Span of management-managerial function of organizing, Project Management

Assignment Help:

Span of management

Span of management refers to the number of subordinates who directly report to one superior. If a manager has too many subordinates then his span is wide and in such cases a manager maintains loose supervision. A manager with few subordinates is said to have narrow span and closer supervision.
   
A wide span results in fewer levels of management resulting in what is known as a flat organization structure. A flat organization is generally characterised by better communication because of shorter lines of communication.
   
A narrow span means more levels of management resulting into a tall organization. A tall organization has longer lines of communication which means that the chances of information getting distorted as it passes from level to level are much higher. Besides the overall costs of management are much higher than in flat structures. The close supervision resulting from narrow spans may make subordinates feel overcontrolled, while the loose supervision due to wide spans may mean that the manager could lose touch with his subordinates and this may lead to reduced productivity especially if the subordinates are not adequately self motivated. The span of management is influenced by certain factors some of which are listed below:
   
They include the competence of the manager and his subordinates. If both are competent, then a wide span is possible, where either or both are not competent, then a narrow span is preferable. The physical dispersion of workers also affects span of management, if employees are scattered in different places, then only a narrow span is possible. The amount of other non supervisory work that the manager has, the more, the less the number of people he can supervise effectively.

The degree of task similarity, if tasks are similar and if jobs are simple and routine, then a wide span is possible. The frequency with which new problems and circumstances keep arising also affects the span. If too many then a narrower span is preferable.


Related Discussions:- Span of management-managerial function of organizing

Why do i need project management, Q. Why do I need project management? ...

Q. Why do I need project management? One more way of asking this question is What if I do not bother with project management? The reality is all projects demand some extent of

Network, charateristics of a good network

charateristics of a good network

Explain about the process of managing risk, Explain about the process of ma...

Explain about the process of managing risk. A process of managing risk: 1. Risk committee establish to address risk issues categorised for example usual risk audits, to estimat

Management skills required for a successful manager, How are the management...

How are the management skills required for a successful manager? Management Skills: The skills needed of a successful manager, while he is working into a industry,

Multilpe choice questions, Which of the following statements about variable...

Which of the following statements about variable and fixed expenses, as they relate to relevance , is/ are true? (1) Variable expenses may or may not be, relevant costs? (2) Varia

Uses and benefits of risk breakdown structure, Uses and Benefits of RBS  ...

Uses and Benefits of RBS  The main uses and benefits of the RBS are outlined in this section.  Risk identification aid  Risk Breakdown Structure is used as a list that

Project management process, Project management Process According to PMB...

Project management Process According to PMBoK, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed

How you would estimate the project management activity, Explain how you wou...

Explain how you would estimate the project management activity. Project management: This effort is dependent onto two things as whether a full-time project manager is to be

Assignment 2 intro to project manage, Assignment #2 . Assignment #2 Yo...

Assignment #2 . Assignment #2 You will need to first develop a customer''s Request for Proposal (RFP), then go to the simplified Project Proposal on pages 76-78 of your text a

Discuss importance of value management in project life cycle, Question: ...

Question: (a) Past projects have shown that cost escalation is a common phenomenon with respect to the amount by which actual costs increases overrun the initial estimated cos

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd