Show method of greasing, Civil Engineering

Assignment Help:

Method of Greasing : Greasing of fixed end requires 20 to 25 minutes. The lifting is hardly 10 mm, ensuring that the gap is created between saddle block and knuckle pin. Saddle is not lifted above collar to prevent lateral creep of the girder. Steel scraper is used to remove old grease, dust and dirt. The contact area is cleaned with oil. Grease is applied and then girder is lowered back.

Greasing of free end requires 45 to 50 minutes. Knuckle plate is tied to the saddle plate with wire rope having turn buckle arrangement to release the load from roller when the girder is lifted. When the girder is lifted about 10 mm and rollers are free, link plate and tooth bar are removed after opening the stud connections. All rollers should be taken out and cleaned with scraper and these are sand-papered with a fine sand-paper of zero grade. Rollers should be examined for any possible signs of flattening or minute cracks with a magnifying glass. Grease graphite grade 3 conforming to IS 508 is applied over the base plate evenly below the roller contact area. The rollers are then placed in position and grease applied at the top contact surface. Link plate and tooth bars are connected with care so that tooth bar is placed in the same inclination as per the drawing.

With the help of turn buckle of wire rope sling, the knuckle plate is lowered over the rollers. This will create gap between the saddle block and knuckle plate. Cleaning and greasing of this area is then carried out similar to the fixed end and girder is lowered back.


Related Discussions:- Show method of greasing

LEVELLING, WHAT IS FLYBBACK LEVELLING

WHAT IS FLYBBACK LEVELLING

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Explain the surface water treatment methods, Explain the Surface Water Trea...

Explain the Surface Water Treatment Methods A. Physical Unit Operations change in water quality is brought about through the application of physical forces screenin

Design of steel structure, design acolumn spice for column sections SC 250 ...

design acolumn spice for column sections SC 250 and SC 220 carrying a load of 500 KN

Aluminium sliding window detail drawings, what are the details of aluminium...

what are the details of aluminium sections and how are they connected for making a door or window

Concrete, What practical steps can one take to mitigate the adverse effects...

What practical steps can one take to mitigate the adverse effects in using aggregates with higher than specified flakiness index in the production of concrete

Aggregate value, how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

how to calibrate AGGREGATE IMPACT VALUE TESTING MACHINE

Water transportation, Water Transportation: Water transport, in its va...

Water Transportation: Water transport, in its various forms, is one of the most efficient forms of transport, because of low fuel consumption, low environmental pollution and

Main problems related with prestressed concrete piles, Question What ar...

Question What are main problems related with prestressed concrete piles ? Answer Origin of Daido piles comes from Japan where these prestressed actual piles are used

Survey, how to draw longitudinal profile

how to draw longitudinal profile

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd