standerd costing, Managerial Accounting

Assignment Help:
Ask queThe standard cost of chemical mixture ~ PQ’ is as follows:
40% of material P @ Rs. 400 per kg.
60% of material Q @ Rs. 600 per kg.
A standard loss of 10% is normally anticipated in production. The following
particulars are available for the month of March, 2005.
180 kgs of material P have been used @ Rs. 680 per kg.
220 kgs of material Q have been used @ Rs. 360 per kg.
The actual of production of ‘PQ’ was 369 kgs.
Calculate the following variance:
a) Material Price Variance
b) Material Usage Variance
c) Material Mix Variance
d) Material Yield Variance
stion #Minimum 100 words accepted#

Related Discussions:- standerd costing

Management decision making, Decision-making is an integral part of all ...

Decision-making is an integral part of all management functions. It is the process of choosing the among alternative courses of action. Managers have to

Facets of cash management, Cash management is related along with the manage...

Cash management is related along with the management of: Cash outflows and inflows of the firm Cash flows inside the firm Cash balances as financing deficit and inve

Explain the concepts of costs, Explain the concepts of costs. A cost ac...

Explain the concepts of costs. A cost accountant is mainly concerned with the following cost concepts. 1. Concept of objectives: it is this concept that gives direction to

State programmed budget, Explain about Programmed budget It having expe...

Explain about Programmed budget It having expects revenues and cost of various products or projects that are termed as the main programmers of the firm. Such a budget can be pr

Bugeting, PART 1 Carlton Ltd operates at capacity and makes glass-topped d...

PART 1 Carlton Ltd operates at capacity and makes glass-topped dining tables and wooden chairs which are then typically sold as sets of four chairs with one table. However, some c

Application areas of linear programming, 5 application areas of linear prog...

5 application areas of linear programing in management accounting

Objectives of receivables management, After going through this section, you...

After going through this section, you must be capable to: Know the need for establishing sound credit policy; Identify the different credit policy variables; Know the cred

Accounting for pension plans, how do i calculate the actuarial gains or los...

how do i calculate the actuarial gains or losses on the present value of plan obligations?

Explain the shut down cost, Explain the Shut down cost A cost which wi...

Explain the Shut down cost A cost which will be still be required to be incurred even though a plant is closed or shut down for a temporary period. Ffor example the cost of

The f–test , The F–test    The significance of the regression results...

The F–test    The significance of the regression results can be tested by using the F- statistics. The F-statistics is a ratio which compares the explained sum of squares and t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd