Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Draw an activity-on-arrow network diagram for the project, Question: (a...

Question: (a) Back~to~Future International, a recently setup non-profit organization by the students of Fashion & Design Institute, has decided to organize a fashion show. The

Element of total quality management, In order to adopt and initiate TQM ...

In order to adopt and initiate TQM within any organization it is necessary to understand the key elements. These elements which form the essential core of the TQM phil

What are the limitations of performance appraisal, Problem: According t...

Problem: According to the PRB report, "Performance management is often confused with performance appraisal or the confidential reporting system presently in force in the servi

Steps of process planning procedure , Steps of Process Planning Procedure ...

Steps of Process Planning Procedure Step 1 Selection of Process: A process is necessary in order to shape form condition and join materials and components with the help of mac

Production tools, Improving the quality of manufactured parts and decre...

Improving the quality of manufactured parts and decreasing the production cycle time requires the use of high powered software programs integrated with computer controlle

How do i get my project organized, Q. How do I get my project organized? ...

Q. How do I get my project organized? Every project that involves surplus to one person requires a project team to get the work done. With no doubt building a motivated project

What is productivity, What is productivity? Productivity: Product...

What is productivity? Productivity: Productivity may be described as the ratio between input and output. Output implies the amount produced or the number of items produce

What do project managers do, Q.  What do project managers do? First of ...

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective

Information software, what is project management information software

what is project management information software

Explain about privatisation of public sector undertakings, Explain about th...

Explain about the privatisation of public sector undertakings. The privatisation of public sector undertakings : After independence India opted for mixed economy. The priv

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd