Show the coating application, Mechanical Engineering

Assignment Help:

Q. Show the Coating Application?

Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application temperature recommended by the manufacturer, but not to exceed 525°F (275°C). Any pipe exceeding 525°F (275°C? shall become the property of the Applicator, and Applicator shall reimburse the OWNER for its total value.

Pipe shall be coated as soon as possible, within a maximum of 4 h of surface preparation. Oxidation of the pipe surface prior to coating, in the form of "blueing" or other apparent formation is not acceptable. If such oxidation occurs, the pipe shall be cooled to the ambient temperature and recleaned at no expense to OWNER.

The powdered epoxy shall be applied to the pipe surface by the electrostatic spray method at a sufficient rate to provide a uniform cured film thickness. Unless otherwise directed by the purchase order the applied film shall be a nominal 20 mil (0.51 mm) average thickness with 18 mil (0.46 mm) minimum thickness and a maximum thickness of 24 mil (0.61 mm). Pipe so rejected by the Company shall be stripped and recoated at no extra cost to OWNER. The coating shall be applied over the full length of pipe to within a maximum of 6" (152 mm) and a minimum of 2" (51 mm) from the ends of the pipe.

In the event that the specified coating thickness is inadequate to obtain less than the maximum allowable holidays per joint of pipe, the Applicator and OWNER shall evaluate the cause for the excessive holidays and determine if the thickness as specified should be altered.


Related Discussions:- Show the coating application

Cad, c programms fpr cycloidal motion

c programms fpr cycloidal motion

Couple, a couple can be balanced by a force equal to its magnitude?

a couple can be balanced by a force equal to its magnitude?

Explain about unit pipe racks, Q. Explain about Unit pipe racks? Unit p...

Q. Explain about Unit pipe racks? Unit pipe racks are the main arteries carrying the pipes and cables into the units, and as such should be centrally located. They are usually

Design of the plc ladder and profibus - asi network, 1 Prepare an updated s...

1 Prepare an updated sketch of the electro-hydraulic system shown in Figure showing the actuators in their start position appropriate to your allocated actuator sequence. 2 By u

Batch furnaces, Batch Furnaces: An insulated, the heating system, cha...

Batch Furnaces: An insulated, the heating system, chamber for placing the job, and a door or various doors for placing the job in place are the necessity of these furnaces. T

Calculate the flow rate and pressure drop , (a) Oil, with density ρ= 900 kg...

(a) Oil, with density ρ= 900 kg/m 3 , and kinematic viscosity υ=0.00001m 2 /s, flows at the rate of 0.2m 3 /s through 500m of a cast iron pipe of diameter d=200mm. Using this infor

Cover left crank case and check shifter drum, Open cover left crank case an...

Open cover left crank case and check shifter drum bolt and washer: Check shifter drum bolt torque and washer direction and avail ability.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd