Streams not wholly alluvial - alluvial streams, Civil Engineering

Assignment Help:

Streams Not Wholly Alluvial

In streams which are not wholly alluvial, consisting of bed of pebbles, rock, etc. the liner waterway is kept equal to the actual surface width of the stream, measured from edge to edge along the high flood level line.

Streams with Rigid Boundaries

The bridge should span from bank to bank, measured along the high flood level line.

Streams which Overflow the Banks

In streams which overflow the banks, the waterway is kept equal to the Lacey's regime width and the river is provided with guide bunds to train the flow.

Span Arrangement

The number of spans and the span length are decided on the basis of the well-known thumb rule that the cost of the superstructure equals the cost of the substructure and foundations. Roughly, the span is 1.5 times the height of the pier from the bottom of the foundation to the top of the pier.

Clearance

Clearance is provided above the high flood level upto the levels where bearings are fixed for accommodating any trees floating along the river. The clearance depends upon the discharge, and varies from 0.15 m for small discharge (upto 0.3 cu m per sec) to 1.5 m for discharge over 3000 cu m per sec.


Related Discussions:- Streams not wholly alluvial - alluvial streams

Backward and forward curved vanes in pumps, Backward curved vanes vs. forwa...

Backward curved vanes vs. forward curved vanes in pumps  Power of a pump is related to discharge as follows: Power = k 1 Q + (k 2 Q 2 / tan A) Where K 1 and K 2 are

State the term - total loss of prestress, Total loss of prestress The ...

Total loss of prestress The total amount of losses of prestresses may be accounted for in a prestressed concrete member by adding different losses which may take place for tha

Measure the stress increment, A raft of size 4 m × 4 m carries a uniform lo...

A raft of size 4 m × 4 m carries a uniform load of 200 kN/m 2 . Using the point load approximation with four equivalent point loads, measure the stress increment at a point in the

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Define inspection of pier or abutment, Define Inspection of Pier or Abutmen...

Define Inspection of Pier or Abutment? Inspection of pier/abutment may then be carried out as under: i. Conduct visual inspection of the entire surface using up and down swe

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Keywords of road pavements, Keywords of Road Pavements: Pavement : T...

Keywords of Road Pavements: Pavement : That part of a road which structurally supports the vehicles travelling on a road. Flexible Pavement   : A layered system of pave

Explain the toxic characteristics - hazardous waste, Explain the Toxic Char...

Explain the Toxic Characteristics - Hazardous Waste - From the results of either  - Extraction Procedure(EP) toxicity (prior to March 1990) or Toxicity Characteristic Leachi

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd