software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Explain about the break even analysis, Explain about the Break Even Analysi...

Explain about the Break Even Analysis. Break Even Analysis: Break even Analysis means that at some point within the operations, total revenue equivalent to total cost. Break ev

Manufacturer''s promotional activity, Explain how a manufacturer's promotio...

Explain how a manufacturer's promotional activity might vary depending upon the sort of distribution channel that operates. Distribution includes getting the right products to

Objectives of materials management, Objectives  of Materials Management: ...

Objectives  of Materials Management: 1. Low  prices: Obtaining  the least possible  price  for purchased materials is the  most  obvious  purchasing  objectives and certai

Explain impact for the management of multinationals, Question : (a) Wha...

Question : (a) What are the factors that have propelled the spread of HRM discourse and practice to developing and less developed countries? (b) Discuss the Morgan's(1986)m

Plan, Plan A plan is a blueprint or framework used to describe how an o...

Plan A plan is a blueprint or framework used to describe how an organization expects to achieve its goals. Planning is the process of developing plans or determining how best t

Quality measurement procedure - tqm techniques, Quality Measurement Procedu...

Quality Measurement Procedure: Quality as a strategic issue implies (i) acceptance of the importance of customer requirements throughout the organization,  (ii) the identifica

Commercial project negociation, I want to make a report on this topic by to...

I want to make a report on this topic by tomorrow morniing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd