Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Entities and variables, There are three main entities in our model. There i...

There are three main entities in our model. There is Ambulance Patients entity which represents all patients coming to the hospital by ambulance cars. The second entity indicates t

Incremental approach to testing by integration test, Explain the incrementa...

Explain the incremental approach to testing represented by the orderly integration test. Integration test: The integration test is looking for to determine whether the mo

Disaster recovery preparation - training, Question 1: Unplanned catastr...

Question 1: Unplanned catastrophes are always waiting just around the corner to derail your project. You have been appointed risk manager to prepare a risk management plan, and

Project Planning Appraisal and Control, 2. Why Conflicts arise between two ...

2. Why Conflicts arise between two or more mutually exclusive projects? Analyse the situations where conflicts may arise and suggest how these conflicts can be resolved.

Concept of values to an organization, The Buddha had said that an individua...

The Buddha had said that an individual is free to think and decide on his own and at the same time he is responsible for his own actions. Organisations are about individuals; they

Traditional definitions of quality, T raditional definitions of Quality ...

T raditional definitions of Quality There are various definitions of quality. According to quality pioneer Joseph M. Juran quality has two meanings that are very important for

Linear Programming Problem, Maximize Z= 3x1 + 2X2 Subject to the constraint...

Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Outline at least three steps common to pert and cpm, QUESTION (a) Feasi...

QUESTION (a) Feasibility Study is a preliminary study undertaken before a real work of a project start what factors should the project manager take into consideration while con

LIne balancing, Q3. What do you understand by “line balancing”? What happen...

Q3. What do you understand by “line balancing”? What happens if balance doesn’t exist?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd