software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Design and implementation of the pms, Question: Performance appraisal (...

Question: Performance appraisal (PA) and management play an important role in the effective management of employees in every viable organisation. However, for many Human Resour

Significance of architecture-centric methods, Question: a) Why are GSD ...

Question: a) Why are GSD projects more difficult to manage than single site collocated projects? b) Which agile practices would be easier to adopt, and which would be challe

Develop and agree a process model for a project, Why is it significant that...

Why is it significant that the project team and the users develop and agree a process model for a project? Any project is a cooperative venture among the clients/users and the

Advantages of rules-planning function, Advantages of Rules In addition ...

Advantages of Rules In addition to the general societal advantage of rules referred to above, the organization and its employees can derive the following benefits from the inst

What are the limitations of performance appraisal, Problem: According t...

Problem: According to the PRB report, "Performance management is often confused with performance appraisal or the confidential reporting system presently in force in the servi

Earned value management is a systematic approach, Question: (a) Earned...

Question: (a) Earned Value Management is a systematic approach to the integration and measurement of cost, schedule, and technical accomplishments in a project. List the benef

Project management, Project management: a. Describe a project you are ...

Project management: a. Describe a project you are currently working on for school or work or your personal hobbies and interests that would benefit from Project Management con

Flow chart, how do I calculate forward pass and backward pass?

how do I calculate forward pass and backward pass?

Span of management-managerial function of organizing, Span of management ...

Span of management Span of management refers to the number of subordinates who directly report to one superior. If a manager has too many subordinates then his span is wide and

Explain the development phase in the project management, Explain about the ...

Explain about the development phase in the project management. Development phase During the development phase, everything that will be needed to implement the project is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd