Specification of wood work for door, Civil Engineering

Assignment Help:

Q. Specification of Wood work for Door?

1. General - Timber for door, window and ventilators frames shall be as specified. Timber shall be sawn in the direction of the grains. All member of a frame shall be of the same species of timber and shall be straight without any warp or bow. Frames shall have smooth, well-planed (wrought) surfaces the depth of the rebate for housing the shutter shall be 15 mm, and the width of the rebate shall be equal to the thickness of the shutters. A tolerance of ± 3 mm and 2 mm shall be permitted in the speci¬fied finished dimensions of timber sections in frames.

2. Joints - The frames shall have dovetail joints. The Jamb post shall be through tenoned into the mortise of the transoms to the full thickness of the transoms and the thickness of the tenon shall be not less than 2.5 cm. The tenons shall closely fit into the mortise without any wedging or filling. The contact surface of tenon and mortise before putting together shall be glued with polyvinyl acetate dispersion based adhesive and pinned with 10 mm dia hard wood dowels, or bomboo pins or star shaped metal pins. The joints shall be at right angles when checked from the inside surfaces of the respective members. The joints shall be pressed in position.

3. Fixing of frames - The frames shall be got inspected and approved by the Enginee-in-Charge before being painted, The surface of the frames abutting masonry or concrete and the portions of the frames embedded in floors shall be given a coating of coal tar. Frames shall be fixed to the abutting masonry or concrete with minimum of three holdfasts or metallic fastners as specified.

4. Measurements - Wood work wrought, framed and fixed shall be measured for finished dimension without any allowance for the wastage or for dimensions beyond specified dimension without any allowance for the wastage or for dimensions beyond specified dimensions.


Related Discussions:- Specification of wood work for door

Structural analysis, steps to analysis a portal frame with sway condition

steps to analysis a portal frame with sway condition

Determine the geometrical parameters for layout, Q. A crossover is to be la...

Q. A crossover is to be laid between two parallel B. G. tracks at 4.725 m centers by using 52 kg, 1 in 8½ and 1 in 12 turnouts. For this layout, i. Determine the main geometrica

An alternative test to confirm concrete strength, Question If concrete comp...

Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is

Explain the bearing capacity failure, A continuous wall footing, 1 m wide,...

A continuous wall footing, 1 m wide, rests on sand, the water table lying at a great depth. The corrected N-value for the sand is 10. Verify the load which the footing can support

Dressing of stones.., what is dressing of stones and its various types

what is dressing of stones and its various types

Abrasion test - tests on stones, Abrasion Test:   This test is carri...

Abrasion Test:   This test is carried out on stones used as aggregates for road construction. The test result shows the suitability of stones against   the grinding action u

Will water damage concrete, As far as only concrete is concerned i.e. plain...

As far as only concrete is concerned i.e. plain concrete, the effect of water seepage is very little (depending upon the grade of concrete) whereas for RCC (reinforced cement concr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd