Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Addressing high nurse turnover at Bronson methodist hospital, identify purp...

identify purpose of case study , general information about hospital, identified problem and proposed solution

Combined layout, Combined Layout The application of the principle of p...

Combined Layout The application of the principle of product layout, process layout or fixed location layout in their strict meanings is difficult to come across. A combination

Explain about the term performance appraisal in organization, Explain about...

Explain about the term Performance Appraisal in organization. Performance Appraisal: This is a systematic and impartial assessment of an worker’s performance on the assign

Advantages of procedures-planning function, Advantages of Procedures 1) P...

Advantages of Procedures 1) Procedures enhance efficiency. The sequence of steps for any operation have been laid out in advance and one only needs to follow the analysis to proc

Formulation of production specification, Specification is an important qua...

Specification is an important quality document for the product because it is here that quality fo the product as a whole is defined in precise technical terms. Although the use

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

The three main types of estimating methodology, QUESTION (a) Accurate e...

QUESTION (a) Accurate estimation is crucial for effective planning and control and is associated with time, information, experience of estimator, techniques used and funding. D

Review of design, Before the preliminary design has progressed further i...

Before the preliminary design has progressed further it should be subjected to a critical review by all those who are connected with the product such as quality engineers

What is productivity, What is productivity? Productivity: Product...

What is productivity? Productivity: Productivity may be described as the ratio between input and output. Output implies the amount produced or the number of items produce

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd