Show the audit work of the given capital project, Auditing

Assignment Help:

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.


Related Discussions:- Show the audit work of the given capital project

Audit, Why is studying Auditing different from studying other accounting to...

Why is studying Auditing different from studying other accounting topics?

Normal audit risk, Normal audit risk Indications that an audit is a normal...

Normal audit risk Indications that an audit is a normal risk audit are: (1) The client having management and staff who are competent and have integrity; (2) Where the client h

Types of audits, Types of audits As far we have tended to think in sta...

Types of audits As far we have tended to think in state of the audit of limited companies, and certainly, the emphasis during this text will be on that companies incorporated

Factors affecting statistical technique, Factors Affecting Statistical Tech...

Factors Affecting Statistical Technique Factors to be taken into concern before adopting statistical techniques as: a) The number of clients to whom it is appropriate since

Issues for finance leases, Issues for Finance Leases For the leases su...

Issues for Finance Leases For the leases such have been categorize as finance leases, a model uses to be checked for the following issues: (i) Check technique used to split

Objectivity - external auditor report, Objectivity - External Auditor Repor...

Objectivity - External Auditor Report Many accounting figures are subjective and contain substantial terms of subjective judgment.  Many more business transactions have financ

I dont understand, Ask qub) How might financial incentives in the form of c...

Ask qub) How might financial incentives in the form of client services unconsciously introduce auditor bias into the independent audit function? Give some specific real-life exampl

Relevance, Relevance The auditor obtains evidence either through compli...

Relevance The auditor obtains evidence either through compliance testing of the internal controls or through substantive tests of the information contained in the financial sta

COBIT, Analyse the ratios in conjunction with the additional information an...

Analyse the ratios in conjunction with the additional information and identify from your analysis, implications for the audit and any particular audit steps that need to be underta

A test for unrecorded liabilities, should your test for unrecorded liabilit...

should your test for unrecorded liabilities be affected by the fact that a letter is obtained in which a responsible management official certifies that to the test of his knowledge

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd