Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

521, HUSKY AIR ASSIGNMENT—PILOT ANGELS The Quality Management Pla

HUSKY AIR ASSIGNMENT—PILOT ANGELS The Quality Management Plan

Describe informative and persuasive presentations, Problem: (a) Describ...

Problem: (a) Describe the difference between informative and persuasive presentations and describe the key strategies for each of these types of presentations. (b) Why is it

Code of professional conduct, A 28 year old quadriplegic man is admitted to...

A 28 year old quadriplegic man is admitted to the hospital with pneumonia and severe pressure ulcers.  You are the enrolled nurse caring for him and hear him asker the doctor that

What do project managers do, Q.  What do project managers do? First of ...

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective

Pm, short note on partnering

short note on partnering

Determining project feasibility and creating schedules, Read the BEC case s...

Read the BEC case study on pages 126–129 of the textbook, and perform the following tasks:   Create a feasibility report for the project in a Word document. Create

Use of both innovative approach in development process, Q. Use of both inno...

Q. Use of both innovative approach in development process? There are many major aspects that will sway the future trends in the development of new products. In the new millenn

Balancing efficiency, Balancing Efficiency An efficient line balancing...

Balancing Efficiency An efficient line balancing will minimize the amount of idle time.  The balance efficiency can be calculated as Eff B = output of task time / in

Components of quality, Components of Quality 1. Product feature shave...

Components of Quality 1. Product feature shave a major effect on sales income ( through market share premium prices etc) . in many industries the total external cust

Project cycle time optimisation, C y c le Time Optimisation Cycle ti...

C y c le Time Optimisation Cycle time optimisation is an operating philosophy of maximising the efficiency of the sub optimal value-added activities while reducing the non-

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd