Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Risk categorisation , Risk Categorisation  Management of risk involves:...

Risk Categorisation  Management of risk involves:    Prevention: To deal with causes.    Recovery: To deal with effects.  There are three categories of project r

Agile software development, Agile software development is a group of softw...

Agile software development is a group of software development procedures based on iterative and incremental development, where requirements and solutions develop through collabora

Content of iso 9000, ISO 8402 deals with standardization of quality voca...

ISO 8402 deals with standardization of quality vocabulary. ISO 9000 is actually a series of guidelines for selection and use of the appropriate systems standards of ISO 90

What is the important role of Controlling in the management, What is the im...

What is the important role of Controlling in the management? Controlling: Controlling is described as which managerial function that seeks to make sure an absolute c

Scatter diagrams, S catter diagrams The possible relationships between...

S catter diagrams The possible relationships between two variables are identified using scatter diagrams. In order to understand data as a whole, it is very important to under

Operations and project management, Operations and project management: ...

Operations and project management: Operations and project management are very important functions in any organisation. Operations management is is concerned with the productio

How do i get my project organized, Q. How do I get my project organized? ...

Q. How do I get my project organized? Every project that involves surplus to one person requires a project team to get the work done. With no doubt building a motivated project

Design and implementation of the pms, Question: Performance appraisal (...

Question: Performance appraisal (PA) and management play an important role in the effective management of employees in every viable organisation. However, for many Human Resour

Define the guidelines for software development program, Define the Guidelin...

Define the Guidelines for Software Development Program In this part we have known some common parameters as checkpoints for the assessment of some software development project.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd