Show the audit work of the given capital project, Auditing

Assignment Help:

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.


Related Discussions:- Show the audit work of the given capital project

Audit evidence, State four factors considered determining sufficiency of a...

State four factors considered determining sufficiency of audit evidence

Audit evidence, the reliabity of audit evidence defers with source is that ...

the reliabity of audit evidence defers with source is that true

Non-adjusting events - audit process, Non-Adjusting Events - Audit Process ...

Non-Adjusting Events - Audit Process Non-adjusting events are those that are indicative of conditions such arose than the balance sheet date as a decline in the market price o

Transaction Class Narratives, Prepare a narrative describing the transactio...

Prepare a narrative describing the transaction cycle process for debt in a municipality.

What is an audit and why there is need for an audit, Question: (a) What...

Question: (a) What is an audit? Why there is need for an audit? (b) Explain the steps the auditor must take before deciding whether to accept the nomination as auditor. (

Examination of Deeds, Examination of Deeds Make Sure that the mortg...

Examination of Deeds Make Sure that the mortgage is in the name shown in the advance records; That there is a document of title to the property within mortgage and that

Valuation and income - verification procedures, Valuation and Income - Veri...

Valuation and Income - Verification Procedures Valuation Valuation of listed securities is easily conformed along with suitable financial publications. Directors' valua

Verification work - audit process, Verification Work - Audit Process A...

Verification Work - Audit Process At the same time the audit process will need verification work as an example: examination of costing records, allocation and verification of

Materiality, how to calculate materiality given the acoountin period inform...

how to calculate materiality given the acoountin period information

Audit procedures, audit procedure for shares or common stock

audit procedure for shares or common stock

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd