Tasks, predecessors and times - process design, Operation Management

Assignment Help:

Tasks, Predecessors and Times - Process Design

1329_Tasks, Predecessors and Times - Process Design 1.png

The first step in the procedure is to draw a precedence diagram, shown here, the task labels and times entered in the nodes.

The next step is to determine the cycle time required to deliver the stipulated rate of output: 

Time cycle = productive time available per hour / output per hour

3600 output per hour / (8,000/5*8)) mail shots per hour = 18 seconds

We then calculate the theoretical minimum number of workstations required. This would be the result if it were possible to design the line such that the task times were evenly spread among the workstations; a very unlikely outcome in practice. However, as we will see later, it can be used to assess the utilisation of the practicable line layout produced by the procedure.

286_Tasks, Predecessors and Times - Process Design 2.png

Theoretical minimum number of workstation = Sum of task times/cycle times = 80/18

=4.4 workstations

The next stage, the allocation of tasks to workstations, is usually conducted by heuristic (ie rule-of-thumb) methods. There are several such heuristics; we will use one of the simpler ones, the longest-task- time heuristic, the results of its application being displayed in the table below. It begins with the first workstation and consideration of the candidate tasks that could be allocated to it. In this case there is only one candidate, 'A', since no other task can begin until 'A' is complete. 'A' is allocated, its time entered, and the remaining unassigned part of the 18-second cycle time calculated and entered (18 - 15 = 3 seconds).


Related Discussions:- Tasks, predecessors and times - process design

Scheduling, external factors affecting schedulling

external factors affecting schedulling

Stakeholder analysis in an organisation, Question 1: Emmott (1997) repo...

Question 1: Emmott (1997) reports that "by the 1990's the whole issue of employment relationships became much more subtle". The concentration now is on the relationship between

Line balencing, What do you understand by “line balancing”? What happens if...

What do you understand by “line balancing”? What happens if balance doesn’t exist?

Decisions making and profit maximization, Question 1. It is often said...

Question 1. It is often said that profit maximization is the sole objective of business conduct. Do you agree with this view? Justify your answer using at least one example /

How to compute the expected labor, The following table shows data on the av...

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $30, overhead rate is 1.0 times labor co

Explain object oriented database model, The relational database model gaine...

The relational database model gained popularity and many proponents during the 1980's and 1990's, a period of time in which IT organizations were seeking to consolidate data from m

Explain why do reporting systems increase the risk, Why do reporting system...

Why do reporting systems increase the risk of semantic security problems?

Explain the need for management to motivate their employees, Problem 1: ...

Problem 1: Team working is gaining importance in modern organisations. Do you agree that all members of an organisation could be expected to be team players? Discuss with exa

What is meant by perpetual inventory system?, Ask question #What is meant b...

Ask question #What is meant by perpetual inventory system?Minimum 100 words accepted#

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd