Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

What level of project management do i need, Q. What level of project manage...

Q. What level of project management do I need? A. This is a complicated question to answer for the reason that it very much depends on the size duration and technical complex

Describe who should carry out an investigation, Question: (a) An emplo...

Question: (a) An employee in an organisation has suffered a major injury in an accident during working hours. Describe who should carry out an investigation into the accident

Policy requirements, Policy requirements The following are the policy r...

Policy requirements The following are the policy requirements: A c countability for projects: For adequate definition and responsible implementation of projects the

How does trevor young define project control, Question: The idea of Pro...

Question: The idea of Project Execution and Control is to develop the product or service that the project was commissioned to deliver, utilizing all the plans , schedules , pr

Why is necessary to plan an is project in detail before work, Give three re...

Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

Effects and four types of risks in engineering projects, Question Using...

Question Using a project drawn from your own experience, discuss the following- (a) What are the two primary stages of risk management of a project? (b) What are the four

What is culture of organisation where study and work done, Consider the org...

Consider the organisation which employs you or where you study. What is the culture of this organisation? Why does this have that exacting culture? What organisational culture woul

Steps to create run chart, The steps to create a run chart are: 1.   Id...

The steps to create a run chart are: 1.   Identify the process to be observed: Ensure that the process involves some kind of repeatable activity in which results remain consis

Project management methodologies, Can yu make an assignment of 2500 to 3000...

Can yu make an assignment of 2500 to 3000 words of essay?

A Grid Analysis (Weighted Scoring Model) to, I need a decision matrix- a Gr...

I need a decision matrix- a Grid Analysis (Weighted Scoring Model) to Help Make the North American Plant Location Decision for the RX 330 I need the acual model calculated based

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd