Show the coating application, Mechanical Engineering

Assignment Help:

Q. Show the Coating Application?

Immediately following surface preparation, the cleaned pipe shall be uniformly preheated by a non-contaminating method to the application temperature recommended by the manufacturer, but not to exceed 525°F (275°C). Any pipe exceeding 525°F (275°C? shall become the property of the Applicator, and Applicator shall reimburse the OWNER for its total value.

Pipe shall be coated as soon as possible, within a maximum of 4 h of surface preparation. Oxidation of the pipe surface prior to coating, in the form of "blueing" or other apparent formation is not acceptable. If such oxidation occurs, the pipe shall be cooled to the ambient temperature and recleaned at no expense to OWNER.

The powdered epoxy shall be applied to the pipe surface by the electrostatic spray method at a sufficient rate to provide a uniform cured film thickness. Unless otherwise directed by the purchase order the applied film shall be a nominal 20 mil (0.51 mm) average thickness with 18 mil (0.46 mm) minimum thickness and a maximum thickness of 24 mil (0.61 mm). Pipe so rejected by the Company shall be stripped and recoated at no extra cost to OWNER. The coating shall be applied over the full length of pipe to within a maximum of 6" (152 mm) and a minimum of 2" (51 mm) from the ends of the pipe.

In the event that the specified coating thickness is inadequate to obtain less than the maximum allowable holidays per joint of pipe, the Applicator and OWNER shall evaluate the cause for the excessive holidays and determine if the thickness as specified should be altered.


Related Discussions:- Show the coating application

What is electrode coatings and how it works, Q. What is electrode coatings?...

Q. What is electrode coatings? • Slag Forming Ingredients. Asbestos, mica, silica, fluorspar, titanium dioxide, iron oxide, magnesium carbonate, calcium carbonate and aluminum

Calculate the length of developed blank, Calculate the Length of Developed ...

Calculate the Length of Developed Blank Part shown in Figure is to be produced from flat sheet by bending operation. Calculate the length of the developed blank. Assume k = 0.

Heat exchangers - air-conditioning guidelines, Q. Heat Exchangers - air-con...

Q. Heat Exchangers - air-conditioning guidelines? Location, size and capacity clearly indicated. Control valves indicated. Space for tube removal, keep space clear of pipes, va

Boiler, Working, specification construction of Lancashire boiler

Working, specification construction of Lancashire boiler

Determine the change in diameter, Determine the change in diameter: A ...

Determine the change in diameter: A thin spherical shell of 1.8 m diameter is 10 mm thick. This is filled with a liquid so that the internal pressure is 1 N/mm 2 . Determine t

Design the keys - shear keys, Design the keys - Shear Keys: A solid ci...

Design the keys - Shear Keys: A solid circular shaft is to transmit 200 kN at 200 rpm. If the maximum shear stress is not to exceed 80 n/mm 2 design the shaft. Design the key

Quality control specialist, At site locations, the WorleyParsons QC Special...

At site locations, the WorleyParsons QC Specialist (QCS) is responsible to verify that the requirements for PMI as specified in the purchase order/subcontract documents are impleme

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd