Tasks, predecessors and times - process design, Operation Management

Assignment Help:

Tasks, Predecessors and Times - Process Design

1329_Tasks, Predecessors and Times - Process Design 1.png

The first step in the procedure is to draw a precedence diagram, shown here, the task labels and times entered in the nodes.

The next step is to determine the cycle time required to deliver the stipulated rate of output: 

Time cycle = productive time available per hour / output per hour

3600 output per hour / (8,000/5*8)) mail shots per hour = 18 seconds

We then calculate the theoretical minimum number of workstations required. This would be the result if it were possible to design the line such that the task times were evenly spread among the workstations; a very unlikely outcome in practice. However, as we will see later, it can be used to assess the utilisation of the practicable line layout produced by the procedure.

286_Tasks, Predecessors and Times - Process Design 2.png

Theoretical minimum number of workstation = Sum of task times/cycle times = 80/18

=4.4 workstations

The next stage, the allocation of tasks to workstations, is usually conducted by heuristic (ie rule-of-thumb) methods. There are several such heuristics; we will use one of the simpler ones, the longest-task- time heuristic, the results of its application being displayed in the table below. It begins with the first workstation and consideration of the candidate tasks that could be allocated to it. In this case there is only one candidate, 'A', since no other task can begin until 'A' is complete. 'A' is allocated, its time entered, and the remaining unassigned part of the 18-second cycle time calculated and entered (18 - 15 = 3 seconds).


Related Discussions:- Tasks, predecessors and times - process design

Integrated solutions in product design, Integrated solutions in product des...

Integrated solutions in product design and control of machinery are based on    CAD and CAM technologies.

Explain the precedence relationships and the estimated times, A project con...

A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activit

Simplex method , Q3. Solve the following Linear Programming Problem using S...

Q3. Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 4 X1+ X2 2 X1, X2 0

Explain coca cola''s change in sales policy, How would you respond to Coca ...

How would you respond to Coca Cola's change in sales policy? How would you ensure Pepsi's board that this response will allow you to remain competitive and profitable?

Explain marketplace and demonstrate its effectiveness, Access how technolog...

Access how technology and the changing demands of customers have impacted the movie business. Suggest a strategy for Netflix's to prevent a new entrant into the marketplace and dem

Compute quantity is a fractional amount, The Bluegrass Distillery produces ...

The Bluegrass Distillery produces custom-blended whiskey. A particular blend consists of rye and bourbon whiskey. The company has received an order for a minimum of 400 gallons o

Linear Programming Problem, Solve the following Linear Programming Problem ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

What is the distinction between prediction and forecasting, Question 1: ...

Question 1: Show the nature and importance of the four logistics-related elements of customer service. Question 2: (a) Describe the concept of supply chain management.

Explain what should johnson estimate time and parts costs, Johnson Industri...

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labour hours, and

Find what is the economic order quantity, The Central Valve Company sells i...

The Central Valve Company sells industrial valves and fluid control devices. One of Central's most popular valves, the Western, has an annual demand of 6,000 units. The price of ea

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd