Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Iso 9001 certification, ISO 9001 is the most difficult of the three stan...

ISO 9001 is the most difficult of the three standards to be chosen for certification , because it includes all the the twently elements. This comprehensive certification i

Explain the sources of conflict, In response to changing customer demands a...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

What are the advantages of division of labour, What are the Advantages of D...

What are the Advantages of Division of Labour? Advantages of Division of Labour: As very similar worker does the same work frequently:- a. It gains proficiency and ski

External factors of syringe management , External Factors Opportunit...

External Factors Opportunity This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attrac

Confidentiality, confidential document in civil project

confidential document in civil project

The series of training sessions to help members, PR has recently joined FPC...

PR has recently joined FPC Company as the new Finance Director. He is needed to work towards getting the finance staff to play a fuller role in the company, becoming more integrate

What are the steps for benchmarking, Question 1: (a) ISO 9000:2008 spec...

Question 1: (a) ISO 9000:2008 specifies the requirements for a Quality Management System. The standard is based on eight quality management principles upon which to develop an

Second elaboration iteration, Perform a status assessment of the second Ela...

Perform a status assessment of the second Elaboration iteration. DO NOT GENERALISE. Assess each activity separately against the outcomes specified for the activity. Generate a deta

Industrial management technique, Thus by the term quality control we mea...

Thus by the term quality control we mean the process of control where the management tries to conform the quality of the product in accordance with the pre determined stand

Project, can make two project for me?

can make two project for me?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd