Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Describe how sharpen the saw is applied, Explain how "sharpen the saw" is a...

Explain how "sharpen the saw" is applied in the Toyota Production System Grading rubric (Highest quality answers will consider ALL of the following) Describe "sharpen the saw

Class work, define the following key terms in product layout: a) Product in...

define the following key terms in product layout: a) Product interval time b) Product duration (throughput time) c) Assembly line balancing

Define why is project management popular tool in recent year, Why is projec...

Why is project management popular tool in recent years?

Activity sampling - process design, Activity Sampling - Process Design ...

Activity Sampling - Process Design This is a method of finding the percentage occurrence of a certain activity by statistical sampling and random observation. It is used when

Explain what is the utilization of pharma, Pharma Blitz develops and market...

Pharma Blitz develops and markets new technological products to be used in health care. The development of a new product operates as follows. When a new technology meets the requis

Explain the marginal productivity of additional firefighters, According to ...

According to the text there appear to be very limited opportunities for input substitution in the production of fire protection services. Which of the following is the most plausib

Iventory control and management, Nuvyug Industries Ltd. Has an annual requi...

Nuvyug Industries Ltd. Has an annual requirement of 5,000 pieces of brake cylinders for its popular brand of golf carts. Each brake cylinder has a carrying cost of ` 25 per unit pe

Line balancing, what do you understand by line balancing?what happens if ba...

what do you understand by line balancing?what happens if balance does not exist?

Calculate the desired cycle time, A company is setting up an assembly line ...

A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table identifies the work elements, times and immediate predecessors:  (a)  Wh

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd