Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Explain how effective teamwork is beneficial, Question: (a) Explain how...

Question: (a) Explain how effective teamwork is beneficial to both the individual and the organisation. (b) Team leaders have to be on the lookout for symptoms of ineffecti

Contrast cost benefit analysis with investment appraisal, Question: (a)...

Question: (a) Describe cost benefit analysis as used to appraise large public sector investments. (b) Compare and contrast cost benefit analysis with investment appraisal.

Bidding , Bidding is a process in which you  quote money in exchange of go...

Bidding is a process in which you  quote money in exchange of goods or services through an auction. They are two types of auctions: open auction and silent auction. In an open auc

Modification of supply - aggregate planning, Modification of Supply - Aggre...

Modification of Supply - Aggregate Planning Some of the methods by which we can modify the supply to match the demand are: a.Hiring and Lay off of Employees: As this poli

Quality standards, Quality Standards Quality Standards form a framework...

Quality Standards Quality Standards form a framework that helps organisations worldwide to develop products and services in the most efficient way. A quality Standard is a norm

Fixed position based layout, Fixed Position Based Layout As the term its...

Fixed Position Based Layout As the term itself implies, fixed layout involves the movement of men and machines to the product which remains stationary. In this type of layout th

Technique to reduce error and increase customer satisfaction, Question: ...

Question: (a) The National Printing Company has been losing customers and orders due to various delays and errors. The Company wants to identify the problems that might be con

Brown &b hyer, Chapter 6 presents several tools that can be useful when ass...

Chapter 6 presents several tools that can be useful when assessing for project uncertainties. Compare and contrast risk mapping, FMEA, and the gut-feeling method. Which method do y

Give a theoretical overview of the management of change, According to the S...

According to the Society for Human Resource Management's (SHRM) 2007 Change Management Survey Report, the top two obstacles encountered during major organizational change are commu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd