Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Stakeholde, Differences between Primary and Secondary Stakeholders?

Differences between Primary and Secondary Stakeholders?

Project management cycle, It is essential that you study the list below to ...

It is essential that you study the list below to ensure that you understand the terminology used in assignment and examination questions. The successful outcome of your assessment

Explain about privatisation of public sector undertakings, Explain about th...

Explain about the privatisation of public sector undertakings. The privatisation of public sector undertakings : After independence India opted for mixed economy. The priv

Explain about the changing information technology, Explain about the changi...

Explain about the changing information technology. Changing Information Technology: Challenges and Prospects There is no suspicion that information technology has create

Process for improvement in an organization, Question: (a) The underlyin...

Question: (a) The underlying reason for benchmarking is to learn from best practices and implement them in your organization in an attempt to improve your business processes

Computerized relative allocation of facilities technique, Computerized Rela...

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

Show idea screening in process of development, Q. Show Idea Screening in Pr...

Q. Show Idea Screening in Process of development? Idea screening involves the acceptance of formulation of the idea by doing cause and effect analysis. This stage usually ident

What does mpmm contain, This product not only having more than 1000 pages o...

This product not only having more than 1000 pages of content explaining how projects should be undertaken successfully, but it also includes: 51 detailed project management temp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd