Simulation and optimization software, Software Engineering

Assignment Help:

A one-car taxi company receives an average of 18 calls per day. The receptionist takes down details of the requested journey and relays them to the driver by radio. Each passenger's journey takes 25 minutes on average. The working day is 12 hours long.

(i) What constitutes the queue in this particular situation?

(ii) How long, on average, will a client have to wait between placing a pickup call and the arrival of the taxi?

(iii) During this waiting time, how many other clients on average will be picked up by the taxi? (Think about the number of people already waiting in queue when a customer arrives.)

(iv) List all the necessary assumptions for your calculations in (ii) and (iii). For each assumption, explain briefly whether you think they may or may not be realistic in this particular example.

(v) What is the probability that the time between two successive calls will exceed one hour?

(vi) What would your answer to (ii) be if the mean of the service time remains the same but the standard deviation is 15 minutes? What type of queuing system is this?

(vii) Based on observation, the more taxis a company operates, the more calls it receives. If the company operated a second car, what rate of calls would result in the same average waiting time as with one car? Express your answer in terms of the average interval between calls.

(viii) The annual costs of operating the company are as follows:

Office and receptionist (for either 1 or 2 cars) £30,000

Fixed costs per car (depreciation, tax etc.) £5,000

Drivers' wages £20,000

The variable costs per car (petrol etc.) are £18/day, when operating full-time.

For the one-car case described in (i)-(iv), and for the two-car case in (vii), calculate the average charge per client necessary to break even. Assume 300 working days per year.


Related Discussions:- Simulation and optimization software

Name certain common tools which are used for load testing, Name certain com...

Name certain common tools which are used for load testing. - Rational Performance Tester by IBM Rational - Open STA an Open Source tool - LoadRunner by HP - Silk Perfo

Data modeling and normalization, The task in this project is to design a no...

The task in this project is to design a normalized database that could be used to collect and store information for a video rental outlet. The database should be structured to s

Text retrieval packages - softare packages, Text Retrieval Packages: T...

Text Retrieval Packages: Text retrieval comprises storage and subsequent retrieval of rat girds, essentially textual rather than numerical, tabular or graphical. Although, eac

Modular software development, After studying the module you should understa...

After studying the module you should understand the principles and techniques associated with modular software development. After studying the module you should understand the c

Find the degree of capability of software reliability model, Q. Define capa...

Q. Define capability. What are the quantities that determine the degree of capability of a software reliability model? Ans: Capability demotes to the ability of the model to

Software project planning necessitate what activities, Q. Software project ...

Q. Software project planning necessitate what activities? What are the difficulties encountered in measuring the Software Costs? Ans. Software project planning necessitate th

Describe incremental model, Q. Describe incremental model? Define core prod...

Q. Describe incremental model? Define core product and detailed plan. Ans. The incremental model is proposed by D.L PARNAS. It is basically implemented by combining elements

State the meaning of data dictionary, What is meant by Data dictionary? ...

What is meant by Data dictionary? The Data dictionary is an organized listing of all data constituents that are related to the system, with precise, accurate definitions so tha

What are the three activities of risk assessment, What are the three activi...

What are the three activities of risk assessment? The three activities are identifying, examining and giving priorities . Risks can be identified by a check list or looking at

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd