Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

What value does project management add, Q. What value does project manageme...

Q. What value does project management add? This is extremely difficult to answer in traditional accounting terms for the reason that the real value is in the quality of the end

Customer value - measure for project management value, C ustomer value ...

C ustomer value There is a considerable debate within the business world on whether the companies will have to deliver value for the shareholders or the customers. There are m

Explain on the verbal and non-verbal tactics, Questiuon 1 a) Describe o...

Questiuon 1 a) Describe on the factors that you need to consider when planning the presentation. b) Describe the importance of listening for members of the audience and expl

Cost benefit analysis, How to determine which project have larger net benef...

How to determine which project have larger net benefit between two projects

Conflicts arise between project manager and ppso staff, What are conflicts ...

What are conflicts probable to arise between project managers and PPSO staff? PPSO (Project and Programme support office) staff can, when they are not careful or when they are

TQM, Value Engineering

Value Engineering

What is a project, Q. What is a project? The term project appears to be...

Q. What is a project? The term project appears to be a buzzword that means a lot of different things to different people. Anything for instance from a secretary's "project" to

Project risk, Identifying Project Risk  Risk identification is a proces...

Identifying Project Risk  Risk identification is a process which determines the types of risks that have potential impact on a project. The risk identification is an ongoing pr

Tangible and intangible while applied to costs and benefits, What do you me...

What do you mean by the terms tangible and intangible while applied to costs and benefits? Tangible costs or benefits are those for that a plausible quantitative value can be

Attractiveness of the industry in which ff currently operate, The Board of ...

The Board of FF Supermarket is examining the company's current market position. As part of the review, the Board has asked for an analysis of industry competition to be undertaken

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd