Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain quantitative risk so important in risk mitigation, Why is quantitat...

Why is quantitative risk so important in risk mitigation? Explain how you have seen this in action in life or in your organization.

Explain what are the disadvantages of nucor''s choice, Instead of a separat...

Instead of a separate performance appraisal system, Nucor judges performance based on bottom line of quality, productivity, and profitability. What are the disadvantages of Nucor's

SEQUENCING PROBLEM, HOW TO SOLVE SEQUENCING PROBLEM FOR N-JOB AND M-MACHINE...

HOW TO SOLVE SEQUENCING PROBLEM FOR N-JOB AND M-MACHINES

Explain characteristic shared by frame relay and atm, which of the followin...

which of the following is a characteristic shared by frame relay and ATM? a. the use of virtual circuits b. the use of fixed-sized packets known as cells c. the use of ded

Explain the purpose of realistic and contrived tests, Explain the purpose o...

Explain the purpose of realistic and contrived tests as part of the installation of a new system. Both of these tests contribute to a critical activity prior to the changeover

Linear programming, Premier coatings Zambia ‘PCZ’ produce both interior and...

Premier coatings Zambia ‘PCZ’ produce both interior and exterior paints from two raw materials, Ml and M2. A market survey indicates that the daily demand for interior paint cannot

Explain what is the maximum inventory level, A company that makes kitchen f...

A company that makes kitchen faucets has found that demand for its model faucet is fairly constant at the rate of 100,000 units per year. Each model of faucet is made using the sam

Characteristics of batch production, Characteristics of Batch Production ...

Characteristics of Batch Production Short Runs: Batch production is characterized by short production runs and frequent changes in set ups. Investment : Needs high in

Find how much does the airport need to set aside now to pay, Orlando Intern...

Orlando International Airport plans to extend passenger capacity of its existing terminal to accommodate its forecasted growth. A new terminal would be needed once the state's busi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd