Tasks, predecessors and times - process design, Operation Management

Assignment Help:

Tasks, Predecessors and Times - Process Design

1329_Tasks, Predecessors and Times - Process Design 1.png

The first step in the procedure is to draw a precedence diagram, shown here, the task labels and times entered in the nodes.

The next step is to determine the cycle time required to deliver the stipulated rate of output: 

Time cycle = productive time available per hour / output per hour

3600 output per hour / (8,000/5*8)) mail shots per hour = 18 seconds

We then calculate the theoretical minimum number of workstations required. This would be the result if it were possible to design the line such that the task times were evenly spread among the workstations; a very unlikely outcome in practice. However, as we will see later, it can be used to assess the utilisation of the practicable line layout produced by the procedure.

286_Tasks, Predecessors and Times - Process Design 2.png

Theoretical minimum number of workstation = Sum of task times/cycle times = 80/18

=4.4 workstations

The next stage, the allocation of tasks to workstations, is usually conducted by heuristic (ie rule-of-thumb) methods. There are several such heuristics; we will use one of the simpler ones, the longest-task- time heuristic, the results of its application being displayed in the table below. It begins with the first workstation and consideration of the candidate tasks that could be allocated to it. In this case there is only one candidate, 'A', since no other task can begin until 'A' is complete. 'A' is allocated, its time entered, and the remaining unassigned part of the 18-second cycle time calculated and entered (18 - 15 = 3 seconds).


Related Discussions:- Tasks, predecessors and times - process design

How to view intermingling of management, The chapter notes that in 2010, in...

The chapter notes that in 2010, in roughly two-thirds of U.S. firms, the CEO is also the chair of the board of directors. More broadly this can be viewed as an intermingling of man

Explain if you sued me for coat what would be the outcome, I promise to giv...

I promise to give you my fur coat. I never give you my coat. If you sued me for the coat what would be the outcome? Support your answer using the Rule, Application, conclusion meth

Explain what is the workstation cycle time, 1. Some tasks and the order in ...

1. Some tasks and the order in which they must be performed according to their assembly requirements. These are to be combined into workstations to create an assembly line. The

Describe difference between significance and meaningfulness, What is the di...

What is the difference between significance and meaningfulness? Which one is more important to experimental results and why do you think so?

Analyze the points involved in avoiding a cash crunch, Analyze the steps in...

Analyze the steps involved in avoiding a cash crunch and make at least one additional recommendation for doing so. Provide specific examples to support your response

Explain what is the optimal solution, Kentwood Electronics manufactures thr...

Kentwood Electronics manufactures three components for stereo systems: CD players, tape decks, and stereo tuners. The wholesale price and manufacturing cost of each item are: Compo

Differences between a team and a work group, Question: (a) "Teams defin...

Question: (a) "Teams definitely are forms of work groups, but not all work groups are teams". Work groups function on three levels: Dependent level, Independent level and Inter

Explain reasonable accommodation to his religious beliefs, Ras is a member ...

Ras is a member of the Rake Religion whose practice forbids using yard rakes for any other reason than worship. Three times a week, Ras attends religious services where a silver ra

Compute the bias and mad for each set of forecasts, Given the series of dem...

Given the series of demand data below Period: 1 2 3 4 5 6 7 8 9 10 Demand: 43 31 52 44 23 48 40 39 30 40 Calculated forecasts for periods 7 through 11 using moving average

Explain the bargaining unit as technical workers, Jack is a 2nd level manag...

Jack is a 2nd level manager at Johnson Controls. His department includes 2 supervisors, 5 night shift security guards, 5 technical workers, 10 janitorial staff, and 25 manufacturin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd