software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Use of operational approach in development process, Q. Use of Operational a...

Q. Use of Operational approach in development process? It has been defined as the application of scientific methods, technology and tools to operation of system with optimum s

Pm, short note on partnering

short note on partnering

Project closure, Project Closure   Project closure is the last stage of ...

Project Closure   Project closure is the last stage of the Project Life Cycle. The beginning of the Project Closure Phase is analysed by the completion of all project objectives

Structure, Differences between wbs and product breakdown structure, Project...

Differences between wbs and product breakdown structure, Project Management

Tools and techniques of layout planning - line balancing, Tools and Techniq...

Tools and Techniques of layout planning - Line Balancing Line balancing is the phases of assembly line study that nearly equally divides the work to be done among the workers

Name an approach to systems implementation, Name an approach to systems imp...

Name an approach to systems implementation?  Matrix operation.

Production and purchasing management, A) Hierarchical planning in Operation...

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

What do you mean by gates and milestones, What do you mean by Gates and Mil...

What do you mean by Gates and Milestones? Gates and milestones: Milestones are a completion of main interim objectives for a project for example the key stages of a pro

Risk breakdown structure for a project , Risk Breakdown Structure for a Pro...

Risk Breakdown Structure for a Project  Risk Breakdown Structure (RBS) is a hierarchical list of risks, which standardises the department's personnel resources that help in pla

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd