Steam and power generation equipment, Mechanical Engineering

Assignment Help:

Q. Steam and Power Generation Equipment?

Locating steam and power generation equipment outside of the process areas ensures that critical facilities feeding major portions of the plant are protected from possible fires or explosions in the process areas. Non-critical steam generators (supplying less than 25% of total demand, or only supply a single plant) may be located within a process area with spacing as for fired heaters.

Central services, such as cooling towers, boilers, power stations and electrical substations shall be located centrally but away from hazardous areas so they will neither be affected by a fire or explosion within the plant nor provide a source of ignition for any potential flammable liquid or gas release. Maintain adequate separation between different utility services because utility losses could then lead to unsafe conditions in other plant units, possibly creating fires or explosions. Increase the reliability of utilities by keeping adequate spacing between boilers or generators. Refer to the Appendices for suggested adequate separation between different utilities.

Properly pressurize substations in accordance with NFPA 496 or install separate electrical substations and motor control centers. Locate substations away from hazardous areas to increase the reliability of the power supplies should an accident occur. Bury electrical distribution cables to limit their exposure to explosions, fires, storms and vehicles and to ease fire fighting accessibility.


Related Discussions:- Steam and power generation equipment

Gas metal arc welding-principle of operation, GAS METAL ARC WELDING-PRINCIP...

GAS METAL ARC WELDING-PRINCIPLE OF OPERATION Gas Metal Arc Welding (GMAW) is one of the arc welding processes in which an electric arc is formed and maintained between a continuo

Construct a plain scale, Construct a plain scale: The distance between...

Construct a plain scale: The distance between Indore and Bhopal is 180 kilometer. It is represented on the map via 9 centimeter. Construct a plain scale for such map, illustra

Fluids, show a schematic circuit diagram of a electric hydraulic gear pump...

show a schematic circuit diagram of a electric hydraulic gear pump with adjustable with one direction flow and explain the operation

Find the stresses by finite method, The stepped bar in Fig Q6 is stretched ...

The stepped bar in Fig Q6 is stretched along the vertical axis and the maximum upward displacement is found to be 0.008 m. The bar has cross-sectional areas of A 1 and A 2 ov

Answer of the question, Classification of dynamometers, with thein neat sk...

Classification of dynamometers, with thein neat sketch with working ?

Cutting tools, calculate carbide tool and you are required to turn 60mm dia...

calculate carbide tool and you are required to turn 60mm dia piece of C20

Capp for machining process, CAPP for Machining Process This explained ...

CAPP for Machining Process This explained mainly two different approaches to Computer Aided Process Planning, i.e.  (a) Variant approach, and  (b) Generative approach.

Thermodynamic Project, ES 347 - Thermodynamics Project Assigned: 3/28/2013...

ES 347 - Thermodynamics Project Assigned: 3/28/2013 Due: 4/25/2013 Problem specification 5 kg of air is contained in a piston-cylinder device, initially at a pressure of 2MPa and a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd