Tasks, predecessors and times - process design, Operation Management

Assignment Help:

Tasks, Predecessors and Times - Process Design

1329_Tasks, Predecessors and Times - Process Design 1.png

The first step in the procedure is to draw a precedence diagram, shown here, the task labels and times entered in the nodes.

The next step is to determine the cycle time required to deliver the stipulated rate of output: 

Time cycle = productive time available per hour / output per hour

3600 output per hour / (8,000/5*8)) mail shots per hour = 18 seconds

We then calculate the theoretical minimum number of workstations required. This would be the result if it were possible to design the line such that the task times were evenly spread among the workstations; a very unlikely outcome in practice. However, as we will see later, it can be used to assess the utilisation of the practicable line layout produced by the procedure.

286_Tasks, Predecessors and Times - Process Design 2.png

Theoretical minimum number of workstation = Sum of task times/cycle times = 80/18

=4.4 workstations

The next stage, the allocation of tasks to workstations, is usually conducted by heuristic (ie rule-of-thumb) methods. There are several such heuristics; we will use one of the simpler ones, the longest-task- time heuristic, the results of its application being displayed in the table below. It begins with the first workstation and consideration of the candidate tasks that could be allocated to it. In this case there is only one candidate, 'A', since no other task can begin until 'A' is complete. 'A' is allocated, its time entered, and the remaining unassigned part of the 18-second cycle time calculated and entered (18 - 15 = 3 seconds).


Related Discussions:- Tasks, predecessors and times - process design

How x control chart is used, How X control chart is used? X control cha...

How X control chart is used? X control chart is used with go and not go inspection.

What is utility of optimised production technology, Q. What is utility of o...

Q. What is utility of optimised production technology to manufacturing operations? Optimised production technology (OPT) optimises the employ of ‘bottleneck resources' (restric

Explain the factors affecting motivation, Explain the factors affecting mot...

Explain the factors affecting motivation . Factors influencing motivation: Achievement-Personal satisfaction in problem solving and job completion. Advancement-Promot

Explain great discrepancy in service levels, After graduation, you decide t...

After graduation, you decide to go into a partnership in an office supply store that has existed for a number of years. Walking through through the store and stockrooms, you fin

Introduction to the operations function, Introduction to the Operations Fun...

Introduction to the Operations Function Firstly, consider the economy where gross domestic product (GDP) has been subdivided into its major divisions which are agriculture, ma

Describe what was the labor productivity, Last week employees at Renee's Fa...

Last week employees at Renee's Fashions worked 360 hours to produce 128 garments. Of these, 8 were seconds which were sold at the outlet store for $90 each. The remaining 120 garme

Explain during the campus spring fling, During the campus Spring Fling, the...

During the campus Spring Fling, the bumper car amusement attraction has a problem of cars becoming disabled and in need of repair. Repair personnel can be hired at the rate of $20

Developed a project and is interested in what, A company has developed a pr...

A company has developed a project and is interested in accelerating the schedule if possible. Below network diagram and tables show all information needed. Partial crashing is avai

Order winning and order qualifying criteria, 1. What you think might be the...

1. What you think might be the order winning and order qualifying criteria for: McDonald's, Southwest Airlines and a university?  Answer:

Perseverance and job related knowledge, (Emotional intelligence; a key fact...

(Emotional intelligence; a key factor to success) I want a 20 question survey for this topic, based on these 5 factors Ethic and integrity, Leadership, Perseverance, Job related kn

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd