Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Benefits of Group Technology, Benefits of Group Technology 1.Reduced F...

Benefits of Group Technology 1.Reduced Flow Times: Compared to the earlier process layout, there are very few halts. Hence flow times are reduced considerably. 2.Process Tim

Describe the various organisational systems, Question 1: Using the "Mat...

Question 1: Using the "Matrix" system of authority and responsibilities, describe the various organisational systems which may be applied to the management of projects. Disc

How to measures defect ratios for the product, Defects found after product ...

Defects found after product delivery per function point Defects found after product delivery per LOC Pre-delivery defects: yearly post-delivery defects Defects per functio

Explain the objectives of a procurement development model, Problem: (a)...

Problem: (a) Explain the objectives of a Procurement Development Model. (b) Explain one Procurement Development Model you are familiar with. (c) "In certain organisation

What is organisation structure in frame work of authority, What is organisa...

What is organisation structure in frame work of authority and responsibility? Organisation Structure: This structure is the systematic arrangement of the people working f

The importance of each phases of the project life cycle, Question (a) D...

Question (a) Discuss the importance of each phases of the project life cycle (b) Assumptions make estimates more accurate. Do you agree with this statement? (c) Outline s

Review of design, Before the preliminary design has progressed further i...

Before the preliminary design has progressed further it should be subjected to a critical review by all those who are connected with the product such as quality engineers

Pm, short note on partnering

short note on partnering

Project cost management, Your project sponsor has asked you and your team t...

Your project sponsor has asked you and your team to refine the existing cost estimate for the project so that there is a solid cost baseline for evaluating project performance. Rec

Real life project, Real life project make as a project manager do it critic...

Real life project make as a project manager do it critical evolution 3000 words

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd