Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Framework for organisational culture, According to Schein (2004),culture is...

According to Schein (2004),culture is essentially an established pattern of behavior built on shared basic assumptions generated by tackling crucial external adaptions and internal

What do you mean by post completion report, What do you mean by post comple...

What do you mean by post completion report? The post completion (PC) report: This report would be created at the closing or finish stage of a project. Post completion rep

Linear programming methods of line balancing, Linear Programming Methods of...

Linear Programming Methods of Line Balancing Assume that a job is broken down into elements tasks and the total duration of all such tasks is 28 minutes. The cycle time i, e,

Relationship-reporting arrangements of manager with sponsor, What type of r...

What type of relationship and reporting arrangements must the project manager have with the sponsor? The sponsor of a project shows the management of the organisation which com

Project management the managerial process, Are you able to assist with assi...

Are you able to assist with assignments mid terms finals at a masters level

Explain the role of the project owner and project sponsor, X Company, a pri...

X Company, a private security firm, has signed a contract to fund the design, construction and running of a local police station. This arrangement is a public private partnership a

Feasibility study for the exploitation of the oil reserves, Question: I...

Question: In the year 2015, the price of petrol has gone up so much that the oil reserves of the Republic of Mauritius start to look interesting to exploit. The oil reserves ar

ASF Mobile App Development, Australian’s Speleological App Project Speleolo...

Australian’s Speleological App Project Speleology is the scientific study of caves and other

How you would organise a project team for rad-type project, Notice how you ...

Notice how you would organise your project team for RAD-type project. What leadership practices would this need by the project leader and what would the team members have to perfor

Analysis the production in manufacturing company, Analysis The factory...

Analysis The factory has the process for the following:  QC of sampling,  receiving orders,  receiving fabrics and accessories,  checking of fabrics,  drawing,  cutting,  sort

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd