Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Backward integration, Backward Integration A strategy in which an orga...

Backward Integration A strategy in which an organization builds competitive benefits by controlling the provider of the raw materials needed to make its products.

Product characteristics and requirements, 1.  Main functions: The web based...

1.  Main functions: The web based site will be fully enabled for viewing via iPad and be fully accessible at the cafe seating only.  The menu will be fully automated to allow order

Describe the key characteristics of a good project, Question 1: a. How...

Question 1: a. How would you define a project? What are the different types of project that exist? (Please illustrate using a model with examples). b. Enumerate and descri

Explain about the process of managing risk, Explain about the process of ma...

Explain about the process of managing risk. A process of managing risk: 1. Risk committee establish to address risk issues categorised for example usual risk audits, to estimat

National competitive bidding (ncb) , Steps for National Competitive Bidding...

Steps for National Competitive Bidding (NCB)  Similar to ICB, we have two ways involved in NCB: one with pre-qualification, another without prequalification. Steps for NCB are

Project management, Project managers can become more successful when they d...

Project managers can become more successful when they develop their understanding of organizations. Any organization can be viewed as having four different frames: structural, huma

Explain constant power and constant impedance, Study of the Load impact on ...

Study of the Load impact on power flow with (constant power, constant impedance, constant current, induction motor) and use the PowerWorld simulator.

What are the major characteristics of a project, Question : (a) Organi...

Question : (a) Organizations and individuals have studied a number of projects that have both succeeded and failed and some common factors emerge. Can you give some reasons fo

Uses and benefits of risk breakdown structure, Uses and Benefits of RBS  ...

Uses and Benefits of RBS  The main uses and benefits of the RBS are outlined in this section.  Risk identification aid  Risk Breakdown Structure is used as a list that

Mbo process, MBO process MBO is the process of collaborative goal setti...

MBO process MBO is the process of collaborative goal setting between the manager and his or her subordinates. It assumes that goals are consistent or compatible from the highes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd