Show the coating application, Mechanical Engineering

Assignment Help:

Q. Show the Coating Application?

Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application temperature recommended by the manufacturer, but not to exceed 525°F (275°C). Any pipe exceeding 525°F (275°C? shall become the property of the Applicator, and Applicator shall reimburse the OWNER for its total value.

Pipe shall be coated as soon as possible, within a maximum of 4 h of surface preparation. Oxidation of the pipe surface prior to coating, in the form of "blueing" or other apparent formation is not acceptable. If such oxidation occurs, the pipe shall be cooled to the ambient temperature and recleaned at no expense to OWNER.

The powdered epoxy shall be applied to the pipe surface by the electrostatic spray method at a sufficient rate to provide a uniform cured film thickness. Unless otherwise directed by the purchase order the applied film shall be a nominal 20 mil (0.51 mm) average thickness with 18 mil (0.46 mm) minimum thickness and a maximum thickness of 24 mil (0.61 mm). Pipe so rejected by the Company shall be stripped and recoated at no extra cost to OWNER. The coating shall be applied over the full length of pipe to within a maximum of 6" (152 mm) and a minimum of 2" (51 mm) from the ends of the pipe.

In the event that the specified coating thickness is inadequate to obtain less than the maximum allowable holidays per joint of pipe, the Applicator and OWNER shall evaluate the cause for the excessive holidays and determine if the thickness as specified should be altered.


Related Discussions:- Show the coating application

Assignment, Which chromium plating is more eco-friendly - trivalent or Hexa...

Which chromium plating is more eco-friendly - trivalent or Hexavalent? Justify your answer in the light of environmental issues caused.

Compton effect, Explain compton effect snd its significance

Explain compton effect snd its significance

Types of culverts - causeway and bridges, Types of Culverts: Culverts ...

Types of Culverts: Culverts are constructed with various materials and to different designs. The popular forms are : (a) Temporary stone scuppers (b) Stone slab culverts

Process to establish standard time for completion of a job, a) What is meth...

a) What is method study. Define various stages of method study. b) What are main techniques used to study path of movement in method study. a) Discuss the process to establis

Explain the evaluation phase of auger shaft, Explain the Evaluation Phase o...

Explain the Evaluation Phase of auger shaft Evaluation Phase of auger shaft Steps: 1. To judge the ideas generated in the creation phase for ability to meet the required

Process of alloy materials sampling, Q. Process of Alloy Materials Sampling...

Q. Process of Alloy Materials Sampling? The following alloy-materials require a minimum of 10% per lot representative PMI sampling. If any incorrect material is found in repres

Determine the deflection at free end, Determine the deflection at free end:...

Determine the deflection at free end: For the beam illustrated in Figure, determine the deflection at free end and the maximum deflection. Figure Solution R

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd