For a project, following information is given:
Activity I.P Expected Time in Weeks
A - 5
B - 6
C A 7
D A,B 2

(i) Draw the network
(ii) Find the critical path & project completion time.

Related Discussions:- System Analysis and Design

Explain various goods from similar amount of resources, Explain various num...

Explain various numbers of goods as output from similar amount of resources (input) in improving productivity. Management can raise productivity that is management can get vari

Describe experienced unprecedented growth, Your public school district has ...

Your public school district has experienced unprecedented growth and as a result has built the new 500 student North Park Elementary School. The district has three older and small

Make scope statement for this project that contains examples, You are in ch...

You are in charge of organizing a dinner-dance concert for a local charity. You have reserved a hall that will seat 40 couples and have hired a jazz combo. Develop a  of all the

Explain programme evaluation and review technique, Explain Programme Evalua...

Explain Programme Evaluation and Review Technique. Programme Evaluation and Review Technique (PERT): It is a technique used for scheduling and controlling the projects whether

Explain an in-n-out pay strategy, An In-N-Out Pay Strategy: Costa Vida's De...

An In-N-Out Pay Strategy: Costa Vida's Decision to Boost Pay

Explain exploitation of the potential of a new technology, What are the thr...

What are the three trends that require managers to adopt a global perspective to exploit the potential of a new technology?

Disadvantages, What are the disadvantages of operation management?

What are the disadvantages of operation management?

Explain what is the amortization schedule, 30 year mortgage at 10 percent i...

30 year mortgage at 10 percent interest rate. Loan amount $300000. 1. What is the amortization schedule for the 1st year (12moonths) 2. What is the remaining balance of the 29years

How to compute the expected labor, The following table shows data on the av...

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $30, overhead rate is 1.0 times labor co

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd