Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

The series of training sessions to help members, PR has recently joined FPC...

PR has recently joined FPC Company as the new Finance Director. He is needed to work towards getting the finance staff to play a fuller role in the company, becoming more integrate

What is project scheduling, Question 1 Briefly explain various activities ...

Question 1 Briefly explain various activities involved in project management Question 2 What is COCOMO? Write necessary steps for cost estimation Question 3 What is proj

What are the contents of project planning document, What are the contents o...

What are the contents of project planning document? Contents of a PPD (project planning document): a. Project resource plans b. Quality control and quality policies proce

Benchmarking - element of total quality management, Benchmarking  is the  p...

Benchmarking  is the  practice of identifying studying and building upon  the best  practices in the industry or in the world. Dynamic companies are constantly monitoring informati

Explain the terms - product and work package, Explain the terms "product" a...

Explain the terms "product" and "work package" and describe how these are related to each other. A product is a particular deliverable from a project and this may also make a wo

Automated storage and retrieval systems, Automated Storage and Retrieval Sy...

Automated Storage and Retrieval Systems Automated  storage  and retrieval systems(SASRS) are system  for receiving  orders for  materials  from  anywhere  in  operations colle

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Define project evaluation review technique, Question 1: As a Business d...

Question 1: As a Business development Officer, how you will bring business to a CRO? Responsibilities and roles of Business development Officer in a CRO Method and Tec

Classical and neo-classical theory of of organisation, What are the differe...

What are the differences between classical theory and neo-classical theory of organisation? Difference between classical theory and neo-classical theory of organisation: The cl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd