Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain one aspect of minimizing litigation, Dedication of resources within...

Dedication of resources within an organization is Answer an indication of stockholder involvement. An unification of global resources under the parent company. One aspect of minimi

Upper bound, Customers arrive at a fast food restaurant with one server at ...

Customers arrive at a fast food restaurant with one server at a mean rate of 30 per hour. The server has just resigned, and the two candidates for the replacement are X (fast but

State the perpetual inventory control systems, State the Perpetual inventor...

State the Perpetual inventory control systems Continuous (Perpetual) Inventory Control Systems: Stock levels are continually monitored and reviewed within ‘real-time’ and

Approaches to determining operations strategy, Approaches to Determining Op...

Approaches to Determining Operations Strategy This describes aspects of operations systems and performance measurement, including trade-offs between performance criteria. We

Explain what order should these jobs be done, A machine shop has two machin...

A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three

Define the operations strategy, What is operations strategy?  Answer: Op...

What is operations strategy?  Answer: Operations strategy is the plan and actions taken at operational level to support and implement the business strategy. An operations strate

Integrated solutions in product design, Integrated solutions in product des...

Integrated solutions in product design and control of machinery are based on    CAD and CAM technologies.

Problems, the rate of use of a particular raw materials from stores is 20 u...

the rate of use of a particular raw materials from stores is 20 units per year. the cost of placing and recieving an order is Rs. 40. the cost of each unit is rs. 100 . the cost of

Expected cost of sell the nursing home, Beverly Enterprises owns a nursing ...

Beverly Enterprises owns a nursing home that is currently earning $2.0 million in cash flow on an annual basis, but this amount is expected to drop in the future. The nursing home

Explain annual holding and order costs, Item Cost - $7.00 Order Cost - $283...

Item Cost - $7.00 Order Cost - $283.00 Annual Hold - 32% of item cost Annual Demand - 22,100 Average Demand - 442 per week Standard deviation of weekly demand 20 per week lead time

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd