Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Q. Steam and Power Generation Equipment?
Locating steam and power generation equipment outside of the process areas ensures that critical facilities feeding major portions of the plant are protected from possible fires or explosions in the process areas. Non-critical steam generators (supplying less than 25% of total demand, or only supply a single plant) may be located within a process area with spacing as for fired heaters.
Central services, such as cooling towers, boilers, power stations and electrical substations shall be located centrally but away from hazardous areas so they will neither be affected by a fire or explosion within the plant nor provide a source of ignition for any potential flammable liquid or gas release. Maintain adequate separation between different utility services because utility losses could then lead to unsafe conditions in other plant units, possibly creating fires or explosions. Increase the reliability of utilities by keeping adequate spacing between boilers or generators. Refer to the Appendices for suggested adequate separation between different utilities.
Properly pressurize substations in accordance with NFPA 496 or install separate electrical substations and motor control centers. Locate substations away from hazardous areas to increase the reliability of the power supplies should an accident occur. Bury electrical distribution cables to limit their exposure to explosions, fires, storms and vehicles and to ease fire fighting accessibility.
Q. Materials used in insulation? All materials must be non-corrosive, compatible with other materials and used in accordance with the Manufacturer's recommendations. All mat
Q. Nitrogen storage and vaporizer? Bulk cryogenic storage of nitrogen must be located away from process equipment, preferably at the edge or corner of the process area where fi
Phase 1 Initially ALL Valves A, B, C, D, E and F are closed. ALL Tanks A, B, C, D, E are separated and each sealed from the atmosphere. Tank E initially has 2' of air @
Q. Flange Facing and Surface Finish? Raised face flange facings are preferred. Flat face flanges to be used only when mating with like equipment (fabricated from brittle mat
polytropic process
Explain Atmospheric Pressure (P atm ) Atmospheric Pressure is the pressure exerted by atmospheric air on any surface. It is calculated by a barometer. The standard values of it
Charpy impact tests, when required shall comply. Impact tests shall be conducted at the minimum design metal temperature or at a lower temperature and shall meet or exceed energ
A 2 Kg mass is suspended in a box by a spring as shown in figure. The box is put on a platform having vibration y = 0.8 sin 6t cm. calculate absolute amplitude of mass
Determine magnitude and direction of the resultant force: A system of forces is acting at the corner of a rectangular block as shown in the figure. Determine magnitude and di
Deflection at the centre - maximum deflection: A simply supported beam of span 6 m is subjected to Udl of 24 kN/m for a length of 2 m from left support. Discover the deflectio
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd