software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Quality movement, QUESTION 1: (a) Explain how TWO of the given gurus h...

QUESTION 1: (a) Explain how TWO of the given gurus have contributed to the Quality Movement, highlighting the major points of their philosophies: (i) Edward Deming (ii)

Objectives of a procurement system, Question 1: (a) Enumerate five obje...

Question 1: (a) Enumerate five objectives of public procurement systems contained in the UNCITRAL Model Law on Procurement of Goods and Construction. (b) Compare and c

What are the disadvantages of bottom-up decentralised, What are the disadva...

What are the disadvantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager

What is a project life cycle, Q. What is a project life cycle? If a pro...

Q. What is a project life cycle? If a project is well prearranged it will progress logically through several phases. There are four standard stages to a typical project. The fi

Internal external factors influence organisational culture, Internal and ex...

Internal and external factors influence the organisational culture Culture facilitates internal integration and harmony as well as external adaptation according to environmental

Relationship between project manager and project team, Project manager and ...

Project manager and project team The project board will ultimately choose whether changes are executed or not and it will then be the responsibility of the project manager to m

Why do projects always seem to cost more than expected, Q. Why do projects ...

Q. Why do projects always seem to cost more than expected? In general this seems to stem from three causes. The first may merely be an overly optimistic cost estimate. Sometime

What is cost benefit analysis, What is Cost Benefit Analysis? Cost Be...

What is Cost Benefit Analysis? Cost Benefit Analysis: This analysis is a mathematical technique for decision-making. This is a quantitative technique used to calculate th

PMP, critical analysis of the pmp

critical analysis of the pmp

Case Study, Develop a work breakdown structure. 3. Make a list of the speci...

Develop a work breakdown structure. 3. Make a list of the specific activities that need to be done between now and the wedding day. 4. For each activity, identify the person (Tony,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd