For a project, following information is given:
Activity I.P Expected Time in Weeks
A - 5
B - 6
C A 7
D A,B 2

(i) Draw the network
(ii) Find the critical path & project completion time.

Related Discussions:- System Analysis and Design

Explain the elements of an organizations environment, Describe the elements...

Describe the elements of an organization's external environment. Why is it important to understand the external environment?

Explain ford and google companies similar and different, But from the outsi...

But from the outside, it's getting harder every day to articulate what Google is. Is it a Web company? A software company? Something else entirely? How are the situations for Fo

Explain model of behaviour modification, Model of behaviour modification an...

Model of behaviour modification and the four contingencies of reinforcement.(cited/referenced)

What are strategies for creating an open environment, 1 Develop an ld score...

1 Develop an ld score for the current layout. What problems can you identify with the current layout? 2. Use trial and error to come up with a better layout that lowers the ld s

Compute the standard time for each work, The Arkade Company has decided to ...

The Arkade Company has decided to use a 15 percent allowance factor based on job time. Calculate the standard time for each work element and for the total job. The frequency equals

Explain gender differences on the reading scores, You are in charge of a pr...

You are in charge of a project that is investigating the effects of gender differences on the reading scores of first, third, and fifth grades in three different school districts.

Explain how might you use quality tools to determine, a) Determine the valu...

a) Determine the value of the p-bar, the mean fraction defective. Then determine the control limits for the p-chart using 99.73% confidence level (3 standard deviations). Is this p

What was jimmy efficiency, 1) Jimmy runs a business in his basement that sp...

1) Jimmy runs a business in his basement that spin aligns and marks golf balls with logos for tournaments. The automated machine goes through three serial steps; the first step tak

Compute the bias and mad for each set of forecasts, Given the series of dem...

Given the series of demand data below Period: 1 2 3 4 5 6 7 8 9 10 Demand: 43 31 52 44 23 48 40 39 30 40 Calculated forecasts for periods 7 through 11 using moving average

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd