software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Elaborate those stages in a project life cycle, QUESTION (a) The projec...

QUESTION (a) The project organization structure clearly identifies the relationship between project team members through defining their duties, responsibilities and lines of au

Supplier quality, Scope of Activities for Supplier Quality In the curre...

Scope of Activities for Supplier Quality In the current day's scenario, certain organisations outsource the movement of  raw materials sources and distribution channels in orde

Why do projects need planning, Q. Why do projects need planning? A basi...

Q. Why do projects need planning? A basic of managing projects is first to plan and then to accomplish. Obviously good project management is lots more complex as we shall see s

Risk categorisation , Risk Categorisation  Management of risk involves:...

Risk Categorisation  Management of risk involves:    Prevention: To deal with causes.    Recovery: To deal with effects.  There are three categories of project r

Robotic painting system project, L Company, a manufacturer of family cars, ...

L Company, a manufacturer of family cars, has invested in a robotic painting system for its cars Ensuring the right quality of paintwork on each car is a critical success factor fo

Disaster recovery preparation - training, Question 1: Unplanned catastr...

Question 1: Unplanned catastrophes are always waiting just around the corner to derail your project. You have been appointed risk manager to prepare a risk management plan, and

Operations and project management, Operations and project management: ...

Operations and project management: Operations and project management are very important functions in any organisation. Operations management is is concerned with the productio

Define and illustrtae the term maintenance strategy, Problem: (a) Def...

Problem: (a) Define and illustrtae the term Maintenance Strategy? Support your answers with relevant examples. (b) Describe the steps that will be taken to improve the

National competitive bidding (ncb) , Steps for National Competitive Bidding...

Steps for National Competitive Bidding (NCB)  Similar to ICB, we have two ways involved in NCB: one with pre-qualification, another without prequalification. Steps for NCB are

Disadvantages of procedures-planning function, Disadvantages of Procedures ...

Disadvantages of Procedures 1) Procedures tend to inhibit rational and logical thinking. The assumptions in the basis of which a procedure was designed might not obtain in all ci

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd