software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Assessing Infrastructure Project-Related Risks, The Three Gorges Dam is pot...

The Three Gorges Dam is potentially one of the largest, if not the largest infrastructure projects completed in the 21st century. Clearly, there were a number of key risks that the

Perform a status assessment of the project iteration, Perform a status asse...

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the it

Attractiveness of the industry in which ff currently operate, The Board of ...

The Board of FF Supermarket is examining the company's current market position. As part of the review, the Board has asked for an analysis of industry competition to be undertaken

Stakeholder management, 3. What are some ways to manage a stakeholder rela...

3. What are some ways to manage a stakeholder relationship closely? Give examples of how you might manage relationships differently based on the unique personalities of different

The Walsham Hotel, Compare and Contrast the KN346 investment and the "plain...

Compare and Contrast the KN346 investment and the "plain vanilla" alternative.

Initial project plan, o Does the project plan clearly identify a set of fun...

o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and

What are the distinguishing characteristics of a project, Question : (a...

Question : (a) What are the distinguishing characteristics of a project? (b) What are the four types of consequences of risk? (c) Explain what you understand by the term

How is economic order quantity depended on costs, How is Economic Order Qua...

How is Economic Order Quantity depended on costs? Economic Order Quantity depends on two costs as illustrated below: - Inventory procurement costs that consist of expenditur

Aspects to good project management, Q. Is that all there is to project mana...

Q. Is that all there is to project management? A. That is by no way all. There are several aspects to good project management that require attention. In summary these perhaps

Second elaboration iteration, Perform a status assessment of the second Ela...

Perform a status assessment of the second Elaboration iteration. DO NOT GENERALISE. Assess each activity separately against the outcomes specified for the activity. Generate a deta

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd