Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Suitability of continuous or flow production, Suitability of continuous or ...

Suitability of continuous or flow Production In order that flow methods can operations satisfactorily a number of requirements must be met: 1.There Must be Substantially cons

Suppose the number of requests for week, An electrical contractor's records...

An electrical contractor's records during the last 5 weeks indicate the number of actual job requests. Predict the number of requests for week 6 using each of the below methods:

Describe possible ways that a company could benefit, Discuss possible ways ...

Discuss possible ways that a company could benefit from making customers more aware of environmental laws. Provide specific examples to support your rationale. Based on what you

Explain what is the minimum number of workstations, An assembly line with a...

An assembly line with a number of tasks is to be balanced. The sum of the task times is 62 minutes. The line will operate for 6 hours per day. What is the minimum number of worksta

Explain one example from your professional experience, The process of outso...

The process of outsourcing the creation of a product or a service is a controversial, yet critical strategic decision for many employers. Describe one example from your professiona

How to determine the sample standard deviation, Determine the sample standa...

Determine the sample standard deviation(s) for the following data: 7, 9, 2, 0, 1, and 5. s = 2.805 s = 3.266 s = 2.927 s = 3.578

Explain what key mistake is christine moreno making, Case Study 5-2: The In...

Case Study 5-2: The Interfering Administrative Assistant Decision-Making Scenario 1. Relying on the concepts presented in chapters 10 and 11, identify the theories and concepts of

Explain principles for determining product mix, The senior management at Ca...

The senior management at Canine Kernels Company CKC is concerned with the existing capacity limitations so they want to accept the mix of orders that maximizes the company's profit

Location strategy, Location Strategy It is difficult  to set  down ru...

Location Strategy It is difficult  to set  down rules whereby the problem  of facilities  location  can be  programmed but  there  are a number of factors which  should be  c

Process Model - Serivces, Apply a proces smodel to a services industry proc...

Apply a proces smodel to a services industry process that experiences problems with either internal or external customers. Discuss all elements

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd