Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Determine acceptance criteria for a project derived, From what product must...

From what product must the acceptance criteria for a project is derived and why? The acceptance criteria must be derived by the Requirements Specification that is where the use

Components of supply chain management, Components of Supply Chain Managemen...

Components of Supply Chain Management Today, it is the basic requirement amongst customers that businesses produce defect-free products to the customer faster and be more consi

Determine the analogy method of estimating, The analogy method of estimatin...

The analogy method of estimating is frequently used to produce broad-brush evaluates at the start of a project. Why this method is mainly suited to such application? Determinin

Process of diagnosing the system, Question 1: What are the steps involv...

Question 1: What are the steps involved in the process of diagnosing the system? Steps involved in the process of diagnosing the system. Question 2: What are the maj

Downward communication from the superior to the subordinate, How must be th...

How must be the downward communication from the superior to the subordinate? There formal communication in between subordinate and superior, here the superior sends directions

Explain the methodology of sequencing the activities, Question 1 For a...

Question 1 For an event manager, organizing an AGM would be a relatively 'dry' affair as the elements of entertainment, decoration and catering are missing in this event (some

H U D guidelines, For an initial secure order under HUD guidelines, are yo...

For an initial secure order under HUD guidelines, are you authorized to remove exterior debris automatically?

Change in scope of statement, Q. Brandi is working as a project manager on ...

Q. Brandi is working as a project manager on a software project. About halfway through development, her team concludes that they had not estimated enough time for some of the techn

Describe the contents of a project initiation document, Describe the conten...

Describe the contents of a project initiation document. Contents of a PID (project initiation document): • Terms of reference for example the concept of the report • Scop

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd