software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Identify a governmental and a not-for-profit program, One of the characteri...

One of the characteristics unique to governmental and not-for-profit organizations is the inability to eliminate unprofitable activities. Clearly, in the case of these activities,

How important are the stakeholders, Q. How important are the stakeholders? ...

Q. How important are the stakeholders? The most significant stakeholder of course is your client or customer. Conversely that perhaps in excess of one person that the sponsor a

Tangible and intangible while applied to costs and benefits, What do you me...

What do you mean by the terms tangible and intangible while applied to costs and benefits? Tangible costs or benefits are those for that a plausible quantitative value can be

Policy requirements, Policy requirements The following are the policy r...

Policy requirements The following are the policy requirements: A c countability for projects: For adequate definition and responsible implementation of projects the

Types of histograms, H i stograms are of five types. They are: B...

H i stograms are of five types. They are: B ell shaped: It can be applied for concepts such as average and standard deviation. D ouble peaked: It is used to com

Brand, contents for introduce a new brand.

contents for introduce a new brand.

Scope of materials management, Scope  of Materials  Management Material...

Scope  of Materials  Management Materials  management  embraces all  functions  concerning  planning  purchasing  production  control  stores  traffic and physical distribution

Checklist to compile a project scope statement, create a risk management pl...

create a risk management plan for all the formulated risks on payroll project

Macro environment, The influence an organisation will normally have over it...

The influence an organisation will normally have over its macro environment will be Limited or non existent

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd