software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

What are the steps for benchmarking, Question 1: (a) ISO 9000:2008 spec...

Question 1: (a) ISO 9000:2008 specifies the requirements for a Quality Management System. The standard is based on eight quality management principles upon which to develop an

Risk management in the tqm framework, Risk Management  in the TQM Framewor...

Risk Management  in the TQM Framework   Total  Quality Management (TQM) is one of the widely used project management technique or approach. TQM mainly concentrates on process m

Steps of heuristic method, Steps of Heuristic Method The heuristic ap...

Steps of Heuristic Method The heuristic approach involves following procedural steps: Identify the work ( job) Break down the work into elemental tasks or steps for

Tolerance and surface finish, Tolerance and Surface Finish Design engi...

Tolerance and Surface Finish Design engineers are always blamed of specifying closer tolerances than necessary. It  is obvious that to achieve a tolerance of ± 0.001 mm is mor

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

Projecr, A paper mill produces two grades of paper viz., X and Y. Because o...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper

Explain the flexibility plans, Question 1: In order to meet the constan...

Question 1: In order to meet the constant changing requirements of the modern business world, organisations are compelled to develop flexibility plans. (a) Explain the vario

Culture, Task 1- Group powerpoint with 1000 word individual assignment You ...

Task 1- Group powerpoint with 1000 word individual assignment You will be allocated to a group. You are part of a global electronics company that has offices in Germany, Paris, Ind

Increasing interest in employ of application development, Increasing intere...

Increasing interest is being taken in the employ of quick application development. Why is that, and are there any dangers related with the RAD approach? RAD has come to promine

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd