Show the coating application, Mechanical Engineering

Assignment Help:

Q. Show the Coating Application?

Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application temperature recommended by the manufacturer, but not to exceed 525°F (275°C). Any pipe exceeding 525°F (275°C? shall become the property of the Applicator, and Applicator shall reimburse the OWNER for its total value.

Pipe shall be coated as soon as possible, within a maximum of 4 h of surface preparation. Oxidation of the pipe surface prior to coating, in the form of "blueing" or other apparent formation is not acceptable. If such oxidation occurs, the pipe shall be cooled to the ambient temperature and recleaned at no expense to OWNER.

The powdered epoxy shall be applied to the pipe surface by the electrostatic spray method at a sufficient rate to provide a uniform cured film thickness. Unless otherwise directed by the purchase order the applied film shall be a nominal 20 mil (0.51 mm) average thickness with 18 mil (0.46 mm) minimum thickness and a maximum thickness of 24 mil (0.61 mm). Pipe so rejected by the Company shall be stripped and recoated at no extra cost to OWNER. The coating shall be applied over the full length of pipe to within a maximum of 6" (152 mm) and a minimum of 2" (51 mm) from the ends of the pipe.

In the event that the specified coating thickness is inadequate to obtain less than the maximum allowable holidays per joint of pipe, the Applicator and OWNER shall evaluate the cause for the excessive holidays and determine if the thickness as specified should be altered.


Related Discussions:- Show the coating application

Evaluate mechanical work - thermodynamics, Evaluate mechanical work in diff...

Evaluate mechanical work in different steady flow process: Work done by steady flow process   and work done in non flow process,   1. Constant Volume Process; W 1-2 = V

Manufacturing systems and automation, This formative assignment seeks to de...

This formative assignment seeks to develop and assess skills associated with basic modern ICT tools and competence in the techniques of Rough-Cut Capacity Planning and F inan

Determine the angle of twist - solid steel shaft, Determine the angle of tw...

Determine the angle of twist - solid steel shaft: A solid steel shaft 6 m long is fixed at each of the end. A torque of 3 kN-m is applied to the shaft at a section 2 m from on

Calculate the length of developed blank, Calculate the Length of Developed ...

Calculate the Length of Developed Blank Part shown in Figure is to be produced from flat sheet by bending operation. Calculate the length of the developed blank. Assume k = 0.

Zenner diode fundamentals of electricity , Zenner Diode: Zenner diode is ...

Zenner Diode: Zenner diode is generally used as a voltage regulator. When voltage falls below the predetermined value, zenner diode functions in the same way as an ordinary diode

Eng chemistry, write notes on internal treatement of water

write notes on internal treatement of water

Define the types of clamping device, Define the Types of Clamping Device ...

Define the Types of Clamping Device Clamping screw. Hook bolt clamp. Lever clamp.   a) Bridge clamp. b) Heel clamp. c) Swinging strap clamp. d) Hi

Computational mechanics in design, Figure shows an impression of one of man...

Figure shows an impression of one of many lifting arrangements produced and used at a steel fabrication workshop. It was manufactured to lift a maximum of 50 kg and due to a produc

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd