Tasks, predecessors and times - process design, Operation Management

Assignment Help:

Tasks, Predecessors and Times - Process Design

1329_Tasks, Predecessors and Times - Process Design 1.png

The first step in the procedure is to draw a precedence diagram, shown here, the task labels and times entered in the nodes.

The next step is to determine the cycle time required to deliver the stipulated rate of output: 

Time cycle = productive time available per hour / output per hour

3600 output per hour / (8,000/5*8)) mail shots per hour = 18 seconds

We then calculate the theoretical minimum number of workstations required. This would be the result if it were possible to design the line such that the task times were evenly spread among the workstations; a very unlikely outcome in practice. However, as we will see later, it can be used to assess the utilisation of the practicable line layout produced by the procedure.

286_Tasks, Predecessors and Times - Process Design 2.png

Theoretical minimum number of workstation = Sum of task times/cycle times = 80/18

=4.4 workstations

The next stage, the allocation of tasks to workstations, is usually conducted by heuristic (ie rule-of-thumb) methods. There are several such heuristics; we will use one of the simpler ones, the longest-task- time heuristic, the results of its application being displayed in the table below. It begins with the first workstation and consideration of the candidate tasks that could be allocated to it. In this case there is only one candidate, 'A', since no other task can begin until 'A' is complete. 'A' is allocated, its time entered, and the remaining unassigned part of the 18-second cycle time calculated and entered (18 - 15 = 3 seconds).


Related Discussions:- Tasks, predecessors and times - process design

Describe find the shortest route from node 1 to node 6, Find the shortest r...

Find the shortest route from Node 1 to Node 6. From Node To Node Distance 1 2 150 1 3 200 2 3 100 2 4 200 2 5 50 3 4 350 3 5 300 4 6 100 5 6 100 Which Answer is it? 300 450 550 650

The role of computers in POM, Obsolete technology can cost an organisation ...

Obsolete technology can cost an organisation its customers.Explain the role of computers in production and operations management

Variables - statistical process control, Variables - Statistical Process Co...

Variables - Statistical Process Control The output of many processes can be measured, and an individual measurement may take any value on a continuous scale. For example, this

Explain project management profession, Microsoft Project, identify the reso...

Microsoft Project, identify the resource that caught your interest and estimate its usefulness to the project management profession.

Finish a net material requirements schedule, Complete a net material requir...

Complete a net material requirements schedule for: a) All items (10 schedules in all), assuming the requirement for each BOM item is 1. b) All 10 items, assum

Iventory control and management, Nuvyug Industries Ltd. Has an annual requi...

Nuvyug Industries Ltd. Has an annual requirement of 5,000 pieces of brake cylinders for its popular brand of golf carts. Each brake cylinder has a carrying cost of ` 25 per unit pe

Explain how are scheduling and productivity related, Scheduling techniques ...

Scheduling techniques are designed to disaggregate the master production schedule into time-phased daily or hourly activities. A detailed production schedule must include when and

Explain how would they be measured, Based on the description of Coyote Comm...

Based on the description of Coyote Community College and its environment, what specific types of measures should they include in each of their perspectives of the balanced scorecar

What is utility of optimised production technology, Q. What is utility of o...

Q. What is utility of optimised production technology to manufacturing operations? Optimised production technology (OPT) optimises the employ of ‘bottleneck resources' (restric

Describe international compensation, Existing salary for managers is 45,000...

Existing salary for managers is 45,000 euros (58,567 us dollars) plus bonuses. Average salary for managers in range is 60,000 euros (78,090), no bonuses. Recommendations must inclu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd