Software project planning, Computer Engineering

Assignment Help:

Software Project Planning

In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost had relatively little impact in estimates of. Presently, software is the most expensive elements in most computer-based systems. With large cost estimation error can make the variation among loss and profit. For the developer Cost overrun can be disastrous.

Software effort and cost estimation will never be an exact science.  There are Too many variables human Technical, Environmental, Political can affect the ultimate effort and cost of software applied to build it. However software project estimation can be transformed from a mysterious art to a series of systematic steps that gives estimates with acceptable risk.

To achieve reliable effort and cost estimates a number of options arise.

1.    The Delay estimation until late in the project (obviously, we can achieve 100% accurate estimates after the project is completed)

2.    The Base estimates on same projects that have already been completed.

3.    The Use relatively simple decomposition techniques to generate project effort and cost estimates.

4.    The Use one or more empirical models for software cost and effort estimation.

Unfortunately, the first option moreover attractive is not practical.  The Cost estimates must be provided up- front.   However, we will recognize that the longer we wait the more we know and the more we know the less likely we are to make serious errors in our estimates.

The option can work reasonably well if the present project is quite same to previous efforts and other project   influences  for example business   conditions,   the   customer,   the   SEE   deadlines  are   equivalent. Unfortunately, previous experience has not always been a good indicator of future results.

The remaining options are viable approaches to software project estimation. Ideally, the method noted for each option should be applied in tandems each used as a cross-check for the other.  The Decomposition techniques will take a divide and conquer approach to software project estimation. By decomposing a project into a major functions and related software engineering activities effort and cost estimation can be performed in a stepwise fashion.  Empirical estimation models can be used to complement decomposition methods and offer a potentially valuable estimation approach in their own right.  The model is based on experience historical data and takes the form.

d=f(Vi)

Where d is one of a number of estimated values example for effort, cost, project duration and Vi are selected independent parameters for example estimated LOC or FP

The Automated estimation tools implements one or more decomposition methods or empirical models.

When combined with an interactive human machine interface automated tools give an attractive option for estimating. Like systems the characteristics of the development company for example experience, environment and the software to be developed are described.  Effort and Cost estimates are derived from these data.

As the historical data used to seed the estimate each of the viable software cost estimation options is only as good. If no historical data exist costing rests on a very shaky foundation.


Related Discussions:- Software project planning

Name of current gui status is there, In which system field does the name of...

In which system field does the name of current gui status is there? The name of the present GUI STATUS is available in the system field SY-PFKEY.

String, super string checker

super string checker

What are the blocks of microprocessor based system, What are the blocks of ...

What are the blocks of microprocessor based system 1.  The Memory and I/O System 2.  The DOS Operating System 3.  The Microprocessor

What is error detection code, What is Error detection code? It is a bin...

What is Error detection code? It is a binary code that notice digital errors during transmission. The detected errors cannot be correct but the presence is shown.

Difference between a null pointer and a void pointer, A NULL pointer is a p...

A NULL pointer is a pointer of any type whose value is zero. A void pointer is a pointer to an object of an unknown type, and is guaranteed to have sufficient bits to hold a pointe

What is script-fu in gimp, Sript-Fu is the first GIMP scripting extension. ...

Sript-Fu is the first GIMP scripting extension. Extensions are split processes that communicate with the GIMP in the similar way that plug-ins do. The distinction is that extension

Enumerate about the specialised hardware, Enumerate about the Specialised h...

Enumerate about the Specialised hardware Specialised hardware such as protected memory or cryptographic memory module for storing and protecting the keys proves to be a good s

Representation scheme in artificial intelligence, Representation scheme in ...

Representation scheme in artificial intelligence: It is not hard to see why logic has been popular representation scheme in AI: In this way, It is easy to represent knowl

Major problems associated in writing with cache memories, Q. Major problems...

Q. Major problems associated in writing with cache memories? The data in main and cache memory can be written by processors or I/O devices. The major problems associated in wri

The major underlying concepts of object orientation, Objects, messages, cla...

Objects, messages, class, inheritance and polymorphism are the major concepts of object orientation.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd