installation and Operation of Meters is given below.

Table: Test Schedule

Meter Type

Schedule

Single Phase LT meters

Once in 5 years after installation

LT three phase meters (CT operated) 20 kVA to 100 kVA

Once in a year to be checked since these are installed for high value consumers

Other LT metering systems

Once in two years after installation

EHT / HT meters

Below 5 MVA - Once in a year
5 to 10 MVA - Once in six months
above 10 MVA - Once in a quarter

The testing schedule for HT consumers should cover the whole Metering System involving CTs, PTs and Pilot Wire. Detailed ratio testing of CT, PT and control Pilot/ wires is to be completed. Testing by mobile vans/mobile cubicles through secondary injections kit and phantom loading might also be carried out through Measurement Unit. All new meters should meet the needs of Accuracy Class spelt out in Table.

                                                   Table: Requirements of Accuracy Class

Type of Consumer

Overall Accuracy Class

EHT Consumers (33 kV)

0.2

HT Consumer (44 to 33 kV)

0.5 or better

LT Consumer (Whole Current meters)

1.0 or better

LT Consumers (CT operated)

1.0 or better

 


Related Discussions:- Test schedule - meter testing

Abrasive jet machining system, Describe the effect of following parameters ...

Describe the effect of following parameters on working rate and accuracy of material removal in AJM. (i) Grain size (ii) Stand off distance (iii) Jet velocity. Draw sch

Obtain expressions for the in-phase and quadrature component, Q. For DSB an...

Q. For DSB and conventional AM, obtain expressions for the in-phase and quadrature components x d (t) and x q (t), and envelope and phase v(t) and φ(t).

What is extended memory system, What is XMS? XMS: The memory system is ...

What is XMS? XMS: The memory system is splits in three major parts as: system area, XMS (extended memory system) and TPA (transient program area). The kind of microprocessor in

Explain 8259 pin diagram, Explain 8259 Pin Diagram. The 8259A adds 8 ve...

Explain 8259 Pin Diagram. The 8259A adds 8 vectored priority encoded interrupts to the microprocessor. It can be expanded to 64 interrupt requests by using one master 8259A and

System of forces.., Example of unlike coplaner parallel force''

Example of unlike coplaner parallel force''

Dc, what is quantization noise

what is quantization noise

FSM(finite state machine, A sequential circuit has two inputs w1 and w2, an...

A sequential circuit has two inputs w1 and w2, and an output, z. Its function is to compare the input sequences on the two inputs. If w1=w2 during any four consecutive clock cycl

Explain about subscriber loops signalling, Q. Explain about Subscriber loop...

Q. Explain about Subscriber loops signalling? In a telephone network, subscriber loop signal linger lies upon the kind of a telephone instrument used. The intra exchange signal

Determine the required voltage at the high-voltage terminals, Q. A 20-kVA, ...

Q. A 20-kVA, 2200:220-V, 60-Hz, single-phase transformer has these parameters: Resistance of the 2200-V winding R1 = 2.50  Resistance of the 220-V winding R2 = 0.03  Lea

Define the objectives of load flow analysis, Define the Objectives of Load ...

Define the Objectives of Load Flow Analysis The objectives of load flow analysis are: (i) To analyse an existing power system, future expansion or a new power system plan.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd