Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain develop an mrp planning schedule showing gross, Assume that Z is ma...

Assume that Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of ea

Production & Purchasing Managements, Hierarchical planning in operations/Pr...

Hierarchical planning in operations/Production managemnt and the types of time frames in each hierarchy?

Explain affirmative action, When it is claimed that people that ‘pay' for w...

When it is claimed that people that ‘pay' for wrongs are unfairly burdened and should not bear the responsibility for the acts of others, they are opposing to Answer reverse discri

Describe what specific planning challenges, Someone Help Please! Select one...

Someone Help Please! Select one of the following companies to study in depth over the next 4 weeks. BP Oil Kimberly-Clark Kroger Nucor Walgreens Wells Fargo Kaiser Permanente Ascen

Explain objective of value stream mapping is to improve data, 1) Bill of ma...

1) Bill of material errors can cause serious problems for MRP system calculations of dependant demands 2) No matter what forecasting technique is used, the probability of a prod

Define state licensure requirements that an organization use, Discuss state...

Discuss state licensure requirements that an organization must comply with in order to become a Medicare Advantage Plan, any exceptions to the State licensure requirement, and any

Explain finite backward scheduling, A process capacity methodology that is ...

A process capacity methodology that is used to show how well parts being produced fit into a range specified by design limits is which of the following? a. Finite backward sche

North west corner rule, advantages and disadvantages of north west corner r...

advantages and disadvantages of north west corner rule

What is basic naive method, 1. The monthly sales for Telco Batteries, Inc.,...

1. The monthly sales for Telco Batteries, Inc., were as follows: Month Sales Jan 20 Feb 21 Mar 15 Apr 14 May 13 Jun 16 Jul 17 Aug 18 Sep 20 Oct 20

Explain assess how southwest airlines culture is different, "Southwest Airl...

"Southwest Airlines" Please respond to the following: Assess how Southwest Airlines culture is different from other airline competitors and the resulting impact on business perf

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd