Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

PROJECT MANAGEMENT CPM/PERT CHAT, prepare CPM/PERT chat and determine the s...

prepare CPM/PERT chat and determine the shortest time this project can be completed (using crash time )

Draw a schematic layout, The flow of materials through eight departments. E...

The flow of materials through eight departments. Even though the table shows flows into and out of the different departments, assume that the direction of flow is not important. In

How minimize the work-in-process inventory, The production manager must det...

The production manager must determine the processing sequence for 7 jobs through the grinding and debarring departments. The same sequence will be followed in both departments. The

Explain sow contains words such as nearly or approximately, If the customer...

If the customers SOW contains words such as nearly or approximately, then: Answer The project manager uses his discretion in determining the meaning The sponsor uses his d

Explain a serial entrepreneur who has previously started, You are an invest...

You are an investor in small businesses, and you have three business plans on your desk. Choose one of the potential business owners listed. Explain why you think that would be the

Explain what is the theoretical number of workstations, Tasks: A - 20 sec -...

Tasks: A - 20 sec - no precedence B - 7 sec - preceded by A C - 20 sec - preceded by B D - 22 sec - preceded by B E - 15 sec - preceded by C F - 10 sec - preceded by D G - 16 sec -

Explain staff time is saved in the form of reduced staff, As throughput imp...

As throughput improves, staff time is saved in the form of reduced staff worked hours per unit of service

Explain saving lives with social media, Compare and contrast the Haiti SM d...

Compare and contrast the Haiti SM discussion with the "Saving Lives with Social Media" case. Create a table that compares and contrasts elements from each. Is an emergent strategy

How is a standard time determined by time study, 1. How is a standard time ...

1. How is a standard time determined by time study?  Answer: The job is broken into well-defined short elements, which are then repeatedly timed by stopwatch, the worker's rate

Find what is the stock worth today, Investor G. Loeb owns a 5-year, $1000 b...

Investor G. Loeb owns a 5-year, $1000 bond with a 5% coupon. If the yield to maturity on similar bonds is currently 10%, what is Mr. Loeb's bond worth today? A security analyst

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd