Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Describe incremental approach to orderly acceptance testing, Describe the i...

Describe the incremental approach to orderly acceptance testing. Acceptance test: The users are invited to perform an acceptance test to check which what they have asked

Two primary stages of risk management of a project, Question Using a pr...

Question Using a project drawn from your own experience, discuss the following (a) What are the two primary stages of risk management of a project? (b) What are the four

What are the popular psychological tests, What are the popular psychologica...

What are the popular psychological tests? Several of the popular psychological tests are as given below: a. Intelligence Tests: Such are conducted for containing an idea o

Estimation Activities in Project Management , i want some on in expert in I...

i want some on in expert in IT project management and follow exactly and carefully the structure sheet.

Budget, Budget A budget is a financial preparation or planning and a re...

Budget A budget is a financial preparation or planning and a record of all planned expenses and revenues. It is a plan for borrowing, saving and spending. A budget is a sign

Goals of an fms, Goals of an FMS The goal of an FMS is to produce a m...

Goals of an FMS The goal of an FMS is to produce a moderate verity of products in moderate. Flexible quantities clearly an F M S is more flexible than conventional high volum

Software project, Scenario: You are a member of the Project Review team for...

Scenario: You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM)

Linear programming methods of line balancing, Linear Programming Methods of...

Linear Programming Methods of Line Balancing Assume that a job is broken down into elements tasks and the total duration of all such tasks is 28 minutes. The cycle time i, e,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd