Q. Show the Settlement due to Excavation?

If  an excavation is made in a sandy soil,  the structure founded near the excavation will be affected and it will cause extra settlement. The settlement due to excavation of the cut will not extend beyond a distance equal to the depth of cut. For example,  if  the depth of cut is 5m, then the building at a distance of 5 m from the excavation  only will effect. This can be minimised by adequately providing the bracings.

When any cut is made in soft clay stratum,  the structure loaded at the sides of  the cut acts like a surcharge. Therefore  the clay near the bottom of the cut yields laterally towards the excavation under this surcharge. Hence, the ground surface above  the yielding clay starts settling.


Related Discussions:- Show the settlement due to excavation

What is sedimentation tank, Q. What is Sedimentation tank ? This is a p...

Q. What is Sedimentation tank ? This is a process in which the water is passed through bases or tanks in which the velocity of water is so reduced or water is given a period of

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

Necessity of air valves in pressurized pipelines, Q. Necessity of air valve...

Q. Necessity of air valves in pressurized pipelines? Air valves are broadly categorized into two major types: single air valves and double air valves. Single air valve comprise

Rectangular tie, how to perform a rectangular tie using optical square?

how to perform a rectangular tie using optical square?

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Explain the primary treatment for wastewater, Explain the Primary Treatment...

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed

Functions and desirable characteristics of pavements, Functions and Desirab...

Functions and Desirable Characteristics of Pavements Function of Pavement A pavement is that part of a road on which vehicles travel. The pavement has the following f

Explain the erosion and sedimentation, Explain the Erosion and Sedimentatio...

Explain the Erosion and Sedimentation Erosion: Removal of soil or other channel material caused by the rapid movement of water over the channel surface. The removed material

Compute the skin friction resistance, A 30 cm diameter pile penetrates a de...

A 30 cm diameter pile penetrates a deposit of soft clay 9 m deep and rests on sand. Compute the skin friction resistance. The clay has unit cohesion of 0.6 kg/cm 2 . Suppose

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd