Solve lp problem using the graphical technique, Operation Management

Assignment Help:

Consider the following LP problem:
Maximize Z = 30X1 + 10X2
Subject to: 3x1 + x2 300
x1 + x2 200
x1 100
x2 50
and x1,x2 0
Solve using the graphical technique


Related Discussions:- Solve lp problem using the graphical technique

Trade offs in the design of operations systems , Trade-Offs in the Design ...

Trade-Offs in the Design of Operations Systems  When contemplating a change in business strategy, it must be borne in mind that an operations system can be designed to do cer

Explain how to create a living, What would you suggest to companies on how ...

What would you suggest to companies on how to create a living, adapting marketing plan?

What are programmed and non-programmed decisions, What are programmed and n...

What are programmed and non-programmed decisions? Programmed decisions are which made in accordance with some procedure, rule or habit. Non-Programmed decisions are those which

Explain what types of interpretations might a consumer make, Reflect on the...

Reflect on the GEICO commercials you have seen and those discussed in your textbook. One of the things that these ads do is invite the audience to become involved and make an inter

Explain what is the roic, (Oscar's Office Building) Oscar is considering ge...

(Oscar's Office Building) Oscar is considering getting into the real estate business. He's looking at buying an existing office building for $1.8 million in cash. He wants to estim

Ethical organizations are founded through ethical leadership, Discuss how e...

Discuss how ethical organizations are created through ethical leadership and organizational structures and systems.

Mean value - statistical aspects of variability, Mean value - Statistical A...

Mean value - Statistical Aspects of Variability The arithmetical mean value (µ, mu) of the measurements can be readily calculated, as follows. Let the class mid- point values

Describe find the shortest route from node 1 to node 6, Find the shortest r...

Find the shortest route from Node 1 to Node 6. From Node To Node Distance 1 2 150 1 3 200 2 3 100 2 4 200 2 5 50 3 4 350 3 5 300 4 6 100 5 6 100 Which Answer is it? 300 450 550 650

Explain efficiency advantages of a new technology, Consider this scenario: ...

Consider this scenario: You are the senior executive responsible for technology innovation for Company A. The company learns of the cost and efficiency advantages of a new technolo

Explain what is the net income for this firm, Lifeline, Inc., has sales of ...

Lifeline, Inc., has sales of $585,000, costs of $273,000, depreciation expense of $71,000, interest expense of $38,000, and a tax rate of 35 percent. What is the net income for thi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd