For a project, following information is given:
Activity I.P Expected Time in Weeks
A - 5
B - 6
C A 7
D A,B 2

(i) Draw the network
(ii) Find the critical path & project completion time.

Related Discussions:- System Analysis and Design

Explain how will you account for any wastage, You are the branch operations...

You are the branch operations manager for a leading manufacturing company. The following are the bill of materials (BOM), Master Production Schedule, and Inventory Record Sheet for

Describe the optimal order size, A retail outlet has its own production fac...

A retail outlet has its own production facility for producing denim cloth. The ordering cost ($150) is the cost of setting up the production process to make the denim cloth. The ca

Steps in work measurement, Steps in  work Measurement: The  various s...

Steps in  work Measurement: The  various steps  are : 1. Break the job  into elements: 2. Record the observed time  for each  element  by means  of time  study  synthesi

Describe database administrator for the itunes store, If you were the datab...

If you were the database administrator for the iTunes store, how might you use predictive analysis to determine which artists and movies will sell most next year?

Explain total annual inventory costs, The Ambrosia Bakery makes cakes for f...

The Ambrosia Bakery makes cakes for freezing and subsequent sale. The bakery, which operates five days a week, 52 weeks a year, can produce cakes at the rate of 116 cakes per day.

Calculate the standard time for the job, An  industrial  engineer  has obta...

An  industrial  engineer  has obtained the  following data  in connection  with a  time  study on  the lines  of the Hawthorne  studies  taking  four different  elements  and five

Explain the essence of project management is risk management, Consider the ...

Consider the following statement: "The essence of project management is risk management." What does it mean in terms of completing a project successfully? Support your response wit

Identify different types of quality system, (a) Identify different types of...

(a) Identify different types of quality system/philosophy/approaches and critically discuss the relative effectiveness of the philosophy, systems and approaches (b) Evaluate the

Attributes - statistical process control, Attributes - Statistical Process ...

Attributes - Statistical Process Control On the other hand, some processes have outputs with attributes to be controlled where counting the number of defects is more appropria

Observation methods, Observation  Methods: The  observation methods i...

Observation  Methods: The  observation methods is the most commonly used  methods  especially in studies  relating to  behavioural sciences. In a way we all observe things aro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd