Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Communication strategy, Communication Strategy: Communication str...

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Demonstrate a critical approach to management theories, Your Integrated Man...

Your Integrated Management Project will be marked initially by a tutor. The marked project may then moderated by another tutor to ensure consistency between markers. A sample of th

Phases of value engineering process, P hases of value engineering process ...

P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona

Explain what deming meant by the following statements, Question: (a) Ex...

Question: (a) Explain what Deming meant by the following statements? What happens if you do not fulfill those principles? (i) Institute leadership. (ii) Drive out fear.

Incremental approach to testing by integration test, Explain the incrementa...

Explain the incremental approach to testing represented by the orderly integration test. Integration test: The integration test is looking for to determine whether the mo

Quantitative analysis., A highly sensitive device used to measure electrici...

A highly sensitive device used to measure electricity activity in the brain is required to have a variance in measurements not exceeding 0.0001 volts^2. if the variance exceeds thi

Need for safety, Need for safety 1. Cost Saving: Two type  of costs ...

Need for safety 1. Cost Saving: Two type  of costs  are incurred by the management  when an accident  occurs. There are the  direct  costs in the  form  of compensation paya

Equity valuation, a) Provide a detailed evaluation of an equity investment ...

a) Provide a detailed evaluation of an equity investment decision in the current economic climate. Your briefing should include: i)  A review of the 'top-down' analysis tha

Describe types of projects requirements according to wijnen, Describe all t...

Describe all types of projects requirements according to Wijnen. Preconditions: It forms the context in which the project should be executed. Illustrations include legisl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd