For a project, following information is given:
Activity I.P Expected Time in Weeks
A - 5
B - 6
C A 7
D A,B 2

(i) Draw the network
(ii) Find the critical path & project completion time.

Related Discussions:- System Analysis and Design

Transportation, I have a transportation problem which is given below: The ...

I have a transportation problem which is given below: The sunshine tomato soup shippers produce tomato soup at three west coast canneries in Bakersfield, phoenix, and Eugene. The

Explain what is framing and how frames work in negotiation, What is framing...

What is framing and how frames work in negotiation. Describe an example

Explain which path is the critical path, Given the information below: 1....

Given the information below: 1. Construct a network using the AON (Activity on Network method) like we did in class. See problem 3.4 on page 90 and its answer in the Appendix on

What is industrial mnagement, What is industrial mnagement? Explain. ...

What is industrial mnagement? Explain. Industrial Management: Industrial Management includes guidance, leadership and control or efforts of a group of individuals toward sev

Explain partitioning a population into hierarchical group, Partitioning a p...

Partitioning a population into hierarchical groups or levels and selecting a sample from each group or level is known as which of the following? Simple random sampling Stra

Explain product development, Explain product development. Product Devel...

Explain product development. Product Development is an activity that involves design or redesign and fabrication of modified or new product and after that testing this to find

Explain what order should these jobs be done, A machine shop has two machin...

A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three

Explain and identify the appropriate tools and techniques, Identify and dis...

Identify and discuss the four basic phases of the Phased Project Planning process. Explain how you will apply the innovative process to change your selected organization. Ide

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd