software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

Project value - measure for project management value, P roject value T...

P roject value The organisations add value to the business through the series of processes. Increasingly such processes are usually undertaken within the context of the projec

Research reports and design documents, Project management-related deliverab...

Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final pro

Give a theoretical overview of the management of change, According to the S...

According to the Society for Human Resource Management's (SHRM) 2007 Change Management Survey Report, the top two obstacles encountered during major organizational change are commu

What is production, What is Production? Production: Production is...

What is Production? Production: Production is any procedure or process developed to transform a set of input tools as men, capital, materials, information and energy with

What are the benefits of project management software, What are the benefits...

What are the benefits of project management software? Project management (PM) software benefits are as follows: a. Project scheduling b. Budgeting and controlling cost

Whole healing system and modality, 1)  Compare your chosen Whole Healing Sy...

1)  Compare your chosen Whole Healing System and Modality by considering: a)  When and by who were they 'invented'? b)  How have the therapies changed over time? c)  What

Understand strategy of organisation by project manager, Why is it significa...

Why is it significant for project managers to understand the strategy of the organisation which uses their services? This enables the project to be considered in the context of

Project risk profile owners, Project risk profile owners  Project risk ...

Project risk profile owners  Project risk profile owners must make sure that they deal with each and every risk of the project. The responsibilities of the project risk owners

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd