Significance of tailwater level in culverts, Civil Engineering

Assignment Help:

Significance of tailwater level in culverts

Headwater level and tailwater level of culverts are significant parameters in hydraulic design. Headwater level can't be set too large, or else flooding upstream may take place leading to the loss of life and properties. Conversely tailwater level of culverts has to comply with the following requirements: 

(i)  For low tailwater levels at the outlet of culverts, small depths of flow can cause vital erosion of downstream channels.

(ii) For high tailwater levels, it can cause the culvert upstream to be flowing full or even under submerged condition. The headwater level is increased in order to flow through culvert and this in turn increases flooding risk related with high headwater level.

231_Significance of tailwater level in culverts.png

Fig: Tailwater level in culvert


Related Discussions:- Significance of tailwater level in culverts

Calculate annual interest rate which is compounded monthly, You wish to buy...

You wish to buy a house and you can afford to make a down payment of $50,000. Your monthly mortgage payment cannot exceed $2,000. If 30-year loans are available at 7.5% annual inte

Support reaction, different types of support force & effect of hinge suppor...

different types of support force & effect of hinge support

Surveying, working from whole to part

working from whole to part

Functions of cap block drive cap and pile cushion, Question What are ma...

Question What are main functions of cap block drive cap and pile cushion in driven piles? Answer Cap block is fit amid hammer end and drive cap to manage hammer bl

Show ph value of water, Q. PH Value of Water? It is a symbol for hydrog...

Q. PH Value of Water? It is a symbol for hydrogen ion concentration and indicates acidity or alkalinity. When P H Value more than 7 water is alkaline and less than 7 water is a

Surveying, what are tie lines? explain in detail

what are tie lines? explain in detail

Traffic surveys, Traffic Surveys: The following traffic surveys are n...

Traffic Surveys: The following traffic surveys are needed for preparing a good road project: Classified Volume Counts This survey is normally carried out for 7 days,

What is partial prestressing, What is Partial Prestressing It is a form...

What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd